GeneralElectnc Company 17b Cunnet Avenue, San Jose, CA 95125 September 17,1993 Docket No. STN 52-001 l
i h
Chet Posiusny, Senior Project Manager Standardization Project Directorate Associate Directorate for Advanced Reactors l
and License Renewal Office of the Noclear Reactor Regulation
Subject:
Submittal Supporting Accelerated ABWR Schedule - P&R Markups for Technical Specification Section 3.7
Dear Chet:
Enclosed are P&R markups for Section 3.7, Plant Systems, of the ABWR Technical Specifications. For convenience, a copy of the letter dated September 16,1993, transmitting revised LCO 3.7.1 and bases is also enclosed. The markups on LCO 3.7.6, Main Turbine Bypass Valves, is based on our earlier markups and reliability analysis transmitted by my May 19,1993 letter, a copy of which is also enclosed.
Please provide a copy of this transmittal to Mark Reinhart.
Sincerely, Y
Nek Fox Advanced Reactor Programs cc: