Submits Const Completion Schedule.Delay Likely in Fuel Loading Date Due to Const,Preoperational Testing & Licensing Milestones.Unit 1 Fuel Loading Scheduled for Apr 1983
ML20050B608
Person / Time
Site: Byron  Constellation icon.png
Issue date: 03/29/1982
From: Delgeorge L
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8204060124
Download: ML20050B608 (1)


Text

-

N Commonwealth ECson O j) ona First Nation:1 Plaza. Chicago. Illinois 7

Addr:ss R: ply to: Post Offica Box 767 f Chicago Illinois 60690 March 29, 1982 Mr. Harold R. Denton, Director Of fice o f Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 7

g J

N

Subject:

Byron Station Units 1 and 2 3

JCMED

,g Construction Completion Schedule 2

NRC Docket Nos. 50-454 and 50-455 a nP 3 1982> ~.

Reference (a):

May 29, 1981, letter from tax rmw a M

-(y H. R. Denton to J. J. D 'Conno r.

b

'v w

Dear Mr. Denton:

This letter is the fourth in a series of quarterly reports to you regarding the construction completion date for Byron Unit 1.

The Byron 1 construction and testing schedule is s till keyed to fuel loading in April 1983.

This schedule is currently being reevaluated as part a f a semi-annual budget review which is expected to be completed in June, 1982.

Although the -review process is not complete, we have concluded that it is likely the completion of the remaining contruction, preoperational testing and licensing milestones will result in a delay of the fuel load date.

No new target date for fuel loading has been established yet but it is believed that the delay in fuel load oate will probably be in the 6 to 8 month range.

The NRC will be informed as soon as new schedules have been established.

Please address further questions regarding the Byron 1 schedule to this office.

I Very truly yours, t

L.

O. DelGeorge Directo r o f Nuclea r Licensing

{