ML20054G522
| ML20054G522 | |
| Person / Time | |
|---|---|
| Site: | Palo Verde |
| Issue date: | 05/24/1982 |
| From: | Van Brunt E ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR |
| To: | Bishop T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, ANPP-21037-GHD, DER-81-51, NUDOCS 8206210634 | |
| Download: ML20054G522 (2) | |
Text
'EK fif
.'. I
~
Tg
^
J,.,.,
//
./
4'Y M6P7@fM IJ%fJhTTf(V C.M ZFd@[qj(D @T M y g
/j,/>
N 3003 P..
- lf,
STA.
P.O. Box 21666 PHoLNIX, ARIZONA 85036 May 24, 1982 ANPP-21037'CHD/BSK U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:
Mr. T. W.
Bishop, Chief Reactor Construction Branch Projects
Subject:
Time Extension for Report - DER 81-51 A 50.55(e) Potentially Reportable Deficiency Relating to Unit 1 Diesel Generator Control Cabinets Wiring Not Separated Between Class 1E and Non-Class 1E File:
82-019-026 D.4.33.2
Reference:
(A) Telephone Conversation between J. Eckhardt and G.
Duckworth on December 30, 1981 (B) ANPP-20015, dated January 28, 1982 (Interim Report)
(C) ANPP-20485, dated March 19, 1982 (Extension)
(D) ANPP-20752, dated April 20, 1982 (Extension)
Dear Sir:
The NRC was notified of the subject Deficiency Evaluation Report in Reference (A).
An Interim Report was transmitted by Reference (B),
and Time Extensions were requested by References (C) and (D).
At that time, it was estimated that a Final Report would be available by May 24, 1982.
Due to the extensive investigation and corrective action required, it is now expected that this information wil' ke finalized by August 24, 1982, at which time a complete report will te submitted.
There is no change to the Interim Report at this time.
Very trul you I
O G
-\\
'N 6 L.
CLLL d ' CLC I%
E. E. Van Brunt, J. e, 8206210634 820524 APS Vice President PDR ADOCK 05000528 Nuclear Projects S
PDR ANPP Project Director EEVBJr/GHD:ske cc:
See Attached Page 2
U. S. Nuclear Rcgulatory Commission Attention:
Mr. T. W. Bishop, Chief NiPP-21037-Gild /BSK May 24, 1982 Page 2 cc:
Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555 J. A. Roedel D. B. Fasnacht G. C. Andognini A. C. Rogers B. S. Kaplan W. E. Ide J. Vorecs J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. llawkinson L. E. Vorderbrueggen G.
- 4. Fiorelli Lynne Bernabei, Esq.
Ilarmon & Weiss 1725 "I" Street, NW Suite 506 Washington, D. C.
20006 R. L. Greenfield Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 l
l 1
I l
l l
-