Forwards Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted
ML20058D896
Person / Time
Site: Pilgrim
Issue date: 11/24/1993
From: Linville J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Boulette E
BOSTON EDISON CO.
Shared Package
ML20058D898 List:
References
NUDOCS 9312060085
Download: ML20058D896 (3)


See also: IR 05000293/1993019

Text

- _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - -

.-

. .

.

.

NOV 2 4 l993

Docket No. 50-293

Mr. E. Thomas Boulette, PhD

Senior Vice President - Nuclear

Boston Edison Company

Pilgrim Nuclear Power Station

Rocky Hill Road

Plymouth, Massachusetts 02360

Dear Mr. Boulette:

SUBJECT: PILGRIM INSPECTION 93-19

This refers to the safety inspection conducted by Messrs. J. Macdonald, A. Cerne, and D. Kern,

of this of6ce on September 28 to November 1,1993 at the Pilgrim Nuclear Power Station,

Plymouth, Massachusetts. Areas relevant to the health and safety of the public examined during

this inspection are described in the enclosed report. Our 6ndings were based upon observations

of performance and independent evaluations of safety systems and quality records.

The

preliminary results have been discussed with Mr J. Bellefeuille and other members of your staff

at the conclusion of the inspection.

Your Engineering Department demonstrated initiative and sound technical judgement in

questioning existing industry guidance during a motor operated valve (MOV) design review.

Subsequent identification of an inoperable safety-related MOV and associated corrective actions

were completed in a timely manner.

1

No reply to this report is necessary, and your cooperation with us is appreciated,

j

j

Sincerely,

0:4fd Cigned By:

hmn C. Unville

James Linville, Chief

Projects Branch No. 3

Division of Reactor Projects

I

Enclosure: NRC Inspection Report No. 93-19

020000

!

9312060085 931124

PDR

ADOCK 05000293

Q

PDR

III

.

..

. _ _ -

-

.

_

.

..

..

.

.

.

..

.

.

NOV 2 41993

Mr. E. Thomas Boulette, PhD

2

ec w/ encl:

E. Kraft, Vice President, Nuclear Operations and Station Director

.'

L. Schmeling, Plant Department Manager

V. Oheim, Manager, Regulatory Affairs and Emergency Planning Department

l

D. Tarantino, Nuclear Information Manager

N. Desmond, Compliance Division Manager

R. Hallisey, Department of Public Health, Commonwealth of Massachusetts

r

R. Adams, Department of Labor and Industries, Commonwealth of Massachusetts

l

The Honorable Edward M. Kennedy

j

The Honorable John F. Kerry

,

The Honorable Edward J. Markey

'!

The Honorable Terese Murray

{

'

The Honorable Peter V. Forman

B. Abbanat, Department of Public Utilities

f

Chairman, Plymouth Iloard of Selectmen

Chairman, Duxbury lloard of Selectmen

l

Plymouth Civil Defense Director

,

Paul W. Gromer, Massachusetts Secretary of Energy Resources

!

Sarah Woodhouse, Legislative Assistant

j

A. Nogee, M ASSPIRG

Regional Administrator, FEMA

l

Office of the Commissioner, Massachusetts Department of Environmental Quality

'

Engineering

Office of the Attorney General, Commonwealth of Massachusetts

,

T. Rapone, Massachusetts Executive Office of Public Safety

Chairman, Citizens Urging Responsible Energy

'

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

K. Abraham, PAO (2 copies)

NRC Resident Inspector

,

!

Commonwealth of Massachusetts, SLO Designee

!

!

.

-

_ . . , _ _

, _ _ _ _

.

,

-

j

-

.

.

.

,

.

'

Mr. E. Thomas Boulette, PhD

3

bec w/ encl:

Region I Docket Room (with concurrences)

E. Kelly, DRP

J. Shedlosky, DRP

M. Oprendek, DRP

bec w/enci (VIA FA1 AIL):

i

W. Butler, NRR

R. Eaton, NRR

W. Dean, OEDO

i

,

'

,

i

l

l

i

RI:DRP

R DRP

RI:D

i

s

Macdonald/meo

Kely

le

~

gf@3

11/18/93

t( Q

j

OFFICIAL RECORD COPY

A:PIL9319.MEO

f

l

,