Responds to NRC Ltr Re Violations Noted in IE Insp Rept 50-285/81-16.Corrective Actions:Upgrading QA Vault w/2-h Fire Rated Ceiling & Door,Fire Rated Dampers,Smoke/Fire Detectors & Suppression Sys
ML20052B640
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 02/26/1982
From: William Jones
OMAHA PUBLIC POWER DISTRICT
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20052B638 List:
References
LIC-82-066, LIC-82-66, NUDOCS 8205030400
Download: ML20052B640 (1)


Text

I Omaha Public Power District 1623 HARNEY a OMAHA, NEBRASKA 68102 a TELEPHONE 536 4000 AREA CODE 402 February 26, 1982 LIC-82-066 Mr. J. T. Collins, Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 760'.1

Reference:

Docket No. 50-285 IE Inspection Report 81-16

Dear Mr. Collins:

Omaha Public Power Dist-ict's response, dated September 4,1981, to the subject Inspection Report provided the District's schedule for upgrading the Fort Calhoun Station quality assurance (QA) vault to ANSI N45.2.9-1979 design criteria.

The extensive scope required by the installation of the large r. umber of TMI mcdifications and equipment during the 1981 refueling outage preempted completion of the necessary vault design and modification work by February 28, 1982. Actions which have been completed include review and approval of the preliminary design, and the final design package will be completed and available for plant approval by March 1, 1982.

Following review and approval of the final design, the District estimates equipment and parts delivery for the modifications will require approximately five weeks.

Based on this schedule, the District expects to complete the vault modifications by June 1, 1982.

Upgrading the QA vault to ANSI N45.2.9-1979 criteria will require installation of a two-hour fire rated ceiling, two fire rated dampers, a two-hour fire rated door, smoke / fire detectors, a fire suppression system, and removal of the existing air conditioner.

Completion of these modifications will provide the Fort Calhoun Station with a QA vault that meets all requirements for a single storage facility.

I W. C.l.dones Division Manaaer f(

Production Operations WCJ/KJM/RWS:jmm cc:

U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement gggy Washington, D.C.

20555 leR - 3 E LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.

,t Washington, D.C.

20036 U

t 82050Soyoo