Responds Partially to FOIA Request for Documents Re Cancelation,Postponement,Termination or Deferral of Nuclear Plant Const Since 800101.Documents Listed in App Have Been Placed in PDR
ML20053A465
Person / Time
Site: Hope Creek, 05000000, 05000452, 05000453, 05000516, 05000517, Washington Public Power Supply System, Satsop, Black Fox, Hartsville, Phipps Bend, Yellow Creek
Issue date: 05/18/1982
From: Felton J
NRC OFFICE OF ADMINISTRATION (ADM)
To: Doi K
Public Citizen's Critical Mass Energy Project
Shared Package
ML20053A466 List:
References
FOIA-82-204 NUDOCS 8205260125
Download: ML20053A465 (6)


Text

PAL-o/6 bR RtGg f

Ig, UNITED STATES D

g

{

p, NUCLEAR REGULATORY COM.*.11SSION q

C WASWNGT ON, D. C. 20555 9

S nEcggygg 4

MAY 20199gs :

D 88M,85k g May 18, 1982

=

Ms. Kathy Doi Critical Mass Energy Project 215 Pennsylvania Avenue, S.E.

IN RESPONSE REFER Washington, DC 20003 TO F01A-82-204

Dear Ms. Doi:

This is in partial response to your letter dated April 19, 1982 in which you requested, pursuant to the Freedom of Information Act, documents relating to the cancellation, postponement, termination or deferral of nuclear plant construction since 1/1/80.

The documents listed on the appendix are being placed in the NRC Public Document Room (PDR) 1717 H Street, N.W., Washington, DC 20555.

The charge for reproducing records located in the PDR is five cents ($0.05) per page, as specified in 10 CFR 9.14(a).

Copies of these documents can be purchased by writing directly to the PDR.

The number of pages per document is indicated in the Appendix.

Upon your agreement to pay the reproduction charges, the PDR will arrange for the records to be reproduced by Literature Research Company, a private reproduction contractor servicing the POR.

You will be billed by Literature Research Company for the reproduction charges, plus tax and postage.

The NRC has not completed its review of documents subject to your request.

We will respond as soon as the review is completed.

Sinc rely, j

/

/

^

/

M.

elton, Director f.

Division of Rules and Records Of fice of Administration

Enclosure:

As stated g205260lk

C.

Re:

F01A-82-20a b

l APPENDIX l

I Hope Creek 2 1.

12/23/81, News release from Public Service Electric and Gas Company announcing approval by )the Board of Directors of the cancellation of Hope Creek 2.

(6pages 2.

12/24/81, NRC daily highlight announcing the 12/23/81 news release.(1 page)

Baiily 1 i-3.

08/26/81, Letter from Northern Indiana Public Service Company withdrawing application for construction permit extension. (2 pages)

/

{

Hartsville A1, A2, B1, B2 j

4.

07/24/81, NRC preliminary notification of TVA announcement of construction j

delay in Hartsville A1, A2.

(1 page) j 5.

08/14/81, Letter from TVA discussing construction delay in Hartsville A1 5

and A2 and indefinite deferral of Hartsville Bl and B2. (2 pages) 6.

04/01/82, j

deferral of Hartsville Al, A2, B1, B2.NRC memo discussing TVA announ ement o)f in j

3 pages

]

7.

03/04/82, NRC preliminary notification of TVA announcement of the indefinite j

deferral of Hartsville Al and A2. (1 page) i i

}

Grand Gulf 2 1

I 8.

1 2/21/81, Letter from Mississippi Power and Light Company discussing construction j

halt on Grand Gulf 2. (6 pages)

Shearon Harris 3, 4 l

9.

12/18/81, Letter from Carolina Power and Light Company discussing the cancellation i

of Harris 3 and 4.

(2 pages)

I f

i i

_ -.. _.. _ _ - _ _ ~ _ _ _. _ _., _ _ _,.., - _ _

~

~

s Pace 2 WPPSS 1-5 10.

09/09/81, Letter from WPPSS discussing construction slowdown of Unit 5. (2 pages) i 11.

12/23/81, (NRC memorandum discussing the extended construction delay of Units 4 and 5.

58 pages) 12.

02/01/82, Letter from WPPSS announcing the termination of Units 4 and 5.

(2 pages) 13.

02/11/82, Letter from McMinnville Water and Light Comnission discussing adoption of resolution with regard to termination of Units 4 and 5.

(3 pages) 14.

03/02/82, Letter )from NRC to R. L. Ferguson discussing termination of Units 4 and 5.

U page 15.

03/17/82, Show Cause Petition regarding WPPSS 4 and 5. (15 pages)

Cherokee 1 and 2 16.

03/04/81, Letter from Duke Power Company transmitting press release announcing indefinite delay of Cherokee 1 and 2. (2 pages)

Jamesport 1 and 2 17.

12/19/80, Request by Long Island Lighting Company to Atomic Safety and Licensing

}

Appeal Board that proceeding on Jamesport 1 and 2 be ended. ( 5 pages) 1 j

18. 01/07/81, NRC memorandum discussing request by LILC0 to terminate Jamesport 1 and 2 proceeding. (1 page) l 19-01/08/81, NRC staff's response to LILC0 request that proceeding on Jamesport 1 and 2 be terminated.

(5 pages) 20.

01/15/81, Order by) Appeal Board to revoke the Jamesport 1 and 2 construction (2 pages penni ts.

4 21.

01/16/81, NRC memorandum discussing Appeal Board order. (1 page) i 22.

01/16/81, NRC daily highlight on Appeal Board order. (l page) 1 23.

02/06/81, Letter from NRC to LILC0 revoking the Jamesport 1 and 2 construction penni ts. (5 pages)

}

t Greem County, i

24.

10/20/80, Notice of Withdrawal of Construction Permit application for Greene l

County. (1 page) 25.

03/31/81, letter from NRC to Ms. P. llollander discussing closure of the

]

j L POR for Greene County.

(1 page)

Page 3 s

Callaway 2 26.

01/07/80, Caseload Forecast Panel meeting summary noting postponement of construction on Callaway 2. (11 pages) 27.

01/19/81, Board flotification by Union Electric Company announcing cancellation of Callaway 2.

(5 pages)

Davis-Besse 2 and 3 28.

01/24/80, Board flotification from Toledo Edison Company announcing termination of Davis-Besse 2 and 3 (4 pages) 29.

11/17/80, Letter from Toledo Edison Company withdrawing Davis-Besse 2 and 3 application. (1 page) 30.

11/26/80, Letter from Toledo Edison Company discussing plans to redress Davis-Besse site. (5 pages) 31.

12/01/80, Board Order discussing termination of Davis-Besse 2 and 3.

(5 pages) 32.

12/ 31/80, Board Order to staff and applicant to submit report on termination of Davis-Besse 2 and 3. (1 page) 33.

10/15/81, Letter from NRC revoking LWA's and cancelling CP applications for Davis-Besse 2 and 3. (5 pages)

Sterling 34.

07/25/80, Letter from NRC to Rochester Gas and Electric Corporation revoking construction permit for Sterling Power Project. (6 psqcs)

New Haven Station 35.

11/20/80, Notice of Withdrawal of Application for construction permit for New Haven Station.

(1 page)

Montague 1 and 2.

36.

03/25/81, ASLB Board order granting motion to terminate proceeding on Montague 1 and 2.

(2 pages)

Greenwood 2 and 3 37.

07/14/88, ASLB order dismissing proceeding on Greenwood 2 and 3.

(1 page)

.n-e-

Page 4 Haven Nuclear Plant 38.

09/03/80, Notice of Withdrawal of application for construction permit for Haven Nuclear Plant. (1 page)

NEP 1 and 2 39.

01/25/80, Notice of Withdrawal of Application for construction pennit for NEP 1 and 2.

(2 pages)

Black Fox 40.

02/16/82, Letter from Public Service Company of Oklahoma announcing cancellation of Black Fox Station, Units 1 and 2.

(3 pages) 41.

03/18/82, Memo to Commissioner Roberts concerning the cancellation of Black Fox Station, Units 1 and 2.

(8 pages) 42*

04/06/82, " Motion for Termination of Proceeding and Withdrawal of Application" before Atomic Safety & Licensing Board on Black Fox Station, Units 1 and 2.

(8 pages)

WNP-4 43.

02/01/82, Letter from Washington Public Power Supply System advising of termination of WNP 4 and 5. (3, ppg,)

Allens Creek 44.

02/12/82, Letter from Houston Lighting & Power Company advising that they are in the process of reevaluating the feasibility of continuing the Allens Creek project.

(2 pages)

Perkins 1, 2, 3 45.

02/03/82, recommend withdrawal of CP application. Board Notification from Duke Po (3 pages i

46.

03/24/82, Board Order regarding withdrawal of CP application.

(3 pages)

Allens Creek 47.

03/15/82, Board Notification from Houston Power & Light indicating continuing study of feasibility of continuation of project.

(1 page)

Pilarim 2 48.

12/16/81, Applicant's response to Board Order on characterization of'bre-construction activities".

(5 pages) t 01/06/82, NRC staff's supplemental response to applicant's motion to withdraw 49.

application.

(7 tcres)

I

~

Page 5 Black Fox 1, 2 50.

01/18/82, Letter to ASLBP fomarding Oklahoma Corporation Commission decisica regarding utility application for rate increase. (77 pages) 51.

03/18/82, Letter from DOE to Mrs. Talton regarding cancellation of Black Fox 1 & 2. (4 pg 52.

03/26/82, Letter to NRC regarding cancellation of Black Fox 1 & 2 (1 page) 53.

04/09/82, Letter to NRC regarding cancellation of Black Fox 1 & 2.

(2 pages)

Pebble Springs 1, 2 54.

04/12/82, Letter to iSLBP regarding withdrawal of application for a Site Certificate for Pebble Springs. (15 pages)

Erie 1 and 2 55.

04/25/80, Notice df Withdrawal of Application for cps for Erie 1 and E. Q ga;e,-)

e i

4 1

i s

1 5

I i

i i

l 4

I

, _ _ _ _..