NOTICE OF VIOLATION Centerior Service Company Docket No. 50-440 Perry Nuclear Power Plant License No. NPF-58 During an NRC inspection conducted on August 23-27, 1993, a violation of NRC requirements was identified.
In accordance with the " General Statement of Policy and Procedure for NRr Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed be'ow:
Technical Specification 3.7.7.1 states that at least three FHB ventilation exhaust subsystems shall be operable when irradiated fuel is being handled in the FHB.
Technical Specification 4.7.7.1.c., in part, requires that each of the three required Fuel Handling Building (FHB) ventilation exhaust subsystems be demonstrated operable after every 720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br /> of charcoal adsorber operation by verifying that a laboratory analysis of a representative carbon sample meets the laboratory testing criteria of Regulatory Position C.6.a of Regulatory Guide 1.52, Revision 2, March 1978.
Contrary to the above, on August 9, 1993, when irradiated fuel was being handled in the FHB, two of the three required FHB ventilation exhaust subsystems were not demonstrated operable after 720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br /> of charcoal adsorber operation by verifying that a laboratory analysis of a representative carbon sample met the laboratory testing criteria of Regulatory Position C.6.a of Regulatory Guide 1.52, Revision 2, March 1978.
This is a Severity Level IV violation (Supplement I).
Pursuant to the provisions of 10 CFR 2.201, Centerior Service Company is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATIN: Document Control Desk, Washington D.C. 20555 with a copy to the U. S. Nuclear Regulatory Commission, Region III, 799 Roosevelt Road, Glen Ellyn, Illinois, 60137, and a copy to the NRC Resident Inspector at the Cleveland Electric Illuminating Company, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This reply should be clearly marked as a " Reply to a Notice of Violation" and should include for each violation:
(1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.
If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be t.t ken. Where good cause is shown, consideration will be given to extending the response time.
h
'A Dated at Glen Ellyn, Illinois Wlliam Snell, Acting Chief
{
this:N day of September 1993 Reactor Support Programs Branch i
l 9310040148 930924 gDR ADOCK 05000440 I
.