ML20051A097

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-482/82-06 on 820329-0402.No Noncompliance Noted.Major Areas Inspected:Const Activities Including Work & Records for Welding & Nondestructive Exam of RCPB
ML20051A097
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/27/1982
From: Gilbert L, Randy Hall, Hunnicutt D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20051A115 List:
References
50-482-82-06, 50-482-82-6, NUDOCS 8205140478
Download: ML20051A097 (6)


See also: IR 05000482/1982006

Text

r-

'

.

. APPENDIX

!

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

This Report Contains Results of an Investigation

Report:

STN 50-482/82-06

Docket:

STN 50-482

Category A2

Licensee:

Kansas Gas and Electric Company

P. O. Box 208

Wichita, Xansas 67201

Facility Name:

Wolf Creek, Unit 1

Inspection at:

Wolf Creek Site, Coffey County, Burlington, Kansas

Inspection Conducted:

March 29 - April 2, 1982

1'd6/8A

Inspector:

/

L. D. Gilbert, Reactor Inspector, Engineering Section

'Date

Reviewed:

-

'

7

h

R. E. Hall, Chief, Reactor Project Section C

Date'

Approved:

/97/l

d#

7/.27/84

D. M. Hunnicutt, Chief, Engineering Section

Date '

Inspection Summary

Inspection during March 29 - April 2, 1982 (Report STN 50-482/82-06)

Areas Inspected: Routine, unannounced inspection of construction activities

including an allegation item and observation of work and review of records

for welding and nondestructive examination (NDE) of Reactor Coolant Pressure

Boundary piping.

The inspection involved 30 inspector-hours onsite by

one NRC inspector.

Results: No violations or deviations were identified.

The allegation dis-

cussed in paragraph 2 was not substantiated.

8205140478 820427

PDR ADOCK 05000482

G

PDR

-

.

DETAILS

1.

Persons Contacted

Principal Licensee Personnel

,

  • D. W. Prigel, Manager QA, Site
  • G. W. Reeves, Assistant Manager QA, Site
  • 0. L. Thero, Supervisor, QA Surveillance
  • C. E. Parry, Supervisor, QA Systems
  • D. A. Colwell, QA Technologist
  • J. L. Stokes, Project Support Supervisor

Other Personnel

J. Johnson, Project Piping Engineer, Daniel International Corporation

(Daniel)

J. Linsome, Mechanical Superintendent, Daniel

G. Robertson, NDE Level III, GE0 Construction Testing

The NRC inspector also interviewed other licensee and contractor employees

during the course of the inspection.

  • Denotes those attending the exit interview.

2.

Allegation Regarding Improper Welding Techniques

An allegation regarding improper welding techniques, received by the NRC

Resident Reactor Inspector on March 4, 1982, was reviewed by the NRC

inspector during the inspection.

A welder claimed that while taking a

test on Performance Test No. N-8-8-B-3 he was told to run the root pass

and " wash" the remainder which he believed to be contrary to the procedure.

He refused to complete the weld by " washing" and was fired.

The welder

also stated that he believed this practice was common onsite for weld-out

of small bore extra strong pipe, but that it is not in accordance with

the procedure.

The following information was obtained by the NRC inspector:

Performance Test No. N-8-8-B-3 is specified in Daniel Procedure

-

CWP-502, Revision 16 for qualification of welders.

The test requires

that a welder complete four consecutive open root butt joints con-

sisting of 1/2-inch NPS pipe with a 0.294-inch nominal wall thickness

in the "6G" position using the gas tungsten-arc welding process and

type ER 308 filler metal.

-

Instructions for welding stainless steel small bore extra strong

pipe are contained in Daniel Procedure CWP-507, Revision 14 under

Weld Procedure Specification (WPS) N-8-8 and Welding Technique

(WT) N-8-8-B-3.

Paragraph 4.18.4 of WPS N-8-8 specifies that a

2

1

.

minimum of three layers of weld metal shall be deposited for wall

thicknesses 1/4-inch and greater.

Therefore, at least three

layers of wald metal should be used to complete the Performance

Test No. N-8-8-B-3.

The welder qualification supervisor informed the NRC inspector

-

that he had been assigned the position on March 29, 1982, since

the previous welder qualification supervisor terminated employ-

ment at the site en March 26, 1982.

'-

The NRC inspector interviewed all eight of the welders listed as

currently qualified to WT N-8-8-B-3.

Each of the eight welders

stated to the NRC inspector that:

a.

He had taken the Performance Test No. N-8-8-B-3, consisting

of four consecutive test welds, which he completed using

between four and seven layers of weld metal.

b.

He had never been requested or instructed to weld the test

weldments nor aly production welds (1/4-inch or greater in

wall thickness) using only two layers of weld metal (root

pass and " wash" remainder),

c.

He could not recall depositing less than four layers of weld

metal on any safety-related weld having a pipe wall thickness

of 1/4-inch or greater.

'

This allegation could not be substantiated and the NRC inspector indicated

that he had no further questions regarding this matter.

3.

Reactor Coolant Pressure Boundary Pipe Welding Activities

a.

Observation of Work

-

The NRC inspector selected eleven completed welds in the Reactor

Coolant Pressure Boundary piping to inspect the final weld surface.

The following welds were inspected and found to be consistent with

the ASME B&PV Code,Section III NB for weld reinforcement limitations,

transition requirements between different wall thickness pipe, and

weld quality.

Drawing

Weld

System

I-M13BB02(Q)

F010

Reactor Coolant

I-M13BB02(Q)

F017

Reactor Coolant

I-M03BB14(Q)

F005

Reactor Coolant

I-M03BB14(Q)

F004

Reactor Coolant

I-M03EP02(Q)

F007

Accumulator Safety Injection

3

--.

.

-

.-

~

.

.

Drawing

Weld

System

I-M03HB24(Q)

F500

Liquid Radwaste

I-M03BB05(Q)

F001

Reactor Coolant

I-M038G24(Q)

F552

Chemical and Volume Control

I-M03BG24(Q)

F553A

Chemical and Volume Control

P-M03BB14(Q)

W534A

Reactor Coolant

P-M03BB15(Q)

W566

Reactor Coolant

The NRC inspector observed the following repair activities on the

Reactor Coolant Pressure Boundary Class 1 piping:

-

Cutting defective Weld F021 in Reactor Coolant System of

of Drawing I-M13BB04(Q) for rewelding.

-

Excavation of a radiographic defect and liquid penetrant

inspection of completed weld repair on Weld F304R-1 in

Reactor Coolant System of Drawing I Loop 3(Q).

-

Wcid repair of counterbore on Weld F905A in Accumulator Safety

Injection System of Drawing I-M03EJ04(Q) for violating minimum

wall thickness requirements. The NRC inspector reviewed the

Weld Repair Instruction WRI 2-FW905-1 and Veld Repair Procedure

CWP-504, Revision 10 and requested that CWP-504 be clarified to

comply with ASME Code Interpretation III-1-79-14, issued

January 25, 1979, in that, weld buildup of pipe counterbores

shall be treated as a weld repair of material under ASME B&PV

Code,Section III NB/NC/ND-4214 and nondestructively examined

accordingly.

This item is considered unresolved pending completion of actions

required in KG&E Surveillance Report S-478 for clarification of

CWP-504 and evaluation of past weld repairs to pipe inside diameter

surfaces.

b.

Review of Records

,

The NRC inspector selected five coraleted welds in the Reactor

Coolant Pressure Boundary piping to review.

The following weld

records were reviewed for adequate wel,d and inspection history

documentation:

Drawing

Weld

System

I-M13BB02(Q)

F010

Reactor Coolant

I-M13BB02(Q)

F017

Reactor Coolant

4

,

.

Drawing

Weld

System

I-M03BB05(Q)

F001

Reactor Coolant

I-M038G24(Q)

FW552

Chemical and Volume Control

I-M038G24(Q)

FW553A

Chemical and Volume Control

No violations or deviations were identified.

4.

Reactor Coolant Pressure Boundary Piping NDE Activities

a.

Observation of Work

The NRC inspector selected two welds in the Reactor Coolant piping

system where the welding and surface preparation were complete and

liquid penetrant examinations were in progress.

The two welds

inspected were Weld W534A of Drawing P-M03BB14(Q) and Weld W566 of

,

Drawing P-M03BB15(Q).

Each weld was liquid penetrant inspected con-

sistent with the requirements of GEO Procedure IPPT-340, Revision 1701-3

for liquid penetrant examination techniques, materials, and acceptance

criteria,

b.

Review of Records

The NRC inspector selected six completed welds in the Reactor Coolant

Pressure Boundary piping to review the NDE records covering evaluation

of weld quality.

lhe following NDE reports were reviewed:

,

NDE Report

Drawing

Weld

System

RT-7213

I-M13BB02(Q)

F010

Reactor Coolant

PT-4476

I-M13BB02(Q)

F010

Reactor Coolant

RT-7214

I-M13BB02(Q)

F017

Reactor Coolant

PT-4476

I-M13BB02(Q)

F017

. Reactor Coolant

RT-6777

I-M03BB05(Q)

F001

Reactor Coolant

PT-4122

I-M03BB05(Q)

F001

Reactor Coolant

RT-5869

I-M03EP02(Q)

F007

Accumulator Safety

Injection

PT-3288

I-M03EP02(Q)

F007

Accumulator Safety

Injection

RT-69921

I-M03BG24(Q)

FW552

Chemical and Volume

Control

5

. - .

- . - -

.

--

. , . - .

...

- -

-_-

-

.-

_ . , -- ..-

'

..

NDE Report

Drawing

Weld

System

PT-69922

I-M03BG24(Q)

FW552

Chemical and Volume

Control

RT-69929

I-M038G24(Q)

FW553A

Chemical and Volume

Control

PT-69930

I-M03BG24(Q)

FW553A

Chemical and Volume

Control

No violations or deviations were identified.

5.

Unresolved Items

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, violations, or

deviations.

One unresolved item disclosed during the inspection is

discussed in paragraph 3.a.

6.

Exit Interview

The NRC inspector met with licensee representatives (denoted in para-

graph 1) and T. E. Vandel (NRC Senior Resident Reactor Inspector) on

April 2, 1982, and summarized the scope and findings of the inspection.

6