I.*
THE TOLEDO EDISON COMPANY DAVIS-BESSE NUCLEAR POWER STATION EMERGENCY PLAN SUPPORTING PROCEDUREG REVISION INDEX PAGE REVISION PROCEDURES REVISION T_EMPORARY MODIFICATIONS 1
AD 1827.01 3
AD 1827.02 8
AD 1827.03 1
AD 1827.04 1
T-6019 I
AD 1827.05 2
AD 1827.06 2
AD 1827.07 2
AD 1827.03 1
c AD 1827.09 1
AD 1827.12 7
AD 1827.13 4
AD 1827.14 1
I AD 1827.15 3
AD 1827.16 1
AD 1827.17 1
AD 1850.04 3
AD 1850.05 5
ADMINISTRATIVE MEMORANDUMS REVISION No. 37 - ECS Pager and Telephone Numbers 26 No. 38 - First Aid Team 11 No. 39 - Fire Brigade 12 No. 41 - Emergency Duty Officer (EDO) 24 No. 42 - Radiation Monitoring Teams (RMT) 15 l
l Revision 141 June, 1982 l
8207060044 820625 t
PDR ADOCK 05000346 F
~
ll oATE
. INTRA COMPANY MEMORANDUM casaa2 June 14, 1982 Rev. 24 Fa6e i All Davis-Besse Station Personnel F
M Terry Murray 7q M w/ppy sect vf Emergency Duty Officer (EDO) and Other Emergency Duties ADMINISTRATIVE MEMORANDUM NO. 41-24 1.
Emergency Duty Officers (EDO's) 1.1 In accordance with the Davis-Besse Station Emergency Plan, the c
following named individuals are qualified Emergency Duty Officers:
L. A. Grime D. A. Huffman B. A. Franta B. L. Geddes W. T. O'Connor S. A. Hall W. C. Rowles J. Hirsch C. T. Daft R. F. Peters t
C. J. Greer D. L. Rhodes p
1.2 The following named individuals are assigned as designated Emergency Duty Officers:
L. A. Grime D. A. Huffman B. A. Franta B. L. Geddes W. T. O'Connor S. A. Hall W. C. Rowles J. Hirsch C. T. Daft R. F. Peters C. J. Greer D. L. Rhodes 1.3 Emergency Duty Officers, in addition to the requirements in the Station Emergency Plan, are responsible for the administrative items as given in Section 5 of EI 1300.12, Administrative Controls.
1.4 The following persons have been trained and are qualified as Emergency Assistants, to assist the EDO in the Emergency Control Center (ECC), if necessary:
Gary Downing Ronald Durdel 24 James Faris Richard C. Vollman Rex Rutledge Stephen G. Wideman ry
g-Admin. Memo No. 41-24 Rev. 24 - June 14, 1982 Page 2 2.
Other Emergency Duties 2.1 The Station Superintendent or his designee is to be notified by the Shift Supervisor of any condition which requires an immediate report and/or notification to the NRC.
~
A revised EDO schedule for the third quarter of 1982 is attached.
TDM:nif jI Attachment 1
0
4 Admin. Memo No. 41-24 Rev. 24 - June 14, 1982 Attachment Page 3 EDO 3rd QUARTER SCHEDULE - 1982 Weekly Dates Individual Assigned June 7
- Bob Peters May 31 June 34 Jim Greer June 7 June 21 Don Rhodes June 14 June 28 Bruce Franta June 21 July 5 Dave Huffman June 28 July 12
- Chuck Daft July 5 c
July 19 Bill Rowles July 12 July 26 Larry Grime July 19 I
August 2 Stu Hall July 26 August 9
- Bruce Geddes August 2 August 16 Judy Hirsch August 9 August 16 -
August 23 Bob Peters August 23 -
August 30 Don Rhodes August 30 -
Sept. 6 Bruce Geddes Sept. 13
- Jim Greer Sept. 6 Sept. 13 -
Sept. 20 Bruce Franta Sept. 27 Dave Huffman Sept. 20 Denotes that week in which the EDO must perform the Monthly 24 Communications Link Test, in accordance with PT 5108.01.
The Emergency Planning Group will be present to assist with the Communications Test each month.
nlf/s J
6/14/82
.