ML20052G852

From kanterella
Jump to navigation Jump to search
Advises That Safeguards Contingency Plan Fully Implemented During 810713-23 Preoperational Insp.Guard Training & Qualification Plan Fully Implemented on 820401.Related Correspondence
ML20052G852
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/13/1982
From: Crane P
PACIFIC GAS & ELECTRIC CO.
To: Engelken R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
NUDOCS 8205190069
Download: ML20052G852 (1)


Text

Y

'ME PAC I P'I C GAS AND ELECTR,IC C O M PANY i

.e

. O R2'A2 i

f LAW DEPARTMENT - 77 BEALE STR E ET, 31ST F LOO R. SAN FRAM l$ bO, C ALIFO R NI A 9 4106. (415) 783 4211 t-E!C ~ 913:

4 3

t May 13, 1982 Mr..R. H. Engelken, Regional Administrator Region V U.

S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 i

Halnut Creek, CA 94596 Re Docket No. 50-275 Diablo Canyon Unit 1 Facility Operating License No. DPR-76

Dear Mr. Engelken:

PGandE's License DPR-76 as amended contains dated require '

ments within Section 2.E, Physical Security Issues.

These requirements have been met as follows.

The Diablo Canyon Safeguards Contingency Plan was fully implemented during the preoperational inspection conducted July 13 - 23, 1981 [ refer to NRC Report No. 50-275/81-15 (IE-V454)].

The Diablo Canyon Glard Training and Qualification Plan was fully implemented on April 1, 1982.

Very truly yours, Philip A. Crane, Jr.