h NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 JUNE 1993 The unit operated at an average reactor power of 94.6% and experienced one (1) shutdown during the '
period.
l i
9307200358 930715
("i; PDR ADDCK 05000382 O
Q@l R
F PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3
[
During the month of June 1993, there were no pressurizer safety valve failures or challenges.
6 i
OPERATING DATA REPORT DOCKET NUMBER: 54382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JULY,1993 COMPLETED BY:
E. G. WlEGERT TELEPHONE: 504-739-6446 OPERATING STATUS 1.
Reporting Period: June,1993 Gross Hours in Reporting Period: 720 2.
Currently Authorized Power Level (MWt): 3390 Maximum Dependable Capacity (Net MWe): 1075 Design Electrical Rating (Net MWe): 1104 3.
Power Level to which Restricted (if any) (Net MWe): N/A 4.
Reasons for Restriction (if any): N/A THIS MONTH YR TO DATE CUMULATIVE 5.
Number of Hours Reactor was Critical 696.0 4.290.0 56,683.0 6.
Reactor Reserve Shutdown Hours 7.
Hours Generator was On-line 6 84.7 4.275.0 55,871.2 8.
Unit Reserve Shutdown Hours 9.
Gross Thermal Energy Generated (MWH) 2,310,136 14.422,833 184,089,886
- 10. Gross Electrical Energy Generated (MWH) 748,390 4,719,370 61,580,840
- 11. Net Electrical Energy Generated (MWH) 712,349 4.513,293 58,684,910
- 12. Reactor Service Factor 96.7 98.8 83.2
- 13. Reactor Availability Factor 96.7 98.8 83.2
- 14. Unit Service Factor 95.1 98.4 82.1 j
- 15. Unit Availability Factor 95.1 98.4 82.1
.j 1
- 16. Unit Capacity Factor (using MDC) 92.0 96.7 80.2 l
- 17. Unit Capacity Factor (Using DER) 89.6 94.1 78.1
- 18. Unit Forced Outage Rate 4.9 1.6 3.8 1
g---
t OPERATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JULY,1993 COMPLETED BY: E G. WlEGERT 1
TELEPHONE: 504-739-6448 OPERATING DATA REPORT (Con 1)
I 19.
Shutdowns Scheduled over next 6 Months (type, date and duration of each):
N/A i
20.
If Shutdown at end of report period, estimated date of startup: N/A 21.
Unit in Commercial Operation THIS MONTH YR TO DATE CUMULATIVE
- 22. Hours in Reporting Period 720.0 4,343.0 68,083.0
- 23. Unit Forced Outage Hours 35.3 88.0
-2,178.7 24.
Nameplate Rating (Gross MWe): 1200 25.
If Changes Occur in Capacity Ratings (Items Number 2 and 24) Since Last Report, Give Reasons: N/A i
f 1
4 r
}
AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JULY,1993 COMPLETED BY:
E. G. WlEGERT TELEPHONE: 504-739-6446 MONTH JUNE DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1 1049 17 649 2
1047 18 1030 3
1050 19 1046 4
1047 20 1054 5
1051 21 1055 6
1057 22 1055 7
10J7 23 1054 8
1049 24 1054 9
1047 25 1054 10 1054 26 1055-11 1056 27 1053 12 1032 28 1053 13 1055 29 1052 14 1056 30 1053 15 698 31 N/A 16 (44)
INSTRUCTIONS On this forrnat, list the average daily unit power level in MWe-Net for each day in the reporting month.
Compute to the nearest whole megawatt.
]
~
- UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JULY,1993 COMPLETED BY:
E. G. WlEGERT TELEPHONE: 504-739-6446 REPORT FOR JUNE.1993 Type Method of Shutting F = Forced Duration Down the Reactor or Cause, Comments and Number Date S = Scheduled (Hours)
Reason (1)
Reducina Power (21 Corrective Actions 93-03 930615 F
35.3 A
3 Root cause: Failure of the square root extractorin the feed water flow circuit for feed water control system
- 1 caused feed water regulating valve #1 to fully open, which overfed steam generator #1 causing a trip due to a high levelin steam generator #1.
(1) REASON (2) METHOD A=
Equipment Failure (explain) 1=
Manual B=
Maintenance or Test 2=
Manual Scram C=
Refueling 3=
Regulatory Restriction 4=
CP:nuation from Previous Period E=
Operator Training and 5=
Power Reduction License Examination 6=
Other(explain)
F=
Administrative G=
Operational Error (explain)
H=
Other(explain)
L l