ML20054E099
| ML20054E099 | |
| Person / Time | |
|---|---|
| Site: | Oyster Creek |
| Issue date: | 04/20/1982 |
| From: | Fiedler P GENERAL PUBLIC UTILITIES CORP. |
| To: | Eisenhut D Office of Nuclear Reactor Regulation |
| References | |
| RTR-NUREG-0737, RTR-NUREG-737, TASK-1.A.3.1, TASK-2.B.2, TASK-2.B.3, TASK-2.B.4, TASK-2.E.4.2, TASK-2.F.1, TASK-2.K.2.10, TASK-2.K.3.15, TASK-2.K.3.19, TASK-2.K.3.22, TASK-2.K.3.24, TASK-2.K.3.27, TASK-TM GL-82-05, GL-82-5, NUDOCS 8204260135 | |
| Download: ML20054E099 (3) | |
Text
GPU Nuclear g
g7 P.O. Box 388 Forked River, New Jersey 08731 609-693-6000 Writer's Direct Dial Number:
Igril 20, 1982 x (9 8D /,
Mr. Darrell G.
Eisenhut, Director Division of Licensing fiECE;y.7. y Office of Nuclear Reactor Regulation k--
kNi b U.
S. Nuclear Regulatory Commission 3
{
man d Y
{
Washington, D.
C.
20555 28
- /
Dear Mr. Eisenhut:
Subject:
Post-TMI Requirements (Generic
~
Letter No. 82-05)
As requested by the subject correspondence of March 17,,1982, and pursuant to 50.54 (f) of the NRC Regulations, we are supplying you with the current status of the applicable NUREG 0737 items.
You will note that on the attachment (Table 1), we have included completion dates or the proposed time of completion.
In addition we have reterenced correspondence previously sent to you which pro-vides our justification and compensatory measures taken in the in-terim while requesting deferment of several items.
This completes our response to Generic Letter 82-05.
If you should have any further questions please call Mr. James Knubel, Manager, BWR Licensing at (201) 299-2264.
Sincerely, W
P. B. Fiedler Vice President & Director Oyster Creek PBF: Bil/kdk Enclosure
.\\n Sworn and subscribed to before me this oh day of April, 1982, weMbe w Notary Public l}
8 2 0 4 2 6D P6 GPU Nuclear is a part of the General Pubhc Utihties System s-s l
"ABIE 1 SIA'IUS OF NUREG 0737 I'IDE Corressat=:rce/
0737 Itsu Subject Status Justification 1
1)
I.A.3.1 Sinulator Exams Done by NRC 2)
II.B.2 Plant Shielding To be (trrpleted Reference Ietter during upcoming Dated 12-24-81, refueling outage P.R. Clark to NRC 3)
II.B.3 Postwihnt Sanpling Requested Deferal Referem e Letter Until Cycle 11 Dated 12-24-81 Outage 4)
II.B.4 Training for Mitigating Core Damage Otmpleted January, 1982 5)
II.E.4.2 Contaiment Isolation Dependability Requested Deferal Reference letter Until Cycle 11 Dated 8-27-81, also Outage 12-24-81 & 2-10-81 6)
II.F.1 (1) Install Noble Gas Effluent Manitors
'Ib be atmpleted during Reference 12-24-81 upcoming refueling Ietter to NRC outage (2) Provide capability for effluent To be conpleted during Reference 12-24-81 monitoring of iodine tpooming refueling Ietter to NRC 1
outage (3) Install in-contaiment radiation-Requested Deferal Reference 12-24-81 level monitors until Cycle 11 Ietter to NRC outage O
1 1
SIATUS OF NUREG 0737 ITEMS - PNE 2 Correspondence /
0737 Item Subject Status Justification 6)
II.F.1 (4) Provide Continuous indication of To be ccmpleted during Reference 12-24-81
- Cont, containment pressure upctming refueling Ietter to NRC outage (5) Provide continuous indication of To be cmpleted during Reference 12-24-81 containment water level upccming refueling Ietter to NRC outage (6) Provide continuous indication of To be coupleted during Reference 12-24-81 Hydrogen concentration in containnent upocming refueling letter to NRC outage i
7)
II.K.2.10 Safety Grade Trip N/A to Oyster Creek 8)
II.K.3.15 Isolation of HPCI and RCIC bedifica-N/A to Oyster Creek tion.
9)
II.K.3.19 Interlock of Recirc Punp Bequested Deferal Reference 12-24-81 Until Cycle 11 Ietter to NRC Outage
- 10) II.K.3.22 RCIC Suction N/A to Oyster Creek
- 11) II.K.3.24 Space Cooling for HPCI/RCIC N/A to Oyster Creek
- 12) II.K.3.27 Connon Reference IcVel Ocmpleted 12-31-80 Reference Corres-pondence to NBC dated 6-23-80, 9-26-80, and 2-10-81 9