ML20053A955

From kanterella
Jump to navigation Jump to search
Forwards IE Emergency Preparedness Appraisal Repts 50-321/81-30 & 50-366/81-30 on 811130-1211 & NRC 811217 Confirmatory Ltr & List of Preparedness Improvement Items. Response to Items Requested within 30 Days
ML20053A955
Person / Time
Site: Hatch  
Issue date: 02/17/1982
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20053A914 List:
References
NUDOCS 8205270498
Download: ML20053A955 (3)


See also: IR 05000321/1981030

Text

(

.

YELLOW

-

,

FEB 171982

Docket Nos. 50-321 and 50-366

Georgia Power Company

ATTN:

Mr. J. H. Miller, Jr.

Executive Vice President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

SUBJECT:

Emergency Preparedness Appraisal

To $ 3rify that licensees have attained an adequate state of onsite emergency

preparedness, the Office of Inspection and Enforcement is conducting special

appraisals at each power reactor site. These appraisals are being perfomed in

lieu of certain routine inspections normally conducted in the area of emergency

preparedness. The objectives of the appraisal at each facility are to evaluate

the overall adequacy and effectiveness of emergency preparedness and to identify

areas of weakness that need to be strengthened. We will use the findings from

,

these appraisals as a basis not only for requesting individual applicant and

licensee action to correct deficiencies and effect improvements, but also for

,

effecting improvements in NRC requirements and guidance.

During the period of November 30 to December 11, 1981, the NRC conducted an

appraisal of the emergency preparedness program at the Hatch Nuclear Station.

Areas examined during this appraisal are described in the enclosed report

(50-321/81-30,50-366/81-30). Within these areas, the appraisal team reviewed

selected procedures and representative records, inspected emergency facilities

and equipment, observed work practices, and interviewed personnel. The

appraisal findings were discussed with Mr. J. T. Beckham, Jr., and Mr. M. Manry

at the conclusion of the appraisal.

In addition, Georgia Power Company

management representatives met with Region II management on January 7,1982, to

discuss the status of the emergency preparedness program.

Energency preparedness deficiencies identified during this appraisal, for which

you have made acceptable commitments to resolve, were discussed in our confirma-

tory letter, ( Appendix A) dated December 17, 1981. This is to infom you that if

the deficiencies are not corrected by the commitment dates provided, the

Commission will determine whether enforcement action is appropriate.

The findings of this appraisal also indicate that there are other areas which

should be considered for improvenent in your emergency preparedness program.

These areas are identified in Appendix B, "Prepareaness Improvement Items," and

are discussed in the body of the enclosed report.

We recognize that an explicit regulatory requirement pertaining to each item

identified in Appendix B may not currently exist.

Notwithstanding this, you are

requested to submit a written statement within thirty (30) days of the date of

8205270 %

-

- - - - - -

-

_ - _ _ _ _ _ _ _ _ _ _ _ .

__.

,

FEB 171982

Georgia Power Company

2

this letter, addressing the results of your consideration of each of the items in

Appendix B.

This request is made pursuant to Section 50.54(f) of Part 50, Title

10, Code of Federal Regulations.

Your corrective actions are to be incorporated

into the sita emergency plan and procedures as appropriate.

.

In conjunction with this appraisal, the emergency plan for your facility was

reviewed to insure compliance with applicable regulations. The results of this

review, included as Attachment 2 to the enclosed report, indicate that certain

areas of your plan do not contain sufficient information to demonstrate

compliance with the planning standards of 10 CFR 50.47(b).

Changes to the

emergency plan to correct these areas are to be provided to this office and the

Office of fluclear Reactor Regulation within 30 days of the date of such change in

accordance with 10 CFR 50.54(q).

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures will

be placed in the f1RC's Public Document poom unless you notify this office, by

telephone, within ten days of the date of this letter and submit written applica-

tion to withhold information contained therein within thirty days of the date of

this letter.

Such application rust be consistent with the requirements of

2.790(1).

The responses directed by this letter and the enclosures are not subject to the

clearance procedures of the Office of Management and Budget as required by the

Paperwork Reduction Act 'of 1980, PL 96-511.

Should you have any questions concerning this appraisal, we will be pleased to

discuss them with you.

Sincerely,

fr

n

James P. O'Reilly

Regional Administrator

Enclosures:

1.

Appendix A, Confirmation of Action

Letter of December 17, 1981

2.

Appendix B, Preparedness Inprovement Items

3.

Inspection Report flos. 50-321, 366/81-30

cc w/ encl:

J. T. Beckham, Vice President and

General flanager-fiuclear Generation

M. Manry, Plant Manager

-

C. E. Belflower, Site QA Supervisor

.

j

~

_ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ . . _

.

1

1

Georgia Power Company

,3

,

'

bec w/ encl:

NRC Resident Inspector

,

Hugh S. Jordan, Executive Secretary

Document Management Branch

State of Georgia

Emergency Preparedness Licensing Branch, IE:HQ

,

s

J

-

.

.

N

V

!

lp

-

RII

R

RI-

IE

H

R

D And'ews:ejw GRJen ns

yBrownleefPagamo

P Stohr

j

> /jy82

A//

2

4/g(g /82

,P/g/82

'J/jh/82

/7

g

,

.

4

+

F

5

.

d

_

_ . _ _ _ _ _ _ _ . _ _

-

7

Appendix A

,

j ** *' 49

UNITED sTnf Es

.

,

y,

k

NUCLEAR REGUL ATORY COMMISSION

l

-,

y

) s.

E

nEGION ll

5

.

? l

101 MAltit 1i A ST N W .Sulil 3100

0,

g

A T L AN T A. GE OftGI A 30101

%,

/

  • * * '

DEC 171s81

  • 101ue

nssic368

~ ' "

A

6^ 534-

y

n>

Georgia Power Company

Cert M

ATTN:

J.

H'.

Miller, Jr.

Executive Vice President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

Subject: Confinnation of Action

This refers to a telephone conversation on December 16, 1981, between

Mr. W. A. Widner of your staff and Mr. R. C. Lewis of this office concern-

ing our appraisal of the emergency preparedness program at the E. I. Hatch

facility on November 20 to December 11, 1981.

Our findings were also dis-

cussed on December 11, 1981, by Mr. D. L. Andrews of this office with

Mr. J. T. Beckham, Jr. , Vice President and General Manager-Nuclear Genera-

tion, and Mr. M. Manry, Plant Manager.

With regard to matters discussed, it is our understanding that you have

undertaken or will undertake the following actions to resolve apparent

deficiencies in your emergency preparedness program:

1.

Organization

Specify, in the Emergency Plan, the onsite emergency organization

a.

of plant staff personnel for all shif ts and the relationship be-

twden the energency organization and the duties and responsibilities

of the normal staff complement.

This includes specifying by posi-

tion or title the major tasks to be performed by the persons

assigned to the functional areas of emergency activity.

This

action will be completed by March 1, 1982.

b.

Describe, down to the working level, the auginented emergency

organization.

This includes staffing of the energency respense

facilities, identification by name and/or position the plant

and corporate nunagers and alternates who are to take charge

of the emergency response facilities, and identification of

contractor or other non-licensee personnel, if any, who will

augment the emergency organization.

This action will be com-

pleted by March 1,1982.

p g,1 w d d I '] %

/

/

/L/

[

YJ )

I

/

U

,

- _ - _ _ _ _ - _ _ _ _ _ _ _ - _ . _ _ - - _

_

- _____

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ .

_ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

a .

Georgia Power Company

-2-

l

!

!

l

2.

Training

Establish an initial training and annual retraining program for all

a.

!

per.sonnel with emergency response responsibilities.

Each program

shall include classroom training, practical exercises and, where

appropriate, hands-on demonstration of each individual's ability

to perfonn assigned emergency functions.

The program shall also

include examinations designed to test the individual's knowledge

of assigned functional responsibilities, and established perfor-

mance levels below which innediate retraining shall be required.

Establishment of the training program will be completed by

April 1,1982.

b.

Implement the training program, described in item 2.a. above, and

provide accelerated initial training for members of the emergency

response organization.

Include in the program implementation,

positive means- to insure that training is maintained current and

that replacement personnel are provided appropriate initial train-

ing prior to being assigned functicnal responsibility within the

emgrgcacy organization.

This program will be in progress by

April 1,1982.

3,

Equinment

Provide special equipment, including shielding and sample transport

container, for post-accident (high activity) containment atmosphere

samples.

This action will be coupleted by February 1,1982.

4.

Procedures

.

Revise Procedures llNP 4849, liNP 4850, llNP 4851, and ilNP 4852, con-

a.

.

cerning of fsite dose calculations, to provide:

(1) accurate method-

ology for determining offsite doses, (2) a technical basis for such

calculations, (3) a means to modify dose projections based on sampling

and analytical results, and (4) guidelines for protective action

recomendations based on protective action guides for the general

public.

..

b.

Develop a procedure for interim post-accident sampling of contain-

ment atmosphere to include use of the special equipment provided in

accordance with item 3 above, precautions and limitations in the use

of the procedure, analytical methods to be employed for such samples,

and dosimetry and other protective equipment required.

Revise Procedure HNp 4725 concerning offsite radiological monitoring

c.

to resolve significant differences in graphical and analytical solu-

tions resulting from the use of that procedure.

~ i

- - - - _ - - _ _ _ _ - - _ - _ _ _ . . _ . _ _ - . - _ _ _ _ - _ _ _ _ . _

-

_

.2

m

  • eA

Georgia Power Company

-3-

l

d.

Develop a procedure for repair and corrective action teams to include expo-

sure limitations for various activities within the plant, protective clothing

,

and equipment available for use by the teams, provisions for briefing team

members on plant conditions and potential hazards, and a framework for team

organization.

The above procedures will be revised or developed and incorporated into the

training program by March 1,1982.

5.

Initial Dose Assessnent

Develop an initial dose assessment procedure, and provide training to onshift

personnel who may be required to make initial offsite dose projections.

Include

training in initial offsite protective action recommendations when projected

.

doses exceed the lower level protective action guides.

This action will be

completed by February 1,1982.

6.

Report

Submit a written report to this office by April 15, 1982, describing actions

taken in the above areas and, for item 2.b., the percent of training completed

and an estimate of when all initial training will be accomplished.

This letter also confims our arrangements for a meeting at the Region II office on

January 7,1982, at 9:00 a.m. with Georgia Power Company management representatives

to discuss the status of your emergency preparedness program.

Please inform this

of fice immediately if your understanding of these matters is different from that

stated above.

The respons!es requested by this letter are not subject to the clearance procedures

of the Office of Management and Budget as required by the Paperwork Reduction Act

of 1980, PL 96-511.

Sincgrely,

y

ha

(it

James P. O'Reilly

Regional Administrator

cc:

J. T. Beckham, Vice President

and General Manager

M. Manry, Plant Manager

C. E. Belflower, Site QA Supervisor

~

.

.

---

APPENDIX B

PREPAREDNESS IMPROVEMENT ITEMS

Based on the results of the NRC's appraisal of tne Hatch Nuclear Station

Emergency Preparedness Program conducted November 30 to December 11, 1981, the

following items should be considered .or improvement:

(References are to

Sections in 0IE Report No. 50-321,366/81-30).

1.

Developing formal selection and qualification criteria for the onsite

Emergency Planning Coordinator (1.0).

2.

Assigning an onsite Emergency Planning Coordinator (1.0).

3.

Providing a staffing chart for the emergency organization (2.1).

4.

Describing augmented emergency organization at emergency response facilities

(2.1).

.

5.

Identifying support organizations with which a formal agreement has been

reached (2.2).

6.

Providing up-to-date copies of the Emergency Plan and Implementing Pro-

cedures in the Control Room (4.1.1.1).

2

7.

Identifying an alternate location for OSC personnel (4.1.1.3).

8.

Maintaining keys to sampling areas near the Chemistry Laboratory (4.1.1.5).

9.

Providing equipment and procedures for high activity gaseous effluent

samples (4.1.1.5).

>

i

10.

Providing shielding for the reactor building unt and main stack sampling

equipment (4.1.1.5).

,

.

1

11.

Establishing procedures for counting high activity samples on or near the

site (4.1.1.5).

12.

Identifying alternate assembly areas for site assembly (4.1.2.1).

13.

Providing decontamination procedures in the decontamination kits (4.1.2.3).

14.

Identifying working space and resources for corporate and non-licensee

l

t

augmentation personnel (4.1.3).

I

15.

Revising the inventory procedure for emergency kits (4.2.1.1).

!

16.

Completing installation of high range monitors (4.2.1.2).

17. Aligning charts and indicator for wind direction (4.2.1.3).

,

l

,

__

Appandix B

2

Preparedness fmprovement f tems

18.

Revising EAL for seismic events in terms of instrument parameters (4.2.1.3).

19.

Providing labels and proper charts for meteorological instruments (4.2.1.4).

20.

Identifying alternate sources of meteorological information characteristic of

site condi tions (4.2.1.4).

21. Clarifying EALs (5.1).

22. Reviewing appropriate references to emergency procedures in E0P (5.1).

23.

Including emergency classification information in alam and abnormal

occurrence procedures (5.2).

24. i, aciding references to the Emergency Plan and EIP's in appropriate emer-

gency instructions and procedures (5.3).

25.

Improving data sheet infomation for offsite monitoring teams (5.4.2.1).

26.

Revising procedures to include additional guidance for offsite monitoring

teams (5.4.2.1).

27.

Revising procedures to provide additional guidance to inplant monitoring

teams (5.4.2.3).

28. Deleting statements in the emergency procedures that state that high-level

samples will be sent to offsite vendors for analysis and implement onsite or

nearsite capabilities (5.4.2.4-5.4.2.11).

29.

Re-evaluating post-accident sampling procedures with regard to the number of

persons required to obtain each sample (5.4.2.4-5.4.2.11).

,

30.

Clarifying the location to which analysis equipment will be moved if the

,

j

analysis lab is not accessible or has a high background (5.4.2.4-5.4.2.11).

i

!

31.

Detemining counting efficiency factors for the counting shields to be used

with high-level charcoal, silver zeolite, and particulate samples (5.4.2.4-

5.4.2.11).

,

32.

Establishing proper procedures for the labeling and disposition of all

post-accident samples (including liquid effluent samples) and consider using

!

preformatted data sheets when obtaining the samples (5.4.2.4-5.4.2.11).

l

'

33.

Clarifying the method by which reactor building vent and main stack sample

l

are transported from the sampling area to the analysis facility and the

!

location of shielding for these samples to be used during transport

{

(5.4.2.4-5.4.2.11).

!

j

34.

Resolving conflict in exposure guides in emergency procedures (5.4.3.1).

,

i

,

1

1

Appendix B

3

Preparedness Improvement Items

35.

Revising exposure criterion for obtaining emergency stack monitoring reading

or sample in HilP 4350 and HilP 4826 (5.4.3.1).

36.

Resolving conflict in Sections B and J of the Emergency Plan concerning Site

Evacuation (5.4.3.2).

37.

Developing a procedure for accountability during emergencies (5.4.3.3).

38.

Revising security procedures to reference actions required by the emergency

implementing procedures (5.4.4).

39. Developing a procedure which provides guidance to the Repair and Corrective

Action Teams (5.4.5).

40.

Identifying organizational authority for initiating a recovery phase

(5.4.6).

41. Developing coordinated drill and exercise program (5.5.2).

42.

Including rumor control in the Public Information Program (6.2).

43.

Providing implementing procedure for activating public information program

during an emergency (6.2).

44.

Maintaining accountability for drills and corrective actions or drill

deficiencies (7.1).

45.

Providing additional training in evaluation techniques for offsite emergency

teams (7.2).

46. itaking electronic calculators available to offsite monitoring teams (7.2).