Omaha Public Power District 1623 HARNEY a OMAHA. NEBRASMA 66102 m TELEPHONE S36 4000 AREA CODE 402 June 1, 1982 LIC-82-226 Mr. Robert A. Clark, Chief U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Licensing Operating Reactors Branch No. 3 Washington, D.C.
20555
Reference:
Docket No. 50-285
Dear Mr. Clark:
Fort Calhoun Station Containment Hydrogen Monitors (NUREG-0737, Item II.F.1.6)
Omaha Public Power District's letter to the Commission, dated March 10, 1982, detailed a delay in placing the subject hydrogen monitors into operation due to damage that occurred during calibration in late 1981. The District returned the hydrogen analyzer cell to the vendor for repair and, based on the vendor's initial repair schedule, the District expected to have the monitors reinstalled and operational by June 1, 1982. However, the District has not received the repaired analyzer cell. The vendor has assured us that the repaired equipment has been shipped to the Fort Calhoun Station and the District expects receipt within the next two weeks.
Af ter receipt, the District will require approximately ten days to reinstall and calibrate the hydrogen
- monitors, lhe District will inform the Commission by July 1,1982 when the containment hydrogen monitors are fully operational.
l
, Sincerely, l
in.
i o
,- n-WJ C. Jones l
Division Manager Production Operations l
cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hamoshire Avenue, N.W.