Responds to 820610 Telcon Request Re IE Bulletin 79-13, Revision 2, Cracking in Feedwater Sys Piping. Water Hammer Problems Not Exhibited at Facility & No Indications Found. Required Insps to Be Conducted During Oct 1982 Maint Outage
ML20054K137
Person / Time
Site: North Anna 
Issue date: 06/11/1982
From: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
REF-SSINS-6820 353, IEB-79-13, NUDOCS 8207010216
Download: ML20054K137 (2)


Text

v GWr'i Or5[AINTRIC AND Powna COMPANY tTtANYA.'bcu.n"oNo,Vamo NIA 20261 L

3'ljgt21 M0 : 01 H.H.Leassano June 11, 1982 Vaca Posesoner Necs.nas Gramarsome Mr. James P. O'Reilly, Serial No. 353 Regional Administrator N0/RMT:rmt U. S. Nuclear Regulatory Commission Docket No. 50-339 Region II License No. NPF-7 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Sir:

This letter is in response to a request made by your staff on June 10, 1982 during a telecon with our staff at North Anna Power Station and Corporate Of fice personnel concerning inspections related to Inspection and Enforcement Bulletin 79-13. Revision 2.

The initial inspection required by the bulletin was satisfactorily completed after hot functional testing was completed on the Unit. As was discussed during the telecon, the Steam Generator /Feedwater piping configuration on North Anna One and Two has not exhibited the water hammer problems that were described in earlier Westinghouse notices.

The recent inse rvice inspection conducted during the refueling outage on the feedwater piping between the Steam Generator and the first isolation valves yielded no recordable indications.

The specific areas which were inspected are as follows; A. One (1), 16" pipe to nozzle weld was volumetrically examined: there were no recordable indications by ultrasonic testing (line no. 16"WFTD-423-601-Q2, weld number 19).

Reference:

DWG NO. VGB-2-2201-[B loop], completed on April,14,1982.

I

(

B. One (1) welded attachment was examined by a magnetic particle test with no recordable indications (line no. 16"-WFPD-424-601-Q2[ welded support]-1).

Reference:

DWG. NO. VGB-2-2101-[A loop], completed on April,14,1982.

C. Nine (9), class 2 pipe supports were visually inspected with no recordable indications (line no. 16" WFPD-424-601-Q2[A loop]. Completed on April.13,1982.

Identification numbers; H-33,H-34,H-35,H-202,H-203,H-204,H-205,H-231,H-232 D. One (1), feedwater nozzle to Steam Generator weld was volumetrically inspected by ultrasonic testing with no recordable indications.

Weld No. 2-9, DWG. NO. VGB-2-11-00[B loop], completed on April.14,1982.

8207010216 820611 PDR ADOCK 05000339 sf G

PDR (t

u.

J

James P. O'Reilly Vauo:M= Etscruic AND POWER COMPANY To Based on the results of these inspections it is our conclusion that continued operation of North Anna Unit Twc is justified. As was stated during the telecon, it is our intention to conduct the required inspections during the oc:ober 1982 Fall maintenance outage. The steam generator nozzle to pipe weld inspections will be conducted in accordance with the criteria set forth in IE3 79-13 utilizing radiographic examinations supplemented by ultrasonic exarina-tions as necessary.

Very t tyly y< urs, I

ff

\\])

R. II. Lea burg cc: Mr. Ilugh C. Dance Region II, Atlanta, CA. 30303 L

J