ML20054K720

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept DER 81-14 Re Failure of Four A-354 Anchor Bolts,Initially Reported 810529 & 0624.Marathon Steel Co Issued Audit Findings Requiring Subtier Suppliers Correct QA Deficiencies.Final Rept Expected 820831
ML20054K720
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/15/1982
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-21181-GHD, DER-81-14, NUDOCS 8207060091
Download: ML20054K720 (7)


Text

Docket Nos. 50-528/529/530

50. 55 (e) Report

?

$hhhh STA.

P.o. Box 21666 PHoENtX, arf 20NA 85036 June 15, 1982 ANPP-21181-GHD/BSK U. S. Nuclear Regulatory Commission Region V c ',

Creekside Oaks Office Park y

.J.

1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 c

N M.

Os

p Attention:

Mr. T. W. Bishop, Chief g

Reactor Construction Projects Branch 3

Subject:

Interim Report, Revision 2 - DER 81-14

'f3 A 50.55(c) Potentially Reportable Deficiency Relating to A-354 Anchor Bolt Failures File:

82-019-026 D.4.33.2

Reference:

(A) Telephone Conversation between J. Eckhardt and B. S. Kaplan on May 29, 1981 (B) ANPP-18271, dated June 24, 1981 (Interim Report)

(C) ANPP-19693, dated December 14, 1981 (Extension)

(D)

Telephone Conversation between Bob Dodds and George Duckworth on January 5, 1982 (Extension)

(E) ANPP-19871, dated January 11, 1982 (Interim Rev. 1)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in References (A) and (B), and revised Interim Report was transmitted by Reference (E).

At that time, it was estimated that a Final Report would be available by June 18, 1982.

Due to the extensive investigation and evaluation required, Revision 2 of the Interim Report is attached.

It is now expected that this information will be finalized by August 31, 1982, at which time a complete report will be submitted.

Very truly yours, M/d W

L E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects ANPP Project Director EEVBJr/GHD:db Attachment

[

cc: See Attached Page 2 8207060091 820615 PDR ADOCK 05000529 g*o,167 PJ PDR

U. S._Nucisar Regulatory Commission

-Attsntion:

Mr. - T. W. Bishop, Chief June 15, 1982 ANPP-21181-BHD/BSK Page 2 cc:

-Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 J. A. Roedel D. B. Fasnacht G. C. Andognini A. C. Rogers B. S. Kaplan W. E. Ide J.-Vorees J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson e

R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen C. A. Fiore111 Lynne Bernabei, Esq.

Harmon & Weiss 1725 "1" Street, NW Suite 506 Washington, D. C.

20006 v.

R. L. Greenfield Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 m

INTERIM REPORT - DER 81-14 l

POTENTIAL REPORTABLE DEFICIENCY l

ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNGS UNITS 1, 2 & 3 I.

Potential Problem The Palo Verde Project purchases anchor bolts from Marathon Steel Company, Phoenix, Arizona, who in turn uses Copper State as a subtier supplier.

Copper State uses subtier suppliers as sources of anchor bolts to them.

Four (4) A-354, Grade BD, 1-1/2 inch diameter bolts, used as anchor bolts for the pipe whip restraints in the containment building, cracked and sep-arated during normal handling. One (1) of these bolts was then lab tested for chemical and mechanical properties in accordance with ASTM A-354.

The bolt passed the chemical, strength, and ductility requirements but ex-ceeded, on the high side, the hardness requirement which is grounds for re-jection. Subsequently, a representative sample consisting of five percent (80) of all remaining A-354 Grade BD, bolts in stock at the jobsite were tested for the hardness requirement. The results showed that 29% (23 out of 80) of these bolts failed with 9 high and 14 low. Of the 14 that tested low, 13 of them also failed the tensile test requirements.

II.

Approach To and Status of Proposed Resolution As a result of the identified A-354, Grade BD, bolt failures supplied by Marathon, via their subtier suppliers, Stop Work Notice 81-SW-4 was issued stopping all concrete placements containing A-354, Grade BD bolts.

The Stop Work Notice was' lifted when all A-354, Grade BD, Bolts were required to be hardness tested prior to embedment in concrete and only bolts within a specified preliminary acceptance range were allowed to be used.

Marathon Steel has issued audit findings requiring that the subtier sup-pliers correct the identified quality assurance deficiencies. These suppliers are:

Copper State Bolt & Nut B & G Manufacturing Blue Ribbon Joseph Dyson Lone Star Screw Custom Bolt Cardinal Industrial Cal Pacific Sullivan Bolt Bosco Fasteners Bechtel has developed a program to verify the quality of all high strength bolts and nuts used at the jobsite. All high strength structural bolts are currently being investigated; however, only problems with A-354, Grade BD, bolts have been identified at this time.

With this present plan, no bolts susceptible to stress corrosion cracking will be considered in the design. Using this-fact, it is felt that it is not necessary to (1) revise storage requirements of the bolts prior to installation, or (2) to perform ultrasonic examination to determine if cracks exist within the installed bolts.

Interim Report - DER 81-14 Page 2 In response to a question asked at a status meeting held at Walnut Creek on October 13, 1981, the B & W core bolt problem on Duke Power Oconee 1 was reviewed for similarities to the Palo Verde bolting failures.

No relationship can be drawn since bolting material (stainless steel) and environments are not similar.

e A354, Grade BD, Polar Crane Bracket to Girder Hold-Down Bolts The same concerns exist for these bolts as those that are embedded.

Unit 3 bolts had not been installed at the time of discovery of the problem. Prior to installation, all bolts remaining in stock were Equotip hardness tested with only bolts within,the ASTM hardness range being used. The results of these tests are shown in Table 2.

The results of hardness tests of a sampling of Unit 1 and Unit 2 bolts will be used to evaluate if Units 1 and 2 are acceptable.

e Other High Strength Structural Bolts Marathon's subsupplier of bolts, Copper State Bolt and Nut Company, sent samples of each available lot of bolts received at the jobsite to a lab for testing. Materials included were A-307, A-325 and A-490 bolts, and A-194, A-325 and A-563-C nuts. The results showed that all bolts and nuts tested were within the limits of their re-spective ASTM specifications.

In addition, an inspection program to verify the tension in the high strength bolts in structural steel connections has been implemented.

This inspection program follows the intent of Subsection 6(d) 5 of the AISC Specification for Structural Joints using ASTM A325 or A-490 Bolts, dated April 26, 1978.

e A-540 Bolts for NSSS Supports Most of the A-540 bolts have been installed for all 3 units.

In Unit 1 thirty two (32) A-540 bolts for the Reac' tor Coolant Pump laterial supports were shortened (saw cut) due to excessive projec-tion. These thirty-two samples have been sent to Bechtel's M & QS lab for complete testing. The results of these tests will be used to evaluate whether the remainder of the A-540 bolts need to be tested.

III. Projected Completio'n of Corrective Action and Submittal of the Final Report Evaluation of this condition and submittal of the Final Report is Fore-cast to be completed by August 31, 1982.

A survey of the design drawings has chown that there are embedded e

A-354, Grade BD,. bolts specified for the following categories:

1)

Pipe Whip and Jet Impingement Restraints 1

F Interim Report - DER 81-14 Page 3 2)

Column Hold-down Bolts (Column No. 9 and Column No. 10) 3)

Bolts installed for potential pipe whip and jet impingement restraints, but not presently planned for use.

4)

Bolts Holding Polar Crane Girders to Brackets Over 95% of these bolts fall into Categories 1 or 3.

All of Units 1 and 2, and a portion of Unit 3, bolts were already embedded prior to dis-covery of the deficiency. An Equotip portable hardness tester was pur-chased to allow hardness testing of these bolts in place. A correlation was made at the jobsite between the Equotip "L" values and Rockwell "C" hardness (used in the ASTM specification). The correlation tests showed that "L" hardness values between 570 and 620 are within the acceptable hardness range allowed by the ASTM specification for A-354, Grade BD, bolts. All bolts presently planned for use with pipe whip restraints embedded prior to discovery of the' problem have been hardness tested.

The results are shown in Table 1.

All bolts embedded after discovery of the problem are being hardness tested prior to embedment to assure that the bolt hardness is within the acceptable ASTM range. The remainder of the embedded bolts in Categories 2 and 3 have been hardness tested.

A sampling of thirty-two (32) bolts of Category 4 installed in each of Units 1 and 2 are being tested to assess their acceptability.

Additiona) Investigation and testing were performed by Bechtel's M & QS Department en three (3) of the four (4) failed bolts.

The basic conclusions of this report are:

1) The belts failed due to progressive stress corrosion cracking (and not hydrogen embrittlement) caused by improper heat treatment of the b61 ting material.
2) Recomm n4s acceptance of A-354, Grade BD, bolts up to hardnesses of e

Rockw s,

"C" = 41 (this' corresponds to Equotip "L" value of "L" 640).

Stress _.-trosion cracking does not become a factor until tensile strenp h;2 of 200,000 psi or greater are achieved. A Rockwell "C"

=

41 cea+44 ponds approximately to a tensile strength of 188,000 psi.

The recomsc3dation made by the Bechtel M & QS Department is based on a Teledyne EngJneering Services. report prepared for the Midland Nuclear Porj ect. The problem at Midland appears to be similar to the Palo Verde problem. Telndyne has been retained to review the Palo Verde data and to prepare a repo;:t for Palo Verde similar to that prepared for Midland containing their investigation, evaluation, and recommendations. Addi-tionally, 2 jobsite walk down has been completed and an independent review of the Teledyne work is in progress by Battelle Pacific Northwest Laboratories. Assuming that the recommendations for Palo Verde are similar to thosefu-a aidland, it is anticipated that the need to modify the design

~

or replace +.?ase bolts will be minimized or eliminated.. Bolts with a.

hardness valve outside the ASTM specified range would be derated in ac-cordance with the recommendations. The preload in the bolts shall be limited f:e 4. very nominal load.

i

.,, _.. ~, _. _ _. _, _ _,,., _ _.. _ _ -

DER 81-14 TABLE 1 BARDNESS TEST RESULTS ON EMBEDDED ANCHOR BOLTS FOR PIPE WHIP RESTRAINTS Unit 1 Unit 2 Unit 3 Total Total Number Tested 518 518 416*

1452 Number within 414 423 371 1208 ASTM Bardness Range (570 <Equotip L< 620)

Number Outside 104 95 45 244 ASTM Hardness Range Bolts too soft (Equotip L) 560 - 569 27 21 14 62 550 - 559 6

4 13 23

<550 2

3 10 15 Total 35 28 37 100 Bolts too hard (Equotip L) 621 - 630 37 51 8

96 631 - 640 26 8

34

>640 6

8 14 Total 69 67 8

144 74 Bolts were embedded in concrete prior to discovery of problem.

342 bolts were in forms /rebar at time of discovery. These 342 bolts were hardness tested prior to concrete placement. Any bolt that tested high was replaced with one within ASTM range (total of 24).

45 bolts tested low, 33 of these were accepted by Engineering by derating the bolts accordingly.

(12 bolts were replaced.)

....._~.-._:...-

1 DER 81-14 TABLE 2 BARDNESS TEST RESULTS FOR UNIT 3 POLAR CRANE TO CIRDER BOLD-DOWN BOLTS Total Number Tested 445*

(Prior to installation)

Number within 368 ASTM Hardness Range (570 <Equotip L< 620)

Nunbar Outside 77 ASTM Bardness Range Number Lower than ASTM Hardness Range (Equotip L) 560 - 569 4

550 - 559 1

<550 7

Total 12 Number Higher than ASTM Hardness Range (Equotip L) 621 - 630 61 631 - 640 4

>640 Total 65 Total Number required for Unit 3 is 288. The remaining stock was tested. Only bolts within ASTM hardness r2nge will be used for Unit 3.

e

~ ~ - - -

- ~ ~ ~ ~ ~ ~ ~ ' " ~ ~ ' ' ' ' ' ' ~ ~

- _.. _.., _....-.--7-~

- m

-~ z.r ;

  1. - - - r 112-"~

27 2J -----

-