ML20056G065

From kanterella
Jump to navigation Jump to search
Submits Comments of on Project Interface Document 46, Rev 2 Re Review of Listed Interface Documents Sent Under 930610 Cover Ltr
ML20056G065
Person / Time
Issue date: 07/15/1993
From: Fliegel M
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Chernoff A
ENERGY, DEPT. OF
References
REF-WM-39 NUDOCS 9309010245
Download: ML20056G065 (3)


Text

,

o o

UNITED STATES

,g

!* (](h~

((

3 NUCLEAR REGULATORY COMMISSION f

WASHINGTON. D C 20555 0001 J

J'A 15 B33 Mr. Albert R. Chernoff, Project Manager Uranium Mill Tailings Remedial Action Projett Office U.S. De;artment of Energy l

Albuqilerque Operations Office i

P.O. Bok 5400 l

Albuquerque, New Mexico 87115 j

Dear Mr. Chernoff:

l i

We have reviewed the following Project Interface Documents (PID's) which were sent under cover letter dated June 10, 1993:

[

1.

05-S-46 (Rev. 2), dated March 11, 1993 - 00E Class I 2.

05-S-48, dated August E. 1992 - DOE Class II 3.

05-5-54, dated December 12, 1992 - DOE Class II l

4.

05-5-55, dated April 22, 1993 - DOE Class I 5.

05-S-56, dated April 2,1993 - DOE Class I l

PID 56, which concerned a reconfiguration of the tailings embankment top slope l

and addition of a transition layer, was previously submitted by the Department

~

of Energy (DOE) and concurred in by letter from our office dated May 27, 1993.

PID 54, which revises the processing site final grading plan, is appropriately i

identified as Class II and, therefore, requires no concurrence.

PID 55 proposes revised procedures for the burial of asbestos-contaminated material (ACM) and ACM stored in metal drums. We concur with PID 55, as submitted.

PID 48 proposes methods for the disposal of highly-contaminated oversize l

demolition material. We are prepared to concur with PID 48 if it-is reissued l

as Class I, and if the resubmittal includes guidelines for minimum lateral I

separation of crushed tanks. The minimum separation limits are desirable to assure that concentrations of non-soil buried matter can be bridged properly, thereby preventing excessive settlement and cover cracking above.

PID 46 (Revision 2) proposes elimination of requirements preventing material with a diameter greater than 6 inches within 100 feet of the embankment side slopes. Attachment A to this PID explains that the previously proposed radon barrier change in Revision 1, based on altered contaminated material sequencing, is no longer needed.

This reestablishes the original 2-foot radon barrier. We concur with the PID as proposed. However, our review noted Ij certain items in Attachment A that require clarification when the final RAECOM analysis is presented in the Completion Report. These concerns are discussed j

in the enclosure.

Oj y

i j' !

M +'

4J" S

9309010245 930715 7

PDR WASTE WM-39 Ppg g

l

w w

i Albert R. Chernoff -

If you have any questions regarding the above, please contact me at i

(301) 504-2155 or the Nuclear Regulatory Commission Project Manager, Mr. Daniel Rom at (301) 504-2573.

Sincerely, 1

OhlG!NAL S;GNED W Myron H. Fliegel, Acting Chief Uranium Recovery Branch Division of Low-level Waste Management and Decommissioning Office of Nuclear Material Safety and Safeguards

Enclosure:

As stated cc:

S. Hamp, DOE /AL C. Cormier, DOE DJSTRIFUTION: Central File #

NMSS r/f RBangart WBrach JAustin JSurmeier LLWM r/f RHall,URF0 LCallan,RIV SWastler TLJohnson EBrummett LHamdan EHarkLSmall[ Boxes"inTCo'n'currence; Blouclto Defitin Distrjtiytion C' pyj Prefsrence

~

o in small Box on "0FC:" line place a: C = Cover'~2 = Cover L'Enciosure N = No Copy LLUR({,

0FC :

LLUR E

LLUR E

E LLWM LLWM g

gg g, NAME:

DRom/eb DGillen MFliegel DATE:

7/t5/93 H

7/t5/93 H

7/l[/93 H

/ /

/ /

i S:\\LLWMTYPE\\EDIE\\GRJPIDs.DSR OFFICIAL RECORD COPY In small Box on "DATE:" line place a: M = E-Mail Distribution Copy H = Hard Copy PDR :

YES X

NO Category:

Proprietary or CF Only ACNW:

YES X

NO Delete file after distribution Yes No i

IG:

YES NO X

f o

o i

l NUCLEAR REGULATORY COMMISSION STAFF COMMENTS ON PID 46 REVISION 2

?

Attachment A to Project Interface Doucment (PID) 46, Revision 2, explains that the previously proposed change in Revision 1, based on altered contaminated L

material sequencing, is no longer needed. This is because the uppermost 10 feet of contaminated material will be icw-level vicinity property i

material, as ut iginally phnneri in the Remedial Action Plan (RAP). Therefore, the original design with a 2-foot-thick radon barrier layer is still adequate.

Attachment A, in part, provided information pertinent to the Nuclear Regulatory Commission staff's comments on the radon barrier design presented 1

n Revision 1.

Revision 2 no longer includes a revised radon barrier; therefore, this information does not require NRC review. However, it did i

include a RAECOM analysis with some revised input values. The following e

comments are provided for Department of Energy's (DOE's) consideration when l

preparing the final RAECOM analysis for the Completion Report:

1.

Apparently DOE has reversed the thickness values of the two contaminated material layers presented in the RAECOM analysis. Table 2 of Attachment A indicates that the remaining million cubic yards of contaminated material is low-level material (weighted average 32 pCi/g Ra-226).

The RAECOM analysis in Table 3 indicates that this material is the top layer and is 1220 cm (40 ft.) thick.

However, the in-place contaminated material (about 3-million cubic yards) is shown only as 305 cm (10 ft.) thick. This, of course, would result in a lower flux rate than if the low-level material was 10-feet thick.

I 2.

The deeper contaminated material layer has a moisture input value of i

1.7 percent.

In the RAP calculation, the deeper layer had a moisture content of 18 percent.

Even if this material was pure sand, had little moisture added, and had little cover, one could still expect at least 5 t

percent moisture content. Adequate justification for long-term moisture values will need to be provided in the Completion Report's analysis.

i The staff ran the RADON code, correcting these probable errors and using 2

calculated diffusion coefficients. The resulting radon flux was 6.6 pCi/m /s.

5 Using the avep/s.

age parameter values and their SEM, the flux was calculated to be 11.8 pCi/m The radon flux, based on the model in Table 3 of i

Attachment A, apparently will meet the Environmental Protection Agency standard; however, the Completion Report needs to provide sufficient data to i

substantiate the final RAECOM analysis and the radon barrier "as-built" design.

e i

Enclosure

~