I.

o UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of CONSOLIDATED EDISON COMPANY OF NEW Docket Nos. 50-247 SP YORK, INC. (Indian Point, Unit No. 2) 50-286 SP POWER AUTHORITY OF THE STATE OF NEW June 1, 1982 YORK (Indian Point, Unit No. 3)

)

NRC STAFF RESPONSE TO WESPAC'S DOCUMENT REQUEST On May 3,1982, Intervenor Westchester Peoples Action Coalition (WESPAC) filed interrogatories which contained requests for documents from the Staff.

For those document requests for which the Staff has not already responded, the responses are provided below.

Interrogatory 2 I

l Supply copies of the August 1981 FEMA report on Indian Point emergency planning, of NUREG-0715, of the Staff review of onsite emergency planning l

(May, 1981), and of the 8/21/81 and 11/19/81 appraisals of onsite planning.

Supply the fullest and most recent information on the FEAM review, including identified deficiencies, referred to in Staff's 12/31/81 filing ("NRC Staff Statement of Position with Respect to the Commission's Six Questions") in this proceeding, at the bottom of page 4.

NRC Staff Response i

NUREG-0715 and the requested Staff documents concerning the review and appraisal of onsite emergency planning are available for inspection and copying in the Local Public Document Room in White Plains, New York l

(LPDR).

e l

l I)So7 sI /

8206040143 820601 PDR ADOCK 05000247 G

PDR l

8 o

2-Interrogatory 3 With regard to the exercise conducted on March 3, 1982:

3(b) Supply copies of all drill scenarios that tested the off-site emergency plan.

3(c) Supply copies of all reports and evaluations written by Staff, FEMA, or the New York State Health Department of the exercise.

NRC Staff Response The NRC documents concerning the March 3, 1982 emergency exercise which were identified in a list attached to the " Response of NRC Staff to Licensing Board Orders of March 10 and April 8,1982" dated May 10, 1982 will be made available for inspection and copying in the LPDR.

Interrogatory 4 What do Staff and FEMA consider as reasonable goals for the time to evacuate the population in an emergency? Include numbers of people, dis-tance to be moved, percentage completion, and percentage who will not be evacuated in a graphical or tabular presentation.

4(a) What is the basis for these goals?

4(b) What accident scenarios are they intended to cover?

4(c) Does the Indian Point Plan meet these goals?

4(d) Did the March 3 exercise meet these goals?

NRC Staff Response NUREG-0396 which was referenced in the "NRC Staff Response to WESPAC's Interrogatories for Nuclear Regulatory Commission Staff", dated May 24, 1982, is available for inspection and copying in the LPDR.

Interrogatory 5 What do Staff and FEMA consider as reasonable goals for notification of people that an emergency exists which would require evacuation?

Include times ahd percentages notified in a graphical or tabular presentation.

5(a) What is the basis for these goals?

5(b) What accident scenarios are they intended to cover?

5(c) Does the Indian Point Plan meet these goas?

5(d) Did the March 3 exercise meet these goals?

NRC Staff Response NUREG-0654 which was referenced in the "NRC Staff Response to WESPAC's Interrogatories for Nuclear Regulatory Commission", dated May 24, 1982, is available for inspection and copying in the LPDR.

Res fully ubmitted, l

Donald F. Hassell l

Counsel for NRC Staff Dated at Bethesda, Maryland this 1st day of June,1982 l

l t

l l

l

. -