ML20054K149

From kanterella
Jump to navigation Jump to search
RO 369/82-39:advising of Postponement Until 820630 for Submitting Complete Rept Re Installation of Two Bolts on Upper Seismic RHR Heat Exchangers.Required Info Unavailable
ML20054K149
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 06/23/1982
From: Parker W
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
RO-369-82-39, NUDOCS 8207010245
Download: ML20054K149 (1)


Text

,

Duxe POWER COMPANY Powzu Bu Lnixo

.m Sourn Cnuncu Srazer, CauntoTTE, N. C. asa4a June 23, 1982 WI LLI AM O. PAR M ER, J R.

Vice Passiotur Tettraont:AntA 704 Straw PaoouctioN 373-4083 N

Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission

'g Region II y

..; o 101 Marietta Street, Suite 3100 m

",g Atlanta, Georgia 30303 r:

Re: McGuire Nuclear Station Unit 1

,[

I Docket No. 50-369 cc

Dear Mr. O'Reilly:

t' On June 9, 1982 your staff was notified that two bolts on the upper seismic support for the residual heat removal heat exchangers had not been installed.

Pursuant to T.S.3.5.2 which is reportable per T.S.6.9.1.12(1), Reportable Occi.crence Report R0-369/82-39 was to have been submitted by June 23, 1982.

At this time, all of the required information is not yet available. The complete report will be submitted by June 30, 1982.

This event was the subject of a technical specification change submitted by Mr. A. C. Thies' (DPC) letter of June 9, 1982.

Very truly yours,

~

a William O. Parker, Jr.

[

PBN/jfw cc: Director Records Center Office of Management and Program Analysis Institute of Nuclear Power Operations U. S. Nuclear Regulatory Commission 1820 Water Place Washington, D. C.

20555 Atlanta, Georgia 30339 Mr. P. R. Bemis Senior Resident Inspector - NRC McGuire Nuclear Station gpytC W '

8207010245 820623 gDRADOCK 05000369 IhM PDR

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _