e UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION g7 g g ATOMIC SAFETY AND LICENSING BOARDf -
BEFORE ADMINISTRATIVE JUDGES James L. Kelley, Chairman Dr. Cadet H. Hand, Jr.
SERVED NAY 2g g-Mrs. Elizabeth B. Johnson
)
In the Matter of
)
Docket Nos. 50-361-0L
)
50-362-0L SOUTHERN CALIFORNIA EDISON COMPANY,
)
)
)
(San Onofre Nuclear Generating
)
Station, Units 2 and 3)
)
May 25,1982
)
ORDER (Making Clarifying Change in Initial Decision)
The Board's Initial Decision of May 14, 1982 included as a condition of full power licenses extension of siren coverage to the " extended" EPZ, including Dana Point and all of San Juan Capistrano.
This condition was inadvertently drafted in such a way as to require completion of the i
additional siren coverage before full power operations could commence.
That was not the Board's intention.
There probably will be a need for several months' time to acquire, install and test the additional sirens.
Moreover, we have found that " alternative means exist to provide a prompt alert to the public concerning an emergency."
(FF G 11, p.172)
In recognition of these circumstances, we intended to allow six months to meet this condition, just as for similar reasons we allowed six months to remedy deficiencies in the offsite arrangements for medical services.
pgog 3
olo 8205280 nc6C
2-Accordingly, paragraph V C 5 of the Initial Decision, at page 216, is amended by striking out the phrase ", along with siren coverage," and adding the following sentence:
Because of the time probably required to extend siren coverage to that area and because adequate alternate means of public notification of an emergency exist for the interim period, such siren coverage can be completed during the first six rxnths of full power operations.
THE ATOMIC SAFETY AND LICENSING BOARD k
@nies L. Kelley, Chairm'an ADMINSTRATIVE JUDGE I
g Dr. Cadet H. Hand, Jr.
/
ADMINISTRATIVE JUDGE
/4 O.
M h det Mrsf Elizabeth B. QWinson ADMINISTRATIVE JUDGE Dated at Bethesda, Maryland, this 25th day of May, 1982.*
- This matter was brought to our attention by the Applicants' comments of l
May 21, 1982, to the Commission on the Initial Decision.
We are issuing i
this clarifying order on our own motion.