ML20050E237

From kanterella
Jump to navigation Jump to search
Urges NRC Not to Accept Current Plant Design & Seismic Readiness Study by Util Selected Consulting Firm.Independent Consultant Should Be Selected
ML20050E237
Person / Time
Site: Diablo Canyon  
Issue date: 04/04/1982
From: Nimmons D
AFFILIATION NOT ASSIGNED
To: Palladino N
NRC COMMISSION (OCM)
References
NUDOCS 8204130129
Download: ML20050E237 (1)


Text

IQ 1110NS 1001 SIERRA STREET BERKELEY,C A 94707 415/524-9886,527-2511 so m s Mr. Nunzio Palladino Chairperson Nuclear Regulatory Commi ssion

.rq

^g

_ a nn.- -

Washington, D.C.

O f

8 9

.:0

/

g7 h 4 April, 1982

?

<<h

~

gyv g_'.h

Dear Mr. Palladino,

I hope that the NRC will decide not t

g Nfll-current plant design and seismic readiness study on the Diablo Canyon

plant, authored by PG&E's selected consulting firm.

I urge the'NRC to select an independent nuclear plant consultant which will perform an entirely new study, in order to estabish once and for all which problems are serious saftey threats and which have been resolved.

I believe there have been so many i nconsi stenci es, omissions, and irregularities with the current study that many are feeling there has been a significant attempt by PG&E to mislead the public.

In order to put those fears to rest, relieve the public anxiety and determine clearly the present risks of the plant as it now stands I think a new, unbiased study. must be done.

For that reason, I hope you will decide not to simply re-evaluate the present study but to undertake an entirely

new, independent, examination of design and construction procedures at the Diablo Canyon Plant.

$O3 s

Io David Nimmons 8204130129 8204o4

-g>

DR ADOCK 05000275 j n ;v.s.t,

PDR

/

/