ML20046B038

From kanterella
Jump to navigation Jump to search
Insp Rept 50-382/93-24 on 930706-09.No Violations Noted. Major Areas Inspected:Effectiveness of Licensee Activities Taken in Response to NRC Audit of safety-related Check Valve Program
ML20046B038
Person / Time
Site: Waterford 
Issue date: 07/26/1993
From: Powers D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20046B033 List:
References
50-382-93-24, NUDOCS 9308030030
Download: ML20046B038 (7)


See also: IR 05000382/1993024

Text

..

.-.

.

-

..

- - . .

.

.

..

,

!

APPDWIX

j

l

U.S. NUCLEAR REGULATORY COMISSION

'

REGION IV

,

,

Inspection Report:

50-382/93-24

h

.

License:

NPF-38

-

,

Licensee:

Entergy Operations, Inc.

.

P.O. Box B

'

K111ona, Louisiana

~

Facility Name:

Waterford Steam Elec'tric Station, Unit 3'

Inspection At:

Taft, Louisiana

l

'

Inspection Conducted:

July 6-9, 1993

,

Inspector:

L. E. E11ershaw, Reactor Inspector, Division of~ Reactor Safety

'

Approved:

24[f.K '

Dr. Dale A. Powers, Chief, Maintenance Section

-Date

Division of Reactor Safety

Inspection Sumary

i

J

Areas Inspectedt - Routine, announced followup inspection of the effectiveness ..

of licensee activities taken in response to an NRC audit of the safety-related

check valve program.

Results:

The licensee's extensive reevaluation of its check valve program.

exceeded the recomendations identified in the 1991 NRC audit report.

The licensee's approach toward program improvements was proactive-

(Section 2.2).

Sumary of Inspection Findinas:

All of the recomendations were closed (Section 2.2).

Attachments:

Attachment - Persons Contacted and Exit Meeting

)

9308030030 930727'

PDR

ADOCK 05000382

,

G

ponj

i

.

.

-2-

DETAILS

1

PLANT STATUS

During this inspection period, the plant was operating at 100 percent power.

2

FOLLOWUP (92701)

During September 30 through October 4, 1991, the NRC conducted an audit of the

licensee's check valve program using draft Temporary Instruction 2515/110,

.

" Effectiveness of Licensee Activities Regarding the performance of Safety

Related Check Valves." The NRC audit report was issued November 19, 1991.

The audit report concluded that the licensee had a satisfactory and effective

inservice test (IST) program and a satisfactory check valve reliability

program; however, certain concerns were identified for licensee consideratior.

2.1 Discussion

The licensee submitted letter W3F191-0831 dated December 26, 1991, in which

responses to the recommendations, including implementing schedules, were

provided. A subsequent licensee letter, W3F193-0129 dated March 29, 1993,

documented a discussion with the NRC in which an extension had been discussed

and concurred with regarding one of the responses.

The inspector reviewed the audit report and licensee responses, and verified

that all issues had been appropriately addressed. The licensee grouped the

responses by subject matter and assigned a commitment tracking number to each

grouping. Since the NRC audit report did not assign unique identifiers to

each recommendation, the inspector used the licensee's commitment tracking

numbers to identify, sort, and evaluate the responses to the recommendations.

Commitment Tracking No. A-17914 dealt with the need to perform a

reevaluation of the check valve design review to determine if additional

valves should be included in the check valve program, and to provide

guidance on prioritizing, grouping, and establishing frequencies of

check valve monitoring and maintenance activities.

)

The licensee responded by establishing actions to (1) evaluate the

adequacy of the check valve program scope; (2) specify enhanced criteria

l

to be considered when evaluating present and future check valve

applications; (3) develop criteria for prioritizir.g, grouping, and

establishing frequencies for monitoring and maintenance activities;

(4) provide application guidance on design input checklists; and

(5) provide information on the design input checklists to ensure that

new and existing check valves were considered for the check valve

program. These actions had been scheduled for completion to support

check valve inspections during the sixth refueling outage, which is

scheduled for March 1994.

.

-3-

1

,

The inspector verified that the methodology for implementing these

actions had been incorporated into the following program

i

documents: Check Valve Analysis and Prioritization Program, a

i

computer program that was installed in June,1993; Waterford 3.

Steam Electric Station Check Valve Program Plan dated December 29,

1992; and Waterford 3 Design Engineering Guide M/C-D-001,

Revision 1, dated January 4, 1993.

Commitment Tracking No. A-17915 dealt with the need to strengthen the

check valve maintenance training program,

j

The licensee responded by stating that additional training needs had

already been identified during curriculum comittee meetings. As a

result, training on specific types of valves was established and

initiated on December 11, 1991.

The inspector verified, by review of attendance records, that

maintenance training was provided to maintenance personnel during

December 1991, and January and February 1992, on specific types of check

valves, and that lesson plans had been strengthened and revised. Also,

a management observation program was in place to monitor various

activities, including training effectiveness.

Comitment Tracking No. A-17916 dealt with six specifically identified

i

issues related to the IST program.

Each issue, including the licensee's

response and actions, is as follows:

.

Recomendation 1 dealt with the IST basis document' that justified the

-!

inclusion or exclusion of check valves for the IST program.

It was

recommended that the licensee formally review, approve, and maintain the

'

document as part of the IST program.

The licensee's response comitted to formalize the document by March

1993.

Subsequently, the licansee requested and received an extension

until December 18, 1993. This was done so that the licensee could

update the IST basis document concurrent with a resubmittal of the_

Waterford 3 IST Plan, which is scheduled for August 1993. The inspector

verified that the licensee had documented (by Letter W3F193-0129 dated

'

March 29, 1993) the extension request made on March 11, 1993, and the

NRC concurrence. The inspector also noted that the licensee had issued

memoranda which directed and provided guidance in formalizing the IST

basis document.

Recommendation 2 dealt with the need to specify the testing requirements

for closure of Safety Injection Valves SI-107A and 1078 in the IST

program.

In addition, it was recommended that the need for leak rate

testing of these valves be evaluated in terms of NRC Information Notice 91-56, " Potential Radioactive Leakage to Tank Vented to

Atmosphere."

. _ _ _ -

.

.

-4-

The licensee committed to add the closure testing requirements (or

submit relief requests) to the IST program as part of the program

revision that will be issued following NRC's review of Change 4 to

Revision 7 of the program. This was scheduled to occur in August 1993.

The inspector noted that relief requests and alternate testing proposals

were prepared for submittal to the NRC.

Further, the inspector noted

that the licensee performed an evaluation of leak rate testing of the

safety injection valves in terms of Information Notice 91-56. This was

documented on an Engineering Review Record dated May 20, 1992. The

evaluation summary stated that the conclusion of the original

calculation was unchanged.

Recommendation 3 dealt with Feedwater Check Valve Test

Procedure OP-903-033, " Surveillance Procedure for Cold Shutdown IST

Valve Testing," incorrectly indicating that ASME Section XI requirements

could be waived for Check Valve FW-181A upon satisfactory performance of

a maintenance visual inspection.

The licensee committed to correct the procedure and to conduct a review

of other testing procedures to determine if the same, or similar notes

existed.

The inspector verified that Procedure OP-903-033 was revised on

November 1, 1991, eliminating the erroneous note. The Event Analysis.

Reporting and Response Department performed a review of past use of this

procedure to determine if the note had ever been invoked.

It was

determined that the provisions of the note had not been used.

Further,

by Memorandum W385-92-0035 dated January 31, 1992, it was documented

that a review of all other procedures that implement IST requirements

revealed no other similar provisions.

Recommendations 4 and 5 suggested that the licensee revise Surveillance

Procedure OP-903-108,"SI Flow Balance Testing," due to its unclear

definition of which check valves were being tested and to revise the

acceptance criteria of the high pressure safety injection cold leg check

valves to reflect the guidance in NRC Generic Letter 89-04, " Guidance on

Developing Acceptable Inservice Testing Programs," respectively.

The licensee committed to revise the procedure to clarify which check

valves were being tested, and to clarify the acceptance criteria for

check valves, and to include appropriate sign-offs for each check valve

tested.

The inspector verified that the clarifications had been made, and that

the testing criteria was revised to account for the minimum flow through

each valve rather than testing the open function of these valves using

criteria for system requirements.

Sign-off locations were also

designated to show completion or verification of check valve testing.

.

.

_ _ - -

-- ..

._

_

.

,

'

-5-

These changes were incorporated into Revision 3 of Surveillance

)

Procedure OP-903-108, dated September 30, 1992.

~i

Recomendation 6 dealt with revising Relief Request 3.1.63 to provide

e

information which would indicate why certain valves in the nitrogen gas

system could not be full-stroke exercised during each refueling outage.

_,

i

The licensee comitted to revise the relief request following the NRC's

review of Revision 7 to the Waterford 3 IST program.

The inspector verified that the licensee had prepared new Relief

Request 3.2.28, which addressed partial-stroke exercising on a quarterly

i

basis and full-stroke exercising during cold shutdown conditions.

Ihis

was scheduled to be submitted with Change 4 to Revision 7 of the

Waterford 3 IST program in August 1993.

The inspector identified a recomendation in the NRC audit report that

'

apparently was not formally included in the licensee's comitment tracking

system. The audit report stated that neither the check valve program nor the

corrective maintenance program included a formal mechanism for routing

corrective maintenance work authorizations to the check valve coordinator

prior to work being performed. The concern was for a potential change that

could impact check valves performance without the check valve coordinator

being cognizant of the change.

While the licensee had not formally identified this recomendation with a

comitment tracking number, it had previously addressed the concern. The

inspector was provided with Testing Procedure MM-007-021, " Check Valve

Monitoring by Non Intrusive Tests and Inspection Methods," Revision 2, dated

,

September 17, 1992. Testing Procedure MM-007-021 provided instructions for

i

i

gathering data on check valves to used in support of Administrative Procedure

MD-001-029, " Check Valve Monitoring, Maintenance, and Trending Program,"

Revision 1, dated April 1, 1990. Test Procedure MM-007-021 addressed r quired

e

input on an attached form at designated points that must be reviewed by the

check valve coordinator prior to work' proceeding beyond that point. Further,

all disassembly activities to be performed on ASME check valves had to receive

an ASME Section XI review by the check valve coordinator.

2.2 Conclusion

The licensee's extensive peevaluation of its check valve' program exceeded the

recomendations identified in the 1991 NRC audit report. The licensee's

approach toward program improvements was proactive. All of the NRC's 1991

audit recomendations for followup are considered closed.

1

1

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - .

.-

.

ATTActMENT

I PERSONS CONTACTED

1.1

Licensee Personnel

  • R. Azzarello, Director, Design Engineering

0. Bulich, Supervisor, Mechanical / Civil Design Engineering

  • D. Dormady, Technical Assistant, Design Engineering
  • T. Gaudet, Supervisor, Operations Licensing
  • J. Hoffpauir, Superintendent,-Maintenance
  • J. Hologa, Manager, Mechanical / Civil Design Engineering
  • T. Leonard, Manager, Technical Services

B. Loetzerich, Licensing Engineer

i

  • C. Rousse, Training Engineer

M. Smith, Supervisor, Mechanical Maintenance Training

.

In addition to the personnel listed above, the inspector contacted other

personnel during this inspection period.

,

  • Denotes personnel that attended the exit meeting.

1

2

EXIT MEETING

'

i

An exit meeting was conducted on July 9,1993. During this meeting, the

inspector reviewed the scope and findings of the report. The licensee did not

identify as proprietary any information provided to, or reviewed by, the

inspector.

1

e

i

l

. .