ML20055A214

From kanterella
Jump to navigation Jump to search
Responds to NRC Requesting Addl Info to 811223 Response Re Violations Noted in IE Insp Repts 50-508/81-14 & 50-509/81-14.Difficulties in Testing Penetrations 23,24 & 44 Limited Due to Unique Design
ML20055A214
Person / Time
Site: Satsop
Issue date: 04/15/1982
From: Leddick R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Bishop J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML20055A199 List:
References
GO3-82-389, NUDOCS 8207150581
Download: ML20055A214 (5)


Text

..

._ h

m Washington Public Power Supply System 3

Box 1223 Elma, Washington 98541 (206)482-4428 T'

3 m

Docket Numbers 50-508 and 50-509 3

5

' 61 April 15, 1982 O

G03-82-389

=

U. S. Nuclear Regulatory Commission, Region V Office of Inspection and Enforcement 1450 Maria Lane, Suite 260 Walnut Creek, California 94596-5368 Attention:

Mr. T. W. Bishop Chief, Reactor Construction Projects Branch

Subject:

NRC INSPECTION AT WNP-3/5 IE REPORT N0. 50-508, 509/81-14 NONCOMPLIANCE (50-508, 509/81-14/01)

References:

1.

G03-81-2866, dated December 23, 1981, Mr. R. S.

Leddick to Mr. B. H. Faulkenbcrry, NRC Inspection at WNP-3/5.

2.

NRC Letter, dated February 22, 1982, Mr. B. H.

Faulkenberry to Mr. R. S. Leddick, same subject.

To complete the NRC evaluation of the corrective actions reported in Reference 1, your staff determined that additional information was re-quired. As a result, Reference 2 outlined NRC questions that had arisen and directed the Supply System to provide a response.

The Supply System approved response to NRC questions concerning the cor-rective actions taken for the subject violation (Failure to assure con-tainment penetrations, Nos. 23, 24 & 44, are tested in accordance with Code requirements) is as follows:

NRC Concern #1 Please explain how a 50 PSIG pressure decay test of the containment guard pipes can be conducted in accordance with NC-6129 without damag-ing the attached secondary bellows. Specification No. 3240-54, Paragraph 8.0liii indicates that the bellows assembly has been designed for a 5 PSI differential pressure.

Please explain also how the bellows will be re-strained to maintain the test pressure for the requisite time period.

Response to #1 The NRC has incorrectly stated the test pressure as being 50 psig. A pressure decay test for the guard pipe welds of these penetrations will be performed at 62.5 psig based on a design pressure of 50 psig.

The 8207150581 820708 PDRADOCK05000g G

U ~ 3I

.1

n

~

l Mr. T. W. Bishop Page 2 April 15, 1982 G03-82-389 Response to #1 (Continued) design pressure of the bellows is 5 psig. To test the guard pipe welds at 62.5 psig, the bellows must be protected from overpressurization.

This will be accomplished by attaching a shroud over the bellows assem-bly. This shroud will have a connection to it allowing it to be pressur-ized to 62.5 psig. A test apparatus will be constructed which will per-mit both the inside and the outside of the bellows to be simultaneously pressurized thus minimizing the a p across the bellow's plies to an acceptably low value. Control and measuring equipment will be provided to independently control the internal and external pressure of the bel-low's plies. Ebasco will provide technical review to assure that Con-tractor 224's procedure satisfactorily meets these requirements.

NRC Concern #2 Please explain why DCN-MN-128, dated June 10, 1981, specifies a design pressure of 200 PSIG for the penetration No. 44 process pipe whereas your response indicates that the line list has always specified 150 PSIG and the appropriate drawing was changed by a field change request on December 12, 1980. Our concern is directed toward the fact that certain design documents apparently still specify 200 PSIG, which would indicate inadequate implementation of your design control system.

Response to #2 To verify the correct design, including pressure, it is necessary to utilize the latest controlled reference drawing duly considering all outstanding (posted) design change documents. This is in accordance with the established Ebasco design control program. As previously ex-plained in Reference 1, the design pressure for line 2CH3-514SA/BR has always appeared as 150 psig in the line list. Drawing G-1300 sheet 1 revision 5 dated May 5, 1980 was revised by FCR-MN-153 dated December 12, 1980 from 200 psig to 150 psig so as to specify the correct design pressure as specified in the line list. DCN-MN-128, dated July 17, 1981, was also written against G-1300 sheet I revision 5.

This DCN was issued to revise the design pressures of the guard pipes for penetrations 23, 24, and 44. Although DCN-MN-128 was issued subsequent to FCR-MN-153, it does not show the change in design pressure of FCR-MN-153 because FCR-MN-153 had not been incorporated into the design drawing at the time l

DCN-MN-128 was issued.

Both the FCR and the DCN are in the process of being incorporated into the design drawing at the same time in revision 6.

The only valid design change information on DCN-MN-128, or any change document, is that which is circled as either being revised, added, or de-lete?.

i Mr. T. W. Bishop Page 3 April 15, 1982 G03-82-389 NRC Concern #3 In your response, under actions taken to prevent recurrence, you state that blockouts have been established and will be maintained for the guard pipe penetrations until successful completion of the 62.5 PSIG pneumatic tests. However, based on the following infornction, we ques-tion whether problems currently exist in the areas of vesign and pro-cedure review and contractor interface coordination which, if not ad-dressed and corrected, could result in the occurrence of similar items of noncompliance.

a.

The civil contractor, without concurrence of mechanical engineering, was released to place concrete inside the containment, including encasement of field weld No. 4.

It was not realized by the civil contractor that this blockout was intended to remain open.

b.

A DCN was issued on June 15, 1981, which stated that the inside containment guard pipe welds would be tested during the combined ILRT and overpressure test of the containment. This DCN did not recognizc that the ILRT would not satisfy construction code re-quirements.

c.

Testing requirements were apparently not considered in the design of the penetrations in question, in that 5 PSIG bellows were in-stalled that cannot be isolated for conduct of the 62.5 PSIG pres-sure tests.

d.

The DCN of June 10, 1981, specifies a design pressure of 200 PSIG for the penetration No. 44 process pipe, yet you state the design pressure should be 150 PSIG.

I Contractor procedures were reviewed and approved which specified e.

pneumatic versus the required hydrostatic tests.

f f.

There was no direction provided to the 251 contractor, by specifi-cation change or DCN allowing the use of the Winter, 1978 addenda provisions of NC-6129 for pressure decay testing nor does the 251 l

contractor's Certificate of Authorization extend to his code adden-da.

In consideration of the above, please inform us whether our concerns are valid and if so, what corrective measures you have taken to pre-i vent recurrence of similar items of noncompliance.

o

r 1

Mr. T. W. Bishop Page 4 April 15, 1982 G03-82-389 f,

Response to #3 Based on the information listed in item 3 of Reference 2, Ebasco Engi-neering does not agree that the NRC's concerns are valid witM regard to design, procedure review and contractor interface coordination.

Ebasco's position is based on the following:

3.1 Items 3a and 3e are isolated occurrences.

When disciplines other than civil are affected by a concrete paur, those disciplines are required to sign off on the concrete pour

/,

card prior to the operation being performed.

Since July 1981, there have been no other cases identified where the testing of mechanical components was impacted by civil activities.

+

As stated in Reference 1, the procedure requiring the use of a pneumatic pressure test where a hydrostatic test was required by ASME Code was incorrectly approved by Engineering. However, this cannot be expected to occur again as it was an isolated Engineering error on a procedure for testing three of approximately one hundred penetrations, the remainder of which are of different design which will be pressure tested in a different3mannir,than penetrations 23, 24, and 44.

3.2 With regard to item 3b, DCN-MN-128 did not establish that the combined ILRT and Overpressure Tests will satisfy construction code requirements for these penetrations.

It merely-recognized that the guard pipe welds were part of the containment vessel pressure boundary and as such would be qualified usir.g the ILRT as well as the ASME Code required internal pressure test.

DCN C h <

MN-128 did not, and could not, modify the use of the maddatory ASME Code test. To clarify Ebasco's design intent, DCN-MN-167 r"

l was issued deleting all mention of the combined ILRT anb0verpres/

l sure Test as this information is not required by the contractor T'e to perform his ASME pressure testing.

It must be emphasized with /

$j

/.

regard to the type of pressure testing specified, that both DCNs,

+

4 were issued to clarify these requirements.

They did not, change the scope of penetration testing required, whether done.by Ebasco

~

in the case of the l'9T, or the contractor in the case of the i i

ASME test.

1 G

3.3 With regard to item 3c, testing requirements were. considered in the design of these penetrations. As explained above, an

~ 1,

/

Engineer's approved test procedure will be used daring,penetra-t (6

h*a f

s.

p' 4

j s

i i.

L

.)

s

~

Mr. T.

W.' Bishop Page 5 April 15, 1982' G03-82-389 3.3 (Continued) tion testing to properly protect the bellows. These penetrations have been designed, and will be tested, in full compliance with the ASME Code.

y, 3.4 The clarification provided herein for item 3d, and the description of the corrective action for item 3f in Reference 1, should alle-viate any concern for these items.

,r

_ Sunnary 3.

a 1/ It must be emphasized that while difficulties have been encountered

~'

during th6, installation of these three penetrations, no pressure test-ing has been performed which is in violation of Ebasco procedures or applicable industry codes and standards. These difficulties are neither extractoinery,in degree nor indicative of a failure in Ebasco's program p

to offectively control design and contractor interface.

It must be 4

'/.

'N',}

reenO)2ed that t.iese installation problems are attributable to the unictiCdesign requirement of the Type IV and IVA penetrations. Their 4

desioh "and wpstruction differs considerably from all other containment

(

mech pical penetrations in that the service of these penetrations re-i *;

quires them to be' located at an elevation below the bottom of the Reagtor Building Annulus. They are therefore completely embedded in ic,j corarete necessitating the use of a pipe within a pipe design. There-i fore, the difficulties which have arisen in testing penetrations 23, 24,

{

and 44 will be limited to these penetrations.

'T In consideration of the above, the corrective action Engineering has tfken in Reference I will prevent recurrence of similar items of concern.

Should you have any questions or desire further information, please con-tact me.directly.

i A

f

'et: l*

1

/!Q,/

~

S. Le dick, 760 l

, Progran Director, WNP-3

^

DRC.'y 4

ccI J. Adams - NESCO b

D. Smithpeter - BPA Ebasco - New York

$NP-3/5 Fibs - Richland s

a 6

I, A

q 4 4.a V

c

. +

-o i

g 4

j c

',/

m,.

,.