Responds to Questions in Aslab 820308 Memorandum & Order Re HPI Nozzles.Thermal Cycle Due to Makeup Flow May Have More Significant Impact on HPI Makeup Nozzles than Thermal Cycling from HPI Actuation
ML20050A815
Person / Time
Site: Rancho Seco
Issue date: 03/31/1982
From: Novak T
Office of Nuclear Reactor Regulation
To: Black R
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
Shared Package
ML20050A808 List:
References
NUDOCS 8204020297
Download: ML20050A815 (2)


Text

_

  1. p ~.m'o, UNITED STATES

!?

. J' ?

NUCLEAR REGULATORY COMMISSION

'cy. ' s"# lE WASHINGTON, D. C. 20555

~y

.7

....+

fiarch 31, 1982 Docket No. 50-312 NEM]RAtiDUM FOR: ' Richard. L. Black, Office of the Executive Legal Director FROM:

Thones M. Novak, Assistant Director for Operating Reactors, Division of Licensing, NRR

SUBJECT:

STAFF TESTIMONY ON RANCHO SECO ASLAB MEMORANDUM AND ORDER DATED MARCH 8, 1982 - HPI N0ZZLES Enclosed is testimony from Mark L. Padovan in response to the Rancho Seco ASLAB Memorandum and Order dated March 8,1982. This testimony addresses the Board's concerns about themal cycling of HPI nozzles, and supplements:

_l) his previous testinony dated December 11, 1981 and January 6,1982 and

2) Jonn F. Stolz's testimony dated February 25, 1982.

Previous testimony on the above subject was concerned with the effects of thermal cycling on the HPI nozzles due to HPI actuations. As a result of noz:le cracking discovered at Crystal River-3 in early February 1982 and at Oconee 2 and 3 in early March 1982, it appears that thermal cycling due to nakeup flow may have a nore significant impact on the HPI/nakeup nozzles that thermal cycling f rom HPI actuation.

Following meetings held with the B&W licensee in March 1982, all operating B &,: plants will have scheduled shutdowns during which the licensee will inspect all HPI nozzles. At this time, Rancho Seco is scheduled for shutdown on April 2,1982.

All other B&W plants have conducted or'are' conducting nozzle inspections. A summary of the results of the nozzle inspections at Oconee, Three Mile Island-l and Crystal River-3 can be found in the meeting minutes enclosed with Mark Padovan's testimony.

Plans for inspections of Davis-Besse 1, Rancho Seco and Arkansas Nuclear One are also provided in the meeting notes.

The staff is continuing to follow this problem and the D&W Owners have established a task group to oversee followup action.

This group has been requested to expeditiously prepare plans to evaluate the cause of the cracking problem and develop long term solutions to prevent recurrence.

8204020277 020331.

PDR ADOCK 05000312 C

PDR

Richard L. Black The respor.ses to 0 restions 2 and 3 require additional information which will be provideo to the Board:

e For Question 2 - Verification of the results of the inservice inspecti n records findings at Oconee.

o e For Question 3 - Clarification on how the therral cycles listed for Rancho Seco were determined and; the nur.ber of thernal cycles that have occurred at Crystal River-3 af ter the initiation of the procedures required by the Connission's May 1979 Order.

?

4 ) r-Thomas M. flovak, Assi: tant Director for Operating Reactors Division of Licersing Enclos ure:

Mark L. Padovan's Testirony cc w/ enclosure: