CCN 93-14098 PHILADELPHIA ELECTRIC COMPANY

~

. fe PEACH BOTTOM ATOMIC POWER STATION g*+ x%, e Mo s R.D.1, Box 208

- h Delta, Pennsylvania 17314

% A mf.*

nen wnDM-THE Imu OF EXCIRENCE (717) 456-7014 D. B. M:ller Jr.

Vce President July 14, 1993 Docket Nos. 50-277 50-278 U.S. Nuclear Regulatory Cammission Document Control Desk Washington, DC 20555

SUBJECT:

Feach Bottam Atomic Power Station Monthly Operatirg Report Gentlemen:

Enclosed are twelve copies of the monthly operating report for Peach Bottam Units 2 and 3 for the month of June 1993 forwarded pursuant to Technical Specification 6.9.1.d urder the guidance of Regulatory Guide 10.1, Revision 4.

Sincerely, DBM/

/

/P mss Enclosure cc:

R.A. Burricelli, Public Service Electric & Gas U.P. Dornsife, Ctamorucalth of Pennsylvania J.J. Lyash, USNRC Senior Resident Inspector R.I. McIran, State of Marylard T.T. Martin, Administrator, Region I, USNRC H.C. Schwemm, Atlantic Electric C.D. Schaefer, Delmarva Ptwer INTO Records Center l

l CCD693.NRC Y l 9307190207 930630 M

(

i PDR ADOCK 05000277 R

PDR

'g

NIC lbnthly Operaticrs Smery Ibach Battcm Atamic Ibwer Staticri June 1993 t

UNIT 2 Unit 2 began the month at naminal 100% power. On June 4, operators redu d load to approxirately 1070 MWe to perform a Itx1 pattern adjustnent after which the unit was Inturned to 100% power. On June 6 power was again reduced to approximately 1050 MWe as requested by the load Dispatdier. The unit was returned to 100% pcuer later on June 6th and remained there until June 24th when power was reduced to 625 MWe for repair of HPCI testable check valve. After repairs were completed the unit was returned to 100% power ard runained there for the rest of June.

INIT 3 Unit 3 began the month at naminal 100% power. On June 12th power was reduced to approximately 750 MWe for IHM calibration and "E" Tip Pachine work. Power remainecl at approximately 750 MWe until June 15th when pcuer was reduced to 630 MWe for red pattern adjustment. 7he unit was returned to approximately 904 MWe and operated in a fuel coastdown mode for the remainder of June.

r i

4 CC0693.NRC

i Docket No. 50-277 Attachment to Monthly Operatire Report for June 1993 uilT 2 REFUEIJPG INRIMNTIOT 1.

Name of facility:

Peach Bottom Unit 2 2.

Schechled date for next refueling shutdown:

Reload 10 scheduled for September 10, 1994.

3.

Scheduled date for restart following refueling:

l Restart following refueling forecast for December 8,1994.

4.

Will refuelirg or resumption of operation therefore require a technical specification change or other license amendment?

No.

If answer is yes, what, in general, will these be?

5.

Scheduled date(s) for submittiry propoccd licensing action ard rnprting information:

t N/A 6.

Important licensiry considerations associated with refuelirg, e.g., new or different fuel design or supplier, unreviewed design or perfonnance analysis rethcds, significant charges in fuel design, new operatirg procedures:

N/A CC0693.NRC

Ibcket No. 50-277 Attachment to Monthly Operating Report for June 1993 Page 2 INIT 2 REFUETJ1C INFU@RTICH (Continued) 7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:

(a)

Core - 764 Fuel Assemblies (b)

Fuel Pool - 2164 Fuel Assemblies, 58 Fuel Rods 8.

The present licensed spent fuel pool storage capacity and the size of any increa.se in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

9.

The projected date of the last refuelirg that can be discharged to the spent fuel pool assuming the present capacity:

September 2003 without full core offload capability.

Septerber 1997 with full core offload capability.

CC0693.NRC

Docket No. 50-278 Attachment to Monthly operating-Ecport for June 1993 UNIT 3 REFUFTDG INFOR!RTIOT 1.

Name of facility:

Peach Bottom Unit 3 2.

Schaluled date for next refueling shutdown:

Reload 9 scheduled for September 11, 1993 Scheduled date for restart followirg refueling 3.

Restart follcuirg refueling scheduled for November 14, 1993 Will refueliry or resumption of operation thereafter require a tedinical 4.

specification change or other license amendnunt?

Yes If answer is yes, what, in general, will these be?

92-19 Omnge safety limit MCFR for Cycle 10 93-01 ARTS /MEIIA 93-06 Drywell Rad Monitors Scheduled date(s) for submitting proposed licensire action and swrting 5.

information:

92-19 Submitted February 1993 93-01 Submitted April 1993 93-06 Scheduled for April 1993 CC0693.NRC f

I

i

\\

Cocket No. 50-278 Attachment to Monthly Operating Report for June 1993 Page 2 UNIT 3 REFUPLIIC INIURfRTION (Continued) 6.

Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

N/A 7.

The number of fuel assemblies (a) in the core ard (b) in the spent fuel storage pool:

(a)

Core - 764 Fuel Assemblics (b)

Fuel Pool - 1945 Fuel Assemblies, 6 Fuel Rods 8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been rtgaested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

9.

The projected date of the last refueling that can be discharged to the spent fuel pool amming the present capacity:

September 2004 without full core offload capability.

September 1998 with full core offload capability.

Cc0603.NRC

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50 - 277 UNIT PEACH BOTTOM UNIT 2 DATE JULY 15,1993 COMPANY PHILADELPHIA ELECTRIC COMPANY M. J. BARON r

SUPERVISOR REPORTS GROUP PEACH BOTTOM ATOMIC POWER STATION

_ TELEPHONE (717) 456-7014 EXT. 3321

.f MONTH JUNE 1993 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET)

(MWE-NET) 1 1055 17 1048 2

1049 18 1D47 3

1045 19 1043 4

1048 20 1045 5

1052 21 1052

-I 6

1060 22 1040 7

1044 23 1044 i

8 1053 24 961 9

1D60 25 1047 10 1059 26 1038 11 1055 27 1038 12 1055 28 1041 13 1056 29 1D46 14 1051 30 1041 l

15 1059 16 1049 4

i l

i

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50 - 278 UNIT PEACH BOTTOM UNIT 3 DATE JULY 15, 1993 COMPANY PHILADELPHIA ELECTRIC COMPANY M. J. BARON SUPERVISOR REPORTS CROUP PEACH BOTTOM ATOMIC POWER STATION

, TELEPHONE (717) 456-7014 EXT. 3321 MONTH JUNE 1993 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET)

(MWE NET) 1 961 17 B69 2

931 18 864 3

927 19 B60 4

938 20 853 5

938 21 B64 6

942 22 B48 7

926 23 852 8

927 24 842 9

934 25 B42 10 929 26 B34 11 921 27 834 12 752 28 827 13 741 29 828 14 745 30 823 15 745 16 874 2

1 l

OPERATING DATA REPORT DOCKET No. 50 277 DATE JULY 15,1993 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY M. J. BARON SUPERv!SOR REPORTS GROUP PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-7014 EXT. 3321 OPERATING STATUS

1. UNIT NAME: PEACH BOTTOM ' NIT 2 NOTES:
2. REPORTING PERIDO:

JUNE, 1993

3. LICENSED THERMAL POWER (MWT):

3293

4. NAMEPLATE RATING (GROSS MVE):

1152

5. DESIGN ELECTRICAL RATING (NET MWE):

1065

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 1098
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

1051

8. IF CHANCES OCCUR IN CAPACITY RATINGS (1TEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE):
10. REASONS FOR RESTRICTIONS, IF ANY:

THIS MONTH YR-TO-DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 720 4,343 166,463
12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 3,719.0 102,103.1
13. REACTOR RESERVE SHUTDDWN HOURS 0.0 0.0 0.0
14. HOURS GENERATOR ON LINE 720.0 3,562.0 98,211.2
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 16, GROSS THERMAL ENERGY GENERATED (MWH) 2,360,484 11,319,679 291,689,423
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 781,700 3,742,600 95,914,990
18. NET ELECTRICAL ENERCY GENERATED (MWH) 753,160 3,620,507 91,907,226 PAGE 1 0F 2

I OPERATING DATA REPORT (CONTINUED)

DOCKET NO. 50 - 277

]

DATE JULY 15,1993 THis MONTH YR-TO-DATE CUMULATIVE

19. UNIT SERVICE FACTOR 100.0 82.0

'59.0

20. UNIT AVAILABILITY FACTOR 100.0 82.0 59.0
21. UNIT CAPACITY F ACTOR (USING MDC NET) 99.5 79.3 52.5
22. UNIT CAPACITY FACTOR (USING DER NET) 98.2 78.3 51.8 i
23. UNIT FORCED OUTAGE RATE 0.0 5.7 14.2 -
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH)*
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESilMATfD DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY 09/16/73 INITIAL ELECTRICITY 02/18/74 COMMERCIAL OPERATION 07/05/74 k

PAGE 2 0F 2 r

h

l j

l OPERATING DATA REPORT DOCKET NO. 50 - 278 DATE JULY 15, 1993 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY i

M. J. BARON SUPERVISOR REPORTS GROUP PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-7014 EXI. 3321 OPERATING STATUS

1. UNIT NAME: PEACH BOTTOM UNIT 3 NGiES:
2. REPORTING PERIOD:

JUNE, 1993

3. LICENSED THERMAL POWER (MVT):

3293

4. NAMEPLATE RATING (CROSS MWE):

1152

5. DESIGN ELECTRICAL RATING (NET MWE):

1065

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 1098
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

1035

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE):
10. REASONS FOR RESTRICTIONS, IF ANY:

THIS MONTH YR-TO-DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 720 4,343 162,359
12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,243.0 102,301.4
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
14. HOURS GENERATOR ON-LINE 720.0 4,224.0 98,921.2
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 2,017,694 13,102,481 291,683,691
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 652.200 4,287,000 95,727,132
18. NET ELECTRICAL ENERGY GENERATED (MWH) 623,246 4,149,195 91,813,161 PAGE 1 0F 2

OPERATING DATA REPORT (CONTINUED)

DOCKET NO. 50 278 DATE JULY 15, 1993 THIS MONTH YR-TO-DATE CUMULATIVE

19. UNIT SERVICE FACTOR 100.0 97.3 60,9
20. UNIT AVAILABILITY FACTOR 100.0 97.3 60,9
21. UNIT CAPACITY FACTOR (USING MDC NET) 83.6 92.3 54.6
22. UNIT CAPACITY FACTOR (USING DER NET) 81.3 89.7 53.1
23. UNIT FORCED OUTAGE RATE 0.0 2.7 12.3
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 11/14/93
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY 08/07/74 INITIAL ELECTRICITY 09/01/74 COMMERCIAL OPERATION 12/23/74 PAGE 2 0F 2

.~n.

4 i

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50 - 277 UNIT NAME PEACH BOTTOM UNIT 2 DATE JULY 15,1993 REPORT MONTH JUNE, 1993 COMPLETED BY PHILADELPHIA ELECTRIC COMPANT

~

M. J. BARON SUPERVISOR REPDRTS GROUP PEACH BOTTOM ATOMIC POWER STATIDW TELEPHCNE (717) 456-7014 EXT, 3321 METHOD OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE l TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO f(1)

(HOURS)

(2)

REACTOR (3)

REPORT #

(4)

(5)

PREVENT RECURRENCE NO.

DATE 15 930606 S

6.0 H

4 N/A EB CKTBRK REDUCED GENERATION REQUESTED BY LDAL DISPATCHER. REACTOR NOT SHUTDOWN.

16 930624 F

8.0 A

4 CE VALVEX REPAIR OF HPCI TESTABLE CHECK VALVE 14.0 (1)

(2)

(3)

(4)

F - FORCED REASON METHOD EXH! BIT C

  • INSTRUCTIONS S SCHEDULED A - E00lPMENT FAILURE (EXPLAIN) 1. MANUAL FOR PREPARATION OF DATA i B - MAINTENANCE DR TEST 2 + MANUAL SCRAM.

ENTRY SHEETS FOR LICENSEE C - REFUELING 3 - AUTOMATIC SCRAM.

EVENT REPORT (LER)

D. REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)

FILE (NUREG-0161)

E. OPERATOR TRAINING + LICENSE EXAMlWAT10N T ADMINISTRATIVE

($)

G - DPERATIONAL ERROR (EXPLAlW)

H - OTHER(EXPLAIN)

EXHIBli ! - SAME SOURCE l

i

i UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET No. 50 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE JULY 15, 1993 REPORT MONTH JUNE, 1993 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY

~

M. J. BARON SUPERVISOE REPORTS CROUP PEACH BOTTOM ATDMIC POWER STATION TELEPHONE (717) 456-7014 EXT. 3321 METHOD OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO NO.

DATE (1) !(HOURS)

(2)

REACTOR (3)

REPORT #

(4)

(5)

PREVENT RECURRENCE 15 930612 S

108,0 H

4 N/A RC FUELXX ROD PATTERN ADJUSTHENT TO A SYMMETRIC PAT 1ERN FOR LPRM CALIBRAT!DN. REACTOR NOT SHUTDOWN 108.0 (1)

(2)

(3)

(4)

F - FORCED REASON METHOD EXHIBli G - INSTRUCTIONS S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2 MANUAL SCRAM.

ENTRY SHEETS FOR LICENSEE C - REFUELING 3 AUTOMATIC SCRAM.

EVENT REPORT (LER)

Da REGULATORY RESTRICT 10N 4a OTHER (EXPLAIN)

FILE (NUREG 0161)

E - OPERATOR TRAINING + LICENSE EXAMINATION F ADMINISTRATIVE (5)

G - OPERATIONAL ERROR (EXPLAIN)

H - OTHER(EXPLAIN)

EXHIBli 1 - SAME SOURCE.