ML20045G486

From kanterella
Jump to navigation Jump to search
Insp Rept 50-289/93-12 on 930517-21.No Violations Noted. Major Areas Inspected:Response to 930207 Forced Intrusion Into Protected Area of TMI-1,contingency Drills,Safety/ Safeguards Interface & Land Vehicle Bomb Procedure
ML20045G486
Person / Time
Site: Crane Constellation icon.png
Issue date: 07/02/1993
From: Keimig R, King E, Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20045G482 List:
References
50-289-93-12, NUDOCS 9307140031
Download: ML20045G486 (9)


See also: IR 05000289/1993012

Text

_ _ _ _ .__.

._

. _

_ _

. _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _

.

A

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-289/93-12

Docket No.

50-289

License No.

DPR-50

Licensce:

GPU Nuclear Corooration

100 Interoace Parkway

Parsippany. New Jersev 07054

Facility Name:

Three Mile Island. Unit 1

Inspection At:

Middletown. Pennsylvania

Inspection Conducted:

May 17-21.1993

Inspectors:

r(dasd 4

y

7 c)-9_3

G. C. Smith, Seniorysical Security Specialist

date

haud d. bV

9-J - 93

E. B. King, Physdecurity Inspector

date

Approved by:

h

7-88

[R. R. KeimIg, C

f, Safeguards Section

date

Division of Rad 'on Safety and Safeguards

Areas Inspected:

Licensee and local law enforcement agency (LLEA) response to the

February 7,1993, forced intrusion into the protected area of TMI-1; the licensee's intrusion

protection strategy; contingency drills; safety / safeguards interface; assessment system; and land

i

vehicle bomb procedure.

l

Results:

Weaknesses were identified in the LLEA response and the licensee's intruJon

protection strategy. The licensee was aware of these weaknesses prior to the inspection and, J

the time of this inspection, was in the process of developing corrective actions. No violations

of the NRC-approved Physical Security program plans were identified.

l

l

h

l

l

9307140031 930702

PDR

ADOCK 05000289

O

PDR

. .. . .

.

_ - _ _ _ _ _ _ _ _ _ _ _ _

,

f

,

DETAILS

1.

Key Persons Contacted

GPU Nuclear Corporation

  • T. G. Broughton, Director, TMI-l
  • M. A. Nelson, PRG Chairman, TMI-1
  • R. E. Rogan, TMI Licensing Director
  • M. K. Pastor, Nuclear Security Director
  • J. F. Stacey, Site Security Manager
  • S. P. Mervine, Support Training Manager
  • R. G. Goodrich, Senior Security Supervisor
  • S. E. Williams, Nuclear Safety Compliance
  • D. F. Moyer, Lead Instructor, Protection Training

D. W. Atherholt, Lead Operations Engineer

'

D. Barry, Security Engineer

D. Hassler, Licensing Engineer

,

Pennsvivania Decartment of Environmental Resources

'

  • R. Janatti, Nuclear Engineer

U. S. Nuclear Reculatory Commission

  • R. Cooper, Director, Division of Radiation Safety and Safeguards
  • M. Evans, Senior Resident Inspector

i

  • F. Young, Senior Resident Inspector

-

D. Beaulieu, Resident Inspector

R. Keimig, Chief, Safeguards Section

Pennsvivania State Police

-

K. E. Doutt, Captain

>

  • denotes those present at the exit meeting

.

'

The inspectors also interviewed members of the licensee's security, operations,

maintenance and licensing staffs.

2.

Backcround

'

On February 7,1993, an intruder drove a vehicle through a locked vehicle gate in the

TMI protected area (PA) fence and crashed through a metal roll-up door into the turbine

building. 'Ihe intruder remained in the PA for approximately four hours before being

apprehended.

,

--

.

,

3

Because of the potential security significance and potential regulatory questions raised by-

the event, the NRC Executive Director for Operations established an Incident

Investigation Team (IIT). The IIT reviewed the event and issued NUREG-1485 in April

1993 to document its findings and conclusions. This inspection was conducted to review

the potential compliance issues identified by the IIT in the area of physical security.

3.

NRC Review of Potential Reculatory Compliance Issues

A.

Licensee Response to the Event

.

'

The inspectors reviewed the licensee's NRC-approved Physical Security Plan,

Contingency Plan and Training and Qualification Plan (the Plans), Security

Procedure A420-IMP-1530.06, dated 12/16/92, " Physical Protection of Protected

and Vital Areas," chronologies developed by the licensee and the NRC after the

incident, and interviewed alarm station operators and response personnel. The

results of the reviews and interviews disclosed the following:

e

Several of the Site Protection Officers (SPOs) who were on patrol when

the event began were near the response positions identified in procedure

A420-IMP-1530.06 and immediately responded to those positions.

The SPOs who initially went to those response positions did not have

shotguns because they were not carrying a shotgun and would have had

to leave their assigned response positions to obtain one. As other SPOs

who were called in from horne arrived onsite, shotguns were delivered to

those SPOs. The licensee recognized that a shotgun is preferred over a

handgun as a response weapon and, before the event, was in the process

of examining options to make response weapons more readily available to

response personnel.

The licensee's decision in this regard will be

reviewed during a subsequent inspection. (Inspector Follow-up Item

50-289/93-12-01)

SPOs acting as escorts and some SPOs acting as search officers were

dispatched, armed with shotguns. The SPOs who did not have shotguns

elected not to carry them because they would be cumbersome when

searching in close quarters and climbing ladders.

The applicable

procedure, A420-IMP-1530.06, did not require the SPOs to be armed with

shotguns. Additionally, the licensee's tactical training program did not

include close quarters training with long guns.

This is noted as a

weakness in the training program and will be reviewed in a subsequent

inspection. (Inspector Follow-up Item 50-289/93-12-02)

e

At the time of the incident, a SPO, who was also designated as an armed

responder, was performing a patrol outside of the PA, and another SPO,

,

-

i

4

also designated as an armed responder, was located just outside tue PA,

j

in the Process Center. The location of these armed responders did not

conflict with the NRC-approved Physical Security Plan because the

locations of the armed responders and other security personnel on duty are

not specified in the Plan.

At the request of the licensee's Emergency Director, (the Director,

Operations and Maintenance) the patrols identified in procedure A420-

IMP-1530.06 were not conducted for several hours after the event began

because the SPOs who would have conducted those patrols were involved

,

in other response activities. This departure from the procedure appeared

1

to be appropriate under the circumstances.

Central and secondary alarm station (CAS/SAS) activities and actions

during the event were determined by the inspectors to be in accordance

with applicable procedures. However, due to the high level of activity in

the CAS during the event, the CAS operator's ability to perform all

required tasks was severely challenged. The licensee recognized this

problem, and, in an attempt to correct it, revised the response procedures

since the event to require a second operator in the CAS during an event.

The efficacy of this action will be reviewed during a subsequent

inspection. (Inspection Follow-up Item 50-289/93-12-03)

'

B.

Local Law Enforcement Acency (LLEA) Resoonse to the Event

The inspectors reviewed the licensee's Plans, the Memorandum of Understanding

(MOU) with the Pennsylvania State . Police (PSP), and interviewed the

Commanding Officer of the local law enforcement ageng (LLEA) having

jurisdiction at TMI and licensee security management personnel. The results of

the inspectors' reviews and interviews were as follows:

,

The then current (May 4,1992) MOU with the PSP identified the

numbers of PSP Troopers that would be able to respond within specified

time frames. During the event, the numbers of troopers identified in the

MOU did not arrive within the time frames specified.

This was

'

considered a weakness.

..

The Commanding Officer stated that the commitments in the 1992 MOU

were based on estimates and, when it was determined after the event that

the committed numbers of troopers could not be guaranteed within the

specified time frames, the MOU was revised by the PSP. The revised

'

MOU reduces the number of trcyrs who would mitially respond and

extends the time for the remaining troopers to respond.

1

.

.

5

The only LLEA personnel who had participated in contingency training

with the licensee's security organization were members of the PSP Special

Emergency Response Team (SERT). The SERT arrived approximately

three hours after the event began.

The inspectors determined through review of applicable procedures and

discussions with the licensee that the licensee had already initiated action

to revise its contingency response procedures to deal with a protracted

LLEA response time. The adequacy of the licensee's action in this regard

will be reviewed during a subsequent inspection. (Inspection Follow-up

Item 50-289/93-12-04).

C.

Licensee Intrusion Protection Strategy

Based on a review of U.S. NRC Regulatory Guide 5.54, the Plans, the

circumstances, and interviews with personnel, the inspectors determined that the

licensee's intrusion protection strategy was in compliance with the Plans.

However, the inspectors determined that the following conditions limited the

effectiveness of the licensee's response:

The responsibility matrices found in the licensee's Contingency Plan were

summarized, as required, in a procedures summary for each postulated

event.

The procedure summaries are intended to be simplified

presentations of the assigned security force responsibilities for use in

training and implementation of the Plan.

They do not have to be

submitted to the NRC for approval. The adequacy of the procedures

summaries for their intended uses appeared marginal based upon the

j

following.

The CAS operator on duty during the event expressed frustration to the

inspectors over the lack of details in the Contingency Plan procedures

summaries with regard to command and control at the onset of the event.

The operator resorted to a recently developed and implemented procedure,

j

A420-IMP-1530.06 (12/16/92), that contained specific response and

i

protective strategy needed to mitigate the event. This procedure resulted

from tne licensee's change in protective and tactical strategies that

,

occurred in late 1992. for all contingency events. Some confusion on the

part of the CAS operator apparently resulted from the limited amount of

training received since the new procedure was implemented.

Another weakness in command and control was identified during the

event. As a result of the limited initial LLEA response, the licensee's

planned response to such an event could not be carried out. Even though

the number of SPOs on site at the time of the event was as committed to

- -

J

.

.

.

6

in the Plan, there were not sufficient officers to establish and staff a

command post and conduct other operations until additional LLEA officers

and SPOs arrived onsite.

A weakness was also identified in search and clear operations. Initiation

of searches for the intruder was delayed because of limited initial LLEA

response and because the SPOs on duty remained at their response

locations, per procedure. As additional SPOs arrived on site, searches

began and continued until the intruder was apprehended.

The SPO who told the Control Room Operators to lock the fire doors did

so only because that action was always taken during previous security

drills; it was not required by security procedures. Locking the doors

inhibited implementation of the licensee's emergency callout procedures.

(This issue is being reviewed further by the Region I Emergency

Preparedness Section.)

To correct these specific weaknesses, the licensee was taking or had taken the

following actions:

Security procedure A420-IMP-i530.06, " Physical Protection of Protected

and Vital Areas," was revised to address the immediate establishment of

a command post when a security event occurs. Additionally, a new

procedure that integrates the LLEA and licensee security force response

activities was being developed.

New procedures were being developed for incorporation into the

Contingency Plan (CP).

The procedures will address the Security

Command and Control Center, Land Surface Vehicle Bomb Threat, Use

of 10 CFR 50.54 (x) and (y) (addresses reasonable departure from a

license condition or technical specification in an emergency if approved

by a licensed senior operator), Site Protection Force Contingency

Response, and the responsibilities of the Security Operations Shift

Supervisor, Central Alarm Station Operator and Secondary Alarm Station

Operator.

A call out process was being developed to ensure the availability of

additional SPOs to respond to an event, when required.

The licensee has taken or plans to take additional significant measures to enhance

the physical security of the station. These measures are exempt from public

disclosure under 10 CFR 73.21, Safeguards Information, and, therefore, are not

further discussed in this report.

However, they will be reviewed during

subsequent inspections. (Inspector Follow-up Item 50-289/93-12-05)

_- ..

..

- - .

-

.-

-

...

,

.

e

7

i

D.

Licensee Contineency Drilh

Based on a review of records of drills conducted between 1991 and this

inspection, and interviews with appropriate Training Department and Security

Department personnel, the inspectors determined that the licensee was conducting

approximately 40 contingency event drills per year, that Security Department

management was actively involved in the conduct of these drills, and that the

i

critiques of the drills were being utilized as an effective mechanism to provide

feedback for improvement. The inspectors also reviewed the effectiveness of the

licensee's corrective action program for the previous two years. They found only

a small number of repetitive weaknesses identified and a declining trend in those

'

that were identified.

Additionally, shortly prior to the event, the licensee

developed enhanced protective strategies for the station, began to train its SPOs

in improved tactical response and conducted more comprehensive dril6 to

-

exercise that training in conjunction with the new protective strategies.

-

The inspectors reviewed the drill scenarios utilized over the past two years

i

and found that the licensee was conducting drills that addressed the more

j

sigmficant contingency events identified in the CP.

A review of training records indicated that a critique was conducted after

j

!

cach drill and a copy of the critique forwarded to the Training Department

l

for review and tracking. Drill weaknesses were analyzed and tracked and,

j

!

if a repetitive weakness was identified, it was incorporated into the

training plans as a " lessons learned" issue.

l

The licensee effectively used the training program, in lieu of procedural

,

revisions, to correct weaknesses identified during drills.

This was

because the CP procedures summaries were not detailed procedures but

rather listings of actions to be taken and decisions to be made which did

'

not lend themselves to meaningful revisions.

Regularly scheduled meetings were held between Security Department and

,

i

Training Department management to discuss training issues and, if

j

needed, to develop additional training to address security operations

concerns.

E.

Safetv-Safeeuards Interface - Emereency Access to Vital Areas (VM

The inspectors reviewed the Plans, the Vital Area (VA) key procedures and

,

inventories, and interviewed security personnel, reactor operators and auxiliary

,

operators. The results of the reviews and interviews were as follows:

.

N

w

-

e

a

- - , . .

-

-

,-

,

,

.,

.

O

8

All security personnel on-shift at the time of the event carried VA hard

keys and also had access to the VAs via key cards and the " zap in"

system.

Five operations personnel carried VA hard keys at the time of the event.

They were the Shift Foreman, the Control Room operator, and three

auxiliary operators.

When interviewed during this inspection, all

operators and auxiliary operators could identify the VA keys on the key

rings.

,

The licensee is revising its procedure for emergency access to vital areas.

It will be reviewed during a subsequent inspection. (Inspector Follow-up

Item 50-289/93-12-06)

F.

Assessment System

The inspectors reviewed the Plans, the preventive maintenance program for the

,

assessment system, interviewed CAS and SAS operators and' the Security

Instrument and Control (I&C) technician who maintains the system, and observed

the system in operation.

The results of the reviews and interviews were as follows:

The assessment system was designed, installed, maintained, and operated

in accordance with the NRC-approved Security Plan. At the time of this

inspection, the licensee was evaluating the system for further possible

enhancements.

The system received routine, scheduled maintenance by a dedicated I&C

technician and was being monitored, on a daily basis, for clarity, contrast,

and operability.

,

G.

Land Vehicle Bomb Procedure

.

The inspectors conducted a review of the licensee's Land Vehicle Bomb-

Contingency Procedure contained in GPU Nuclear Security Department procedure

A400-PLN-1530-01, " Security Standby / Counter Measures", Rev. O, dated

1/29/93. That procedure was preceded by another Security Department procedure

which was reviewed by an NRC inspector in October 1990. The inspectors

'

determined that the procedure satisfied the requirements of the NRC Generic Letter 89-07, which identified the requirements for land vehicle bomb

I

contingency planning. The inspectors also determined, based on observations and

discussions with security supervisors, that they were knowledgeable of the

!

procedure, its content and location. The licensee's procedure detailed short-term

.

.

.

9

actions that could be taken to protect against attempted radiological sabotage

involving a land vehicle bomb if such a threat were anticipated.

4.

Exit Meetine

The inspector met with the licensee representatives identified in paragraph I at the

conclusion of the inspection on May 28, 1993. A representative of the Pennsylvania

Department of Environmental Resources and the Region I Director, Division of Radiation

.

'

Safety and Safeguards also attended the exit meeting. At the exit meeting the purpose

and scope of the inspection were reviewed and the findings presented. The licensee

acknowledged the inspection findings.

,

>

?

,

h

>

b