Download: ML20052C373 (2)


Text

sy k

~

=

6-0 O

6 6

n APR 2 913a 9

  • / %

.;O Docket Nos. 50-460, 50-513 I

'l, v

a fg>

S

..$ W'*

[

',4"b Washington Public Power Supply System s

4 P. O. Box 968 J

9 3000 George Washington Way Richland, Washington 99352 p

Attention: Mr. R. W. Root' Acting Program Director Gentlemen:

Cubject:

Systematic Assessment of Licensee Performance for the Period of July 18, 1980 through June 1981.

In 1990 the NRC instituted a program for Systematic Assessment of Licensee "erformance (SALP). The NRC staff beqan collecting available observations anrf, based on those observations, evaluating the performance of power reactor licensees (includinq construction permit holders) with respect to nuclear safety. Durinq the first annual cycle of this program, licensee performance was evaluated in two steps:

first, by a SALP Board in the appropriate NRC Regional Office; and then by a SALP 9eview Group at NRC Headquarters.

The SALP Review Group produced a single report summarizing its assessments for power reactors throughout the U.S.

This report was issued in November 1981 (NUREG-0834, Final Report, NRC Licensee Assessments").

Subsequently, a number of changes were made to the program. The new program ias published in the Federal Register on March 22, 1981, and includes the following principal chanqes:

(1) Adoption of regional level evaluations.

This eliminates review by the SALP Review Groun at NRC Headquarters with its attendant national report while imnroving the timeliness of providing evaluation results.

(2)

Establishment of new evaluation criteria which are not dependent upon the average performance level.

(3) Establishment of a process for taking licensee comments into account.

The second annual cycle of the SALP program for the W4P-1/4 projects covered the period of July 18, 1980 through June 1981 and used a combination of old and new assessment process. The results of the second cycle assessment were discussed with you and members of yourstaff in meetings on September 16-17, 1981. Enclosure (1) to this letter contains the final report for

/

second cycle assessment. This report has been modified to reflect the y j new evaluation criteria h.

...l....

a L....

j

... /.

cumi.ur)

S 9 HP ENGELKEN

  • "'""4

/U2'"' /g/g?"

"4/

y)""

,, 8205040721 820429

~' ' ' '"

PDR ADOCK 03000460

( NZ A PDR OFFICIAL RECORD COPY

' " 'm-32u2

T.

'fashington Public "over %oply;Systen Apji 2 01932 "hould you have any questions concerning the enclosed report we will be

, lad to discuss them with you.

Sincerely, C';Ni t'cnerf r; L H. E. gusu R. H. Engelken Renional Administrator inclosure:

as stated cc w/o enclosure:

R. R. Classcock, nuality Assurance nirector bcc:

DMB/ Document Control Desk (RIDS)

Distributed by RV:

State of WA (Lewis)

RHE (w/o enc)

Resident Inspector Project Inspector