Informs of Implementation of Tech Spec Amend 49 Re Mechanical & Hydraulic Snubbers,Effective 820330. Requirements Cannot Be Implemented on Existing Spare Parts Purchased Prior to Effective Date.Mfg Date Info Required
ML20053E931
Person / Time
Site: Beaver Valley
Issue date: 05/28/1982
From: Carey J
DUQUESNE LIGHT CO.
To: Varga S
Office of Nuclear Reactor Regulation
References
TAC-10477, TAC-10478, NUDOCS 8206100220
Download: ML20053E931 (2)


Text

~

c ggs Telephone (412) 456-6000

~ IoI*8o,[* "

May 28, 1982 Shippmgport. PA 150770004 Director of Nuclear Reactor Regulation United States Nuclear Regulatory Commission

=

Attn:

Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing Washington, DC 20555

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Technical Specifications Amendment 49-Mechanical and Hydraulic Snubbers Gentlemen:

We were issued the subject amendment with an effective date of March 30,1982. The new speci.ication includes a requirement for maintaining records of service life for all snubbers including "the date at which the service life commences".

This letter is to notify you that we are implementing this requirement for new material purchased under requisitions issued since the effective date of the amendment. This requirement cannot be implemented on existing spare parts which were purchased prior to the effective date of the amendment. We are interpreting " service life" as commencing at the time of installation of these spare components unless a limited shelf life was specified by the vendor, providing that these spare parts were maintained in accordance with the recommended storage requirements.

We have a significant number of existing spare parts (ie seals / reservoirs) for which we have been unable to determine the exact manufacturing dates since this information had not been requested on the time of purchase.

We are currently requiring this information on all new purchase orders for snubber parts to provide the requisite information, and this discrepancy will be eliminated when the present stock is exhausted.

We believe the testing and visual inspections that will be performed under the revised specification will assure that all snubbers are capable of perf orming their intended safety function.

Very tr ly yours,

,0 J. J. Carey Vice President, Nuclear 8206100220 820528 DR ADOCK 05000334 p

PDR

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Technical Specifications Amendment 49-Mechanical and Hydraulic Snubbers Page 2 cc:

Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, PA 15077 I.

U. S. Nuclear Regulatory Commission c/o Document Management Branch Washington, DC 20555 a