Confirmation of Action Re Agreements Reached at 820219 Mgt Exit Interview Following Emergency Preparedness Appraisal. Corrective Actions Required for Significant Appraisal Findings Submitted
ML20049H757
Person / Time
Site: Davis Besse 
Issue date: 02/23/1982
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
References
NUDOCS 8203030515
Download: ML20049H757 (2)


Text

CONFIRMATION OF ACTION FFEB 2 3 Ed2

\\ \\en N

d

/' t

-)/

p' 'r i*f d'! 73 9

,,a n n.

f _;ay

~.

Docket No. 50-346

, 7 'L '~ pp g

Toledo Edison Company

\\

',- ^ f0

\\-

,i' ATTN:

Mr. Richard P. Crouse x

n

-(s 4/

Vice President

,,J '

Nuclear

~'~

Edison Plaza 300 Madison Avenue Toledo, OH 43652 Gentlemen:

This letter is to confirm agreements reached between you and others of your staff, and Mr. W. Axelson and other members of the NRC staff on February 19, 1982, during the management exit interview following the NRC Emergency Preparedness Appraisal.

Immediate corrective actions are required for significant Appraisal Findings.

The exact nature of the required actions, as well as the agreed upon dates for such actions, are as follows:

1.

Procedure for Implementation of Emergency Plan Required Actions a.

The licensee shall provide a schedule for installation and calibration of a upgraded seismic monitoring system which will be capable of determining earthquakes greater then OBE levels (Alert Emergency) and SSE levels (Site Area Emergency). EALs shall be calculated for OBE and SSE levels and incorporated into the Emergency Plan and its procedures.

This shall be completed by March 22.

b.

All operations crew personnel (licensed operators) shall be re-trained relevant to implementation of Special Procedure 1105.17, Seismic Monitoring System Procedure.

CONFIRMATION OF ACTION 8203030515 820223 PDR ADCCK 05000346 3/

j G

PDR

, /p

CONFIRMATION OF ACTION Toledo Edison Company 2

This shall be completed before startup following the forthcoming refueling outage.

c.

Documented guidance and training shall be provided for the operating crew (licensed operators) to cope with a loss of vital DC power.

This shall include provisions to ensure that the Shift Supervisor will classify such an event in accordance with the Emergency Plan.

This shall be completed before startup following the forthcoming refueling outage.

d.

EALs shall be developed for the main steam line radiation monitors (N-16) for those events listed in Table 4-1 of the Emergency Plan.

In addition, training shall be provided to appropriate radiation assessment personnel relevant to the use of the EALs.

This shall be completed before startup following the forthcoming refueling outage.

If our understanding of your planned actions described above is not in accordance with the actual plans and action being implemented, please contact this office by telephone and in writing within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Further, please inform this office, in writing, upon completion of all the above action items.

Sincerely, Original cisned by James G. Keppler James G. Keppler Regional Administrator cc:

T. D. Murray, Station Superintendent DMB/ Document Control Desk (RIDS)

Resident Inspector, RIII Harold W. Kohn, Power Siting Commission Helen W. Evans, State ot Ohio RII g R II RIII RIII RIII RIII RIII N

] ll 1$ ?

$^

e69 4

f Grant /jp A 1s Paper [11o 1

Sphssard Davis K

1pr 2/22/82 2 l'L' ?'!.

2J 67-S/g/e*yzZ-18A CONFIAMATION OF C ON