Text
.
~
D DA/RYLAND h
h COOPERAT/VE
- PO BOX 817 261? EAST AV SOUTH
- LA CROSSE. WISCONSIN S4601 j
(608) 788 4 000 May 21, 1982 In reply, please 3
refer to LAC-8303 DOCKET NO. 50-409 Mr. James G.
Keppler, Director U.
S.
Nuclear Regulatory Commission Directorate of Regulatory Operations Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137
SUBJECT:
DAIRYLAND POWER COOPERATIVE LA CROSSE BOILING WATER REACTOR (LACBWR)
PROVISIONAL OPERATING LICENSE NO. DPR-45 REPORTABLE OCCURRENCE NO. 82-10
Reference:
(1)
LACBWR Technical Specifications, Section 6.9.1.8.c (2)
LACBWR Technical Specifications, Section 5. 2.1. 3. (b).
Dear Mr. Keppler:
In accordance with Reference 1, this is to inform you of degradation discovered in the primary reactor containment during periodic Type C surveillance leakage rate testing while in a shutdown condition.
As a result of conducting periodic Type C leak tests on the Heating 1
Steam Condensate Return Valve, the leak flow rates determined from the valve exceeded the permissible leak flow rates as defined in Technical Specifications (Reference 2).
The test leakage rate was determined to be 25.8 SCFH.
The Acceptance Criteria is 0.375 SCFH.*
The test was performed on May 21, 1982.
Prompt notification of test results to Region III, United States Nuclear Regul.. tory Commission, was accomplished at 1545 on May 21, 1982, by L.
S.
Goodman, LACBWR Operations Engineer.
4
- Shall not exceed 1% of leakage rate L where L is 37.5 SCFH.
pg pg t
/ 3 82052,80 i N S
m 24 m
Os 8
Mr. James G.
Keppler, Director LAC-8303 U.
S.
Nuclear Regulatory Commission May 21, 1982 Repairs or adjustments to the Heating Steam Condensate Return Valve will be accomplished and a retest will be performed.
If there are any questions concerning this report, please contact us.
Very truly yours, DAIRYLAND POWER COOPERATIVE dtto Frank Linder, General Manager FL:LSG:af cc:
NRC Resident Inspector