ML20058A727

From kanterella
Jump to navigation Jump to search
Insp Repts 50-313/93-31 & 50-368/93-31 on 931021-25. Violations Noted.Major Areas Inspected:Evaluation of Circumstances Re Deficiency in Reactor Bldg Sumps
ML20058A727
Person / Time
Site: Arkansas Nuclear  
Issue date: 11/16/1993
From: Stetka T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20058A723 List:
References
50-313-93-31, 50-368-93-31, GL-85-22, IEB-93-002, IEB-93-2, IEIN-88-028, IEIN-88-28, IEIN-89-077, IEIN-89-77, IEIN-90-007, IEIN-90-7, IEIN-92-071, IEIN-92-71, IEIN-93-034, IEIN-93-34, NUDOCS 9312010205
Download: ML20058A727 (9)


See also: IR 05000313/1993031

Text

_

9

i

APPENDIX

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

i

Inspection Report:

50-313/93-31

50-368/93-31

,

Licenses:

DPR-51

NPF-6

-

t

Licensee:

Entergy Operations, Inc.

Route 3, Box 137G

i

Russellville, Arkansas

facility Name: Arkansas Nuclear One, Units 1 and 2 (ANO-1 and ANO-2)

Inspection At: Russellville, Arkansas

,

L

Inspection Conducted: October 21-25, 1993

l

Inspectors:

R. Azua, Resident Inspector

.,

L. Smith, Resident Inspector

l

,

JCCN

p //(,f93

Approved:

-e

-

Thomas F. Stetha, Chief, Project Section D

Date ~

Inspection Summar_y

Areas Inspected (ANO-1 and -2): This special inspection was performed to

evaluate the circumstances concerning deficiencies discovered by the licensee

in the reactor building sumps for ANO-1 and -2.

Results (ANO-1 and -2):

One apparent violation involving three examples was identified:

(1)

The reactor building sump for ANO-1 was found.to have several

unscreened penetrations which were not reflected on installation

instructions and procedures and, therefore, not in accordance with

the facility design basis (Section 1.1).

(2)

The licensee failed to correctly translate the design basis

requirements for the ANO-1 reactor building-sump, when scupper

holes were added to design drawings during plant construction

without appropriate screening (Section 1.1).

9312010205 931116

PDR

ADOCK 05000313

G

PDR

- - _ __ _ - - _______

__

..

-2-

(3)

The reactor building sump for ANO-2 was found to have several

'

unscreened penetrations in the lower structural support which were

not reflected on installation instructions and procedures and,

,

therefore, not in accordance with the facility design basis

(Section 1.1).

Failure to identify tears in the screen mesh during sump cleaniness.

inspections is considered to be a weakness (Section 1.1).

Identification of penetrations in the ANO-2 reactor building sump while

the plant was at power resulted in the licensee requestint enforcement

discretion from the' requirements of Technical Specification 3.0.3 in

order to remain at power while repairs were being effected. The NRC

granted this request on October 22, 1993 (Section 1.1).

The licensee's Information Notice evaluations were focused on sump

debris cleaniness and, as a result, did not identify the reactor

building sump screen deficiencies (Section 1.2).

On October 25, 1993,

,

the licensee made a commitment to review a select sample of previous

Information Notices and other industry notification evaluations. This

effort will be performed to determine the quality of other notification

evaluations (Section 1.2).

1

Summar_y of Inspection Findings:

Apparent Violation 313/368/9331-01 was opened (Section 1.1)

Attachments:

Attachment - Persons Contacted and Exit Meeting

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

4

i

.

-3-

DETAILS

1 ONSITE RESPONSE TO EVENTS (93702)

1.1 Reactor Buildina Sump Desian Basis Deficiencies

On October 1,1993, with ANO-1 station in Refueling Outage IRll, licensee

,

personnel noted an apparent inadequacy with the reactor building sump screens.

The procedure to perform a calibration of the reactor building sump level-

instrumentation required that the integrity of the grouting, where the cabling

passes through the sump curb, be verified. During this verification, it was

noted that the conduit opening needed to be regrouted.

Licensee personnel

questioned why this regrouting was necessary considering that there were other

openings already existing in the curb. System engineering was notified of the

existence of these other openings. System engineering conducted a review of

the sump conditions and, as a result, identified the following penetrations

that did not conform to requirements:

Twenty-two (22) 6-inch diameter by 3-inch high semicircular holes, or

scuppers. These scuppers were constructed of 6-inch diameter pipe that

was split and imbedded in the sump curb at the reactor building floor

elevation. These scuppers were not screened.

Four (4) conduit / pipe penetrations into the sump which were not

'

,

adequately screened.

Two of the penetrations were in the horizontal

portion of the sump screen where a conduit and pipe penetrated the sump

screen. The north face of the sump had a single opening penetrated by

two conduits.

The sump access panel on the east end of the sump also

had a single opening penetrated by two conduits.

'

An approximately 1-inch conduit penetration in the west end of the sump

curb was not completely grouted nor screened to prevent debris from

entering the sump. The penetration was below the sump screen framework

'

and in the top of the sump curb.

Licensee system engineering identified that the penetrations did not conform

with the requirements for the reactor building sump screens as described in

,

the ANO-1 safety analysis report, and the unit's design basis Upper Level

Document ULD-1-SYS-04, which stated that the purpose of the sump screens was

to prevent the passage into the sump of any debris larger than the sump screen

mesh size of 0.132 inch by 0.132 inch. The failure by the licensee to

correctly translate the design basis requirements, as set forth in the ANO-1

safety analysis report, to the installed configuration, is considered to be an

apparent violation 10 CFR Part 50, Appendix B, Criterion III

(313/368/9331-01).

.

f

-

_

.

,

-4-

In addition to these design problems, the licensee identified two defects,

i

which appeared to be tears in the screen mesh covering the sump and some

debris in the sump.

One defect was located in the screen mesh on the sump

access panel at the east end of the sump (a 90 angle tear approximately

12 inches by 1 inch on the vertical and 14 inches by 1 inch on the

horizontal).

The other defect was located in the horizontal portion of the

sump screen at the south side of the sump (approximately a 12-inch by 1-inch

tear). The debris consisted of small amounts of duct tape and concrete dust

'

and gravel.

The licensee attributed this debris to ongoing cutage activities.

'

As a result of these findings, the licensee initiated Condition

l

Report CR-1-93-0390. The licensee stated that, although the sump screens were

in nonconformance with the design basis, the determination as to whether the

reactor building sump was operable or inoperable could not be adequately

determined without an engineering evaluation.

Based on the fact that ANO-1

was shut down for an outage, there was no immediate operability concern, thus

the reactor building sump was declared operable for the existing plant

j

conditions. As a result of this initial operability determination, in

accordance with the reportability guidance in the licensee's Administrative

Procedure 1000.104, Revision 10, " Condition Reporting and Corrective Actions,"

the licensee concluded that a report to the NRC was not required.

At the time of the issuance of the condition report, the licensee was

concerned with the status of the ANO-2 reactor building sump screens, since

ANO-2 was at full power operation. The licensee reviewed the as-built

drawings of the ANO-2 sump screens to determine if scupper holes, or any other

penetrations that might bypass the sump screens, were present. The licensee

also reviewed the pictures from the plant surrogate tour system to verify if

any conduits or pipes penetrated through the screens.

In addition, they

verified that no apparent tears in the screen mesh were visible. The licensee

also made a determination that the angle of the pictures provided sufficient

view of the sump screen base to corroborate their conclusion that no scupper

holes existed.

Finally, the licensee reviewed previous postoutage/preheatup

containment building visual inspection documentation to determine if any

anomalies had been previously noted.

None were identified.

Based on this

review, the licensee believed that the conditions affecting the ANO-1 reactor

building sump screens did not similarly affect ANO-2.

The licensee continued to review the issue concerning the operability status

of the ANO-1 reactor building sump in an effort to correct the identified

deficiencies prior to plant startup.

In accordance with Procedure 1000.104, a

corrective action plan review was required within 14 days of the initiation of

the condition report. The licensee had set a goal to have a final operability

determination completed within this 14-day period. The licensee's reviews

included a review of the debris transport calculations that would help

determine the amount of debris the sump screens would be subjected to in the

event of a loss-of-coolant accident.

In addition, the licensee was reviewing

other plant drawings and touring the reactor building to determine if other

_____

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

___

-5-

drainage mechanisms existed that could adversely affect the sump. Finally,

the licensee was developing the corrective action plan to address the

deficiencies.

While reviewing Drawing C-172, " Reactor Building Concrete Details-Sheet 2,"

the licensee noted that, although the drawing indicated the presence of the

scupper holes in question, it did not provide any indication that they needed

to be screened.

The presence of these holes on the drawing, without any

specifications that they be screened, was a failure by the licensee to

correctly translate the design basis requirements for the reactor building

sump screens into drawings.

This is another example of violation

(313/368/9331-01).

During the review of the ANO-1 reactor building drainage system, the licensee

identified that the reactor building drain headers, which empty into the sump,

were unscreened and provided several additional potential paths for debris

intrusion into the sump.

These paths included six 10-inch floor drains at

various elevations, the 2-inch drain line under the reactor cavity, several

open funnels at upper elevations which catch drainage from various equipment,

and 2-inch open drains under the rails of the refueling machine.

The licensee

included these findings in the corrective action plan being developed.

The licensee did not believe that the problems identified in the ANO-1 reactor

building drainage system were present in ANO-2.

This belief was based on the

knowledge that ANO-2 was a more recent design and, due to the fact that ANO-2

was of a different design, had different drain covers and screens in the

drains, as corroborated by a cursory review of some of the design

documentation.

On October 11, 1993, the licensee completed the repairs and modificationc on

the Unit I reactor building sump screens, curbs, and drains.

As of October 14, 1993, a final operability determination had not been made by

the engineering staff. The licensee made the decision to declare that the

reactor building sump had been inoperable due to the probability, based on the

engineering evaluation conducted to date, that the low pressure injection

system would be adversely affected due to debris migrating into the reactor

building sump following a large break loss-of-coolant accident. As the result

of this decision, a report was made to the NRC in accordance with the

requirements of 10 CFR 50.72.

To completely ensure AND-1 reactor building sump integrity, the licensee

conducted subsequent walkdowns between October 12 and 18. As the result of

these walkdowns, additional findings, which included small holes and tears in

the sump screens, and sump frame bolting deficiencies were identified.

The

licensee took action to correct these conditions.

On October 22, the licensee determined that the ANO-1 reactor building sump

had been inoperable prior to the last refueling outage.

This conclusion was

based on calculations which determined that the least amount of volume of

l

-

_ _ --- _ ----

)

.

.

_

-6-

insulation required to significantly degrade flow to the decay heat removal

outlet valves and restrict low pressure injection flow was calculated to be

. 5-1.0 f t'.

An assessment of the transport calculations for insulation that

could be postulated to break free following 'a large break loss-of-coolant

accident, indicated that approximately 15 ft of insulation could have entered

the sump.

On October 18, 1993, the licensee decided to perform a more in-depth review of -

the design documentation of the ANO-2 reactor building drainage system.

By

October 21, 1993, the licensee had identified that all but three drains in the

reactor building had the appropriate sized screens, as set forth in the design

basis requirements. The licensee was unable to confirm the presence of

screens for these remaining three drains.

In addition, the licensee

determined that two of these three drains were inaccessible while the plant

was operating at power.

Therefore, the licensee began fabricating screens for

installation on the ends of the piping from the drains in question where they

entered the sump.

Based on the uncertainty resulting from the lack of supporting data, the

licensee made the decision to make an ANO-2 reactor building entry while at

power.

The purpose of this entry was to inspect the ends of the piping from

the drains in question for the new screen installation, to inspect a random

sample of the other reactor building drains (to verify the accuracy of the

design documentation), and to perform an inspection of the reactor building

sump and sump screens.

On October 22, the licensee made the decision to convene the AN0-2

safety review committee to draft Continued Safe Operation

Determination CS0-93-02. The purpose of this document would be to provide the

basis for an Enforcement Discretion Request in the event that during the tour

of the sump a condition, that would cause the sump to be declared inoperable,

was identified and had to be corrected.

On October 22, members of the licensee staff entered the reactor building

accompanied by the inspector. The drains inspected were all found to be

properly screened during the tour of the reactor building. When inspecting

l

the reactor building sump screens, the licensee identified seven penetrations

through the grout at the base of the sump screen assembly, which were

~

unscreened and, therefore, could bypass the sump screens.

In addition, the

licensee identified a flashlight within the sump structure.

The dimensions of each penetration were approximately 1 inch high by 3 inches

in length. These penetrations made the sump design contrary to the design

requirements set forth in the ANO-2 safety analysis report and design basis

i

Upper Level Document ULD-2-SYS-04, which stated that the purpose of the sump

screens was to prevent the introduction of any debris into the reactor

building sump which was larger than would be allowed to pass through the .09-

inch by .09-inch sump mesh screen.

These holes in the grout did not appear on

any of the design drawing instructions or installation procedures. This

failure by the licensee to correctly translate the design basis set forth in

..

.

. - _ _ _

_ _ _ _ _ _ _

.

_

-

-

.

.

.

.

F

-7-

,

the safety analysis report into installation instructions and procedures is

,

another example of violation (313/368/9331-01).

As a result of this finding, the licensee declared the ANO-2 s"mp inoperable

.

and placed ANO-2 in Technical Specification Action Statement 3.0.3.

This

!

'

action statement required the licensee to correct the deficiency within I hour

or begin plant shutdown so that the plant was in hot standby within the next

,

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and cold shutdown in the following 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />. The licensee then

!

submitted their request for enforcement discretion, CS0-93-02, to the NRC to

allow the licensee to continue operation for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> while they repaired the

sump screens. The NRC reviewed the licensee's submittal and

granted enforcement discretion at 8:13 p.m. on October 22, 1993.

'

On October 23, at approximately 3:30 a.m., the licensee completed the sump

screen required modifications and exited Technical Specification 3.0.3

approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> after they had entered it.

l

The licensee planned on completing their operability determination of the as-

found condition of the ANO-2 sump by November 5, 1993.

In addition, the

licensee evaluated the affect of the flashlight found in the sump and

..t

determined that it did not pose a clogging threat due to the existence of

vortex breaking screens locrted on the end of suction piping.

i

1.2 Generic Communications Response

i

The inspector conducted a review of the licensee's actions with respect to

previous notifications regarding reactor building sumps that the NRC had

issued to the industry.

The NRC had issued several information notices

(IN's 88-28, 89-77, 90-07, 92-71, and 93-34), a generic letter (GL 85-22), and

a bulletin (NRC Bulletin 93-02), addressing reactor building sumps, sump

screen design, and the different types of material that could become debris

and obstruct the screens during the design basis accident.

.

The main topic of most of these notices pertained to insulation materials and

the potential for these materials to block the sump screens in the event of

the design basis accident.

It appeared that the licensee's focus was

concentrated mainly on the debris concerns and not on screen design, screen.

integrity, or screen configuration.

This became evident in the licensee's

response to Information Notice 89-77, " Debris in Containment Emergency Sumps

and Incorrect Screen Configuration." The information notice identified

deficiencies in the sumps of three operating facilities, which included

designs not in accordance with plant drawings, missing screens, and gaps in

the screens which resulted in the introduction of debris'large enough to have

caused pump damage or flow degradation.

In response to this notice, the

licensee implemented a procedural change on August 6, 1990, to the ANO-1

precriticality checklist to require the inspection of sumps, sump area, and

grating for debris that may have the potential for screen inlet blockage.

Since ANO-2 already had a precriticality checklist requirement to inspect the~

sump for debris and screen integrity, no recommendations were made. The

licensee's review of the information notice did not include the need for a

-

-

-

. - -

-.

.

._

.

.

.

_

.

. _ _

.

'

.

-8-

plant specific walkdown of the sumps to address the screen integrity and

]

configuration problems identified in the information notice.

)

'The inspector discussed the finding regarding the adequacy of generic

communication followup with the licensee. As a result of these discussions,

the licensee committed to review a selected sample.of previous Information

Notices and other industry information evaluations back to 1988 to assure that

these communications were properly reviewed and resolved. The licensee stated -

that, if significant discrepancies are identified during this review, the

scope of the review would be increased.

i

1.3 Conclusions

Upon discovery of the reactor building sump deficiencies the licensee took

prompt and effective corrective actions, which involved thorough engineering

evaluations. The failure to insure that the reactor building sump designs

were in accordance.with-the design basis requirements, specified in the safety

'

analysis reports, was considered to be a violation. The licensee's failure to

- I

conduct a complete and thorough review of previous industry notifications

regarding sump screen integrity and configuration is considered to be a

3

j

weakness.

.

.

,

i

!

,

,

,

' ~ '

"-

-

.,,

_,y.

.

.

..

-

-

i

ATTACHMENT 1

1 PERSONS CONTACTED

,

1.1 Licensee Personnel

  • C. Anderson, Unit 2 Operations Manager
  • S. Bennett, Acting Licensing Supervisor
  • J. Barrett, Quality Control Supervisor

'

S. Boncheff, Licensing Specialist

  • M. Cooper, Licensing Specialist
  • W. Greeson, Mechanical, Civil and Structural Engineering Manager

i

  • R. Howerton, Engineering Support Manager
  • R. King, Acting Licensing Director
  • R. Lane, Design Engineering Director
  • D. Mims, Unit 2 System Engineering Manager
  • J. Taylor-Brown, Quality Control Supervisor
  • J. Vandergrift, Unit 1 Plant Manager
  • J. Yelverton, Vice President Operations
  • Denotes personnel that attended the exit meeting.

In addition to the

personnel listed above, the inspectors contacted other personnel during this

i

inspection period.

2 EXIT MEETING

An exit meeting was conducted on October 25, 1993.

During this meeting, the

inspectors reviewed the scope and findings of the report. The licensee

acknowledged the inspection findings and did not express a position on these

-

findings.

The licensee committed to review previous NRC and industry

communications to assure proper resolution as discussed in this report.

The

licensee did not identify as proprietary any information provided to, or

reviewed by, the inspectors.

i

!

!

!

!

!

,

l

,