Requests Addl Info Re Cork Seam Contamination as Result of 790328 Accident
ML20058F023
Person / Time
Site: Crane Constellation icon.png
Issue date: 11/23/1993
From: Masnik M
Office of Nuclear Reactor Regulation
To: Long R
GENERAL PUBLIC UTILITIES CORP.
References
TAC-M69115, NUDOCS 9312070283
Download: ML20058F023 (4)


Text

m o

Dockel No. 50-320 November 23, 1993

'3r. Robert L. Long j

Director, Corporate Services /

)

Director, IMI-2 i

GPU Nuclear Corporation 1

P.O. Box 480 s

Middletown, Pennsylvania 17057-0191

Dear Dr. Long:

l

SUBJECT:

THREE MILE ISLAND CORK SEAM (TAC NO. M69115 - REQUEST FOR ADDITIONAL INFORMATION) l The staf f has reviewed GPU Nuclear Corporation (GPUN) letter (C312-93-2074) dated November 12, 1993.

The letter provides preliminary information regarding the Three Mile Island Unit 2 (TMI-2) cork seam that was contaminated as a result of the March 28, 1979 accident.

The staff has identified the need for additional information, particularly with regard to GPUN activities to accurately characterize the contamination. Also, the staff needs details on the plans for removing the contaminated water and eliminating future water intrusion into the TMI-2 buildings that contain the contaminated cork seam.

The enclosure contains the specific request for information.

The staff requests a response to our request for additional information by December 10, 1993, so as to not adversely impact the schedule for the approval for the Post Defueling Monitored Storage License Amendment.

This request affects nine or fewer respondents and, therefore, is not subject to Office of Management and Budget review under Public Law 96-511.

If you i

have any questions regarding this review, please contact me at (301) 504-1191.

Sincerely, i

Original signed by:

l Michael T. Masnik, Senior Project Manager Non-Power Reactors and Decommissioning 1

Project Directorate _.

Division of Operating Reactor Support Office of Nuclear Reactor Regulation

Enclosure:

Request for Additional Information on the Cork Seam cc w/ enclosure:

See next page j

DISTRIBUTI@:

Docket file 50-320 EHylton

.[

NRC PDRs MMasnik t

ONDD r/f OGC (15-B-18)

F, Grimes gj20 g

(

}

)

20 RDudley P

PDR egion I JSharkey JAustin (5-E-4) i

  • See previous concuri ONDD:LA*

.. 00: PM

  • ONDD:(A)SC#

ONDD:(A)D, EHylton MMasnik:dmj JSharkey RDudley

%jy i

11/23/93 11/ 23 93 11/23/93 11/23/93 L

/

B3tC BLE CENTiB COPY

,i:

-69115.MM (TMI #3 DISK)

cdr acc %,

l o

i j

4 UNITED STATES
  • i'

%gggf f [E NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 0001

%g w November 23, 1993

  • ...f Docket No. 50-320 Dr. Robert L. Long Director, Corporate Services /

Director, 1MI-2 GPU Nuclear Corporation P.O. Box 480 Middletown, Pennsylvania 17057-0191

Dear Dr. Long:

SUBJECT:

THREE MILE ISLAND CORK SEAM (TAC NO. M69115 - REQUEST FOR ADDITIONAL INFORMATION)

The staff has reviewed GPU Nuclear Corporation (GPUN) letter (C312-93-2074) dated November 12, 1993.

The letter provides preliminary information regarding the Three Mile Island Unit 2 (TMI-2) cork seam that was contaminated as a result of the March 28, 1979 accident. The staff has identified the need for additional information, particularly with regard to GPUN activities to accurately characterize the contamination. Also, the staff needs details on the plans for removing the contaminated water and eliminating future water intrusion into the TMI-2 buildings that contain the contaminated cork seam.

The enclosure contains the specific request for information.

The staff requests a response to our request for additicnal information by December 10, 1993, so as to not adversely impact the schedule for'the approval for the Pott Defueling Monitored Storage License Amendment.

This request affects nine or fewer respondents and, therefore, is not subject to Office of Management and Budget review under Public Law 96-511.

If you have any questions regarding this review, please co' tact me at (301) 504-1191.

Sincerely, hk Michael T. Masnik, Senior Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Operating Reactor Support Office of Nuclear Reactor Regulation

Enclosure:

Request for Additional Information on the Cork Seam cc w/ enclosure:

See next page e

f

a.

6 '

l ENCLOSURE l

(

REQUEST FOR ADDITIONAL INFORMATION CORK SEAM CONTAMINATION l

1 1.

Will the licensee commit to updating the appropriate section of the Post _

~

Defueling Monitored Storage (PDMS) Safety Evaluation Report (SER) with the cork seam information in the next PDMS SER revision? Provide a short description of the type of information that will be included in the revision.

^

2.

Provide a description of actions that have been taken or are being taken to prevent further inleakage into the cork se m.

For each action provide an estimated completion date.

3.

Provide an estimate of the amount of water and radioactive contamination in the cork seam.

4.

Describe plans for removing the radioactively contaminated water from the cork seam.

Include an estimated completion date.

5.

Describe your monitoring program to monitor water level and contamination containment in the cork seam once the facility enters PDMS.

I T

l i

i R

3

Dr. R. L. Long Three Mile Island Nuclear Station GPU Nuclear Corporation Unit No. 2 Docket No. 50-320 cc:

I Regional Administrator, Region I Mr. Robert Rogan i

U.S. Nuclear Regulatory Commission GPU Nuclear Corporation 475 Allendale Road P. O. Box 480 i

King of Prussia, Pennsylvania 19406 Mitdietown, Pennsylvania 17057' 1

Dr. Judith H. Johnsrud Mr. David J. McGoff Environmental Coalition on Nuclear Office of LWR Safety and Technology l

Power NE-23 i

433 Orlando Avenue U.S. Department of Energy State College, Pennsylvania 16801 Washington, D.C.

20545 l

Ernest L. Blake, Jr., Esq.

Mr. Wythe Keever Shaw, Pittman, Potts, and Trowbridge The Patriot 2300 N Street, N.W.

812 Market Street i

Washington, D.C.

20037 Harrisburg, Penr.sylvania 17105 i

Secretary Mr. Robert B. Borsum j

U.S. Nuclear Regulatory Commission B & W Nuclear Technologies Washington, D.C.

20555 Suite 525 i

1700 Rockville Pike Mr. Russell Schaeffer, Chairperson Rockville, Maryland 20852 Dauphin County Board of Commissioners Dauphin County Courthouse Mr. Marvin I. Lewis r

Front and Market Streets 7801 Roosevelt Blvd. #62 Harrisburg, Pennsylvania 17120 Philadelphia, Pennsylvania 19152 l

William Dornsife, Acting Director Mr. Jane Lee i

Bureau of Radiation Protection 183 Valley Road i

Department of Environmental Resources Etters, Pennsylvania 17319 P. O. Box 2063 Harrisburg, Pennsylvania 17120 Mr. Walter W. Cohen, Consumer i

Advocate Mr. Ad Crable Department of Justice i'

Lancaster New Era Strawberry Square,14th Floor 8 West King Street Harrisburg, Pennsylvania 17127 Lancaster, Pennsylvania 17601 U.S. Environmental Prot. Agency Ms. Michele G. Evans Regien 111 Office Senior Resident Inspector (TMI-1)

ATTN:

EIS Coordinator U.S. Nuclear Regulatory Commission 841 Chestnut Street P. O. Box 311 Pniladelphia, Pennsylvania 19107 Middletown, Pennsylvania 17057 Mr. Eric Epstein l

2308 Brandywine Drive Harrisburg, Pennsylvania 17110 a

.