Forwards QA Program Insp Rept 99900519/82-02 on 820517-21 & Notice of Nonconformance
ML20058G904
Person / Time
Issue date: 07/06/1982
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Komes J
BECHTEL GROUP, INC.
Shared Package
ML20058G909 List:
References
REF-QA-99900519 NUDOCS 8208030445
Download: ML20058G904 (3)


Text

.

Docket No. 99900519/82-03 3R.06 M2 Bechtel Power Corporation Gaithersburg Power Division ATTN:

Mr. J. M. Komes, Vice President and General Manager 15740 Shady Grove Road Gaithersburg, MD 20760 Gentlemen:

This refers to the inspection conducted by Mr. J. R. Costello of this office on May 17-21, 1982, of your facility at Gaithersburg, Maryland, and to the discussions of our findings with Mr. D. C. Kansal and members of your staff at the conclusion of the inspection.

Areas examined during this inspection and our findings are discussed in the enclosed report.

Within these areas, the inspection consisted of an examina-tion of procedures and representative records, interviews with personnel, and observations by the inspector.

During this inspection it was found that you failed to meet certain NRC requirements.

The specific findings and references to the pertinent require-ments are identified in the enclosures to this letter.

Please provide us within 30 days from the date of this letter a written state-ment containing: (1) a description of steps that have been or will be taken to correct this item; (2) a description of steps that have been or will be taken to prevent recurrence; and (3) the dates your corrective actions and pre-ventive measures were or will be completed.

Consideration may be given to extending your response time for good cause shown.

The response requested by this letter is not subject to the clearance pro-cedures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

08 6

arest sc:est e eC vPe o:1Es v 7-1.

JRCostello/rf CJHale UPotap EHJohnson J

llins

/5///82 6/25/82 6g/82 6/p[82

%y/t/82\\9

B208030445 820706 PDR GA999 EECDECH 99900519 PDR

Bechtel Power Corporation In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

If this report contains any information that you believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary that you (a) notify this office by telephone within 10 days from the date of this letter of your intention to file a request for withholding; and (b) submit within 25 days from the date of this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than 7 days are available for your review, please notify this office promptly so that a new due date may be established.

Consistent with Section 2.790(b)(1), any such application must be accompanied by an affidavit executed by the owner of the information which identifies the document or part sought to be withheld, and which contains a full statement of the reasons on the basis which it is claimed that the-information should be withheld from public disclosure.

This section further requires the statement to address with specificity the considerations listed in 10 CFR 2.790(b)(4).

The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the specified periods noted above, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, Uldis Potapovs, Chief Vendor Programs Branch

Enclosures:

1.

Appendix A - Notice of Nonconformance 2.

Appendix 8 - Inspection Report No. 99900519/82-02 3.

Appendix C - Inspection Data Sheets (9 pages)