ML20052C644

From kanterella
Jump to navigation Jump to search
Forwards Supplemental Info to 820126 Interim Finding on Facility.Info Is Final Rept of 820202 full-scale Joint Exercise.Fema Evaluation & Exercise Manual Encl
ML20052C644
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/22/1982
From: Krimm R
Federal Emergency Management Agency
To: Grimes B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
Shared Package
ML20052C645 List:
References
NUDOCS 8205050326
Download: ML20052C644 (2)


Text

I

)

,a w

  1. v wg 4

f g *( Federal Emergency Management Agency S

Washington, D.C. 20472 m

g f

e o

o REcy,VEq _,.zz\\,

22 MAR 1982 g5 =

r 4 79 g

I MEMORANDUM FOR: Brian Grimes

/

Director 4

p/

Division of Emergency Preparedness q

f U.S. Nuclear Re ulatory Commission FROM:

1 m Assistant Associate Director Office of Natural and Technological Hazards SU3]ECT:

Supplemental Finding on the Enrico Fermi Atomic Power Plant, Unit 2 Attaciled is supplemental information to our January 26, 1982, Interim Finding on the Enrico Fermi Atomic Power Plant, Unit 2.

The information, prepared by FEMA Region V, is a final report of the February 2,1982, full-scale joint exercise and consists of an evaluation of planning standards A-P based on the exercise and the Michigan State and Monroe and Wayne County site specific plans.

The report was transmitted to the State of Michigan on March 10, 1982, with a request that a schedule of remedial actions to the listed deficiencies be provided by April 6, 1982. Once corrective action has been taken on the significant deficiencies by the State and local governments, the offsite radiological emergency planning should be adequate to protect the health and safety of the pubic within the 10 and 50-mile emergency planning zones.

Attachment 8205050326 820322 st PDR ADOCK 05000341 F

pop

)

a[-n Federal Emergency Management Agency

.. *3Q Region V 300 South Wacker,24th Floor, Chicago, IL 60606 (312) 353-1500

+.

MAR 10 W P

MEMORANDUM FCR:

Assistant Associate Director, Office of Natural and Technological Hazards FROM:

Regional Director, Region V

SUBJECT:

2nrico Fer=1 Final Report Forwarded for your review is the Final Report of the Enrico Fermi Atc=ic

?ower ?lant,linit II, full scale exercise conducted on February 1 cnd 2, 1982.

Participating in the exercise with the utility was the State of Michigan, Monroe County and Wayne County.

Observing the off-site portion of the exercise were representatives from Federal Energency Management Agency Region V, the Regional Advisory Co==ittee, and personnel from the argonne National laboratory.

A Post-Exercise Critique and Public Meeting were conducted on February 3, 1982.

FEMA Region V (in accordance with 44 CFR Part 350), intends to provide you with the " Regional Director's Formai Review" of tne sita-specific plans for Fermi II as soon as possible.

b John T. Anders n Regional Director Attachment.