ML20045F321

From kanterella
Jump to navigation Jump to search
Requests That Util Staff Provide NRC W/Schedule of Progress to Date & Monthly Updates Until New Reception Ctr, Functional.Three Ltrs Re Impending Loss of Wellesley Reception Ctr,Scheduled for December 1993,encl
ML20045F321
Person / Time
Site: Pilgrim, Seabrook
Issue date: 06/29/1993
From: Eaton R
Office of Nuclear Reactor Regulation
To: Boulette E
BOSTON EDISON CO.
Shared Package
ML20045F323 List:
References
NUDOCS 9307070184
Download: ML20045F321 (3)


Text

m

Docket No. 50-293 June 29, 1993 Mr. E. Thomas Boulette, Ph.D Senior Vice President - Nuclear Boston Edison Company Pilgrim Nuclear Power Station i

RfD #1 Rocky Hill Read Plymouth, Massachusetts 02360

Dear Mr. Boulette:

SUBJECT:

REPLACEMENT FACILITY FOR THE WELLESLEY RECEPTION CENTER Enclosed are three letters related to the impending loss of the Wellesley Reception Center (WRC), currently scheduled for December 1993.

In the letter to Mr. Congel, dated June 9,1993, the Federal Emergency Management Agency (FEMA) asked the U.S. Nuclear Regulatory Commission (NRC) to coordinate with you and the Seabrook licensee to provide whatever assistance is needed by the Massachusetts Emergency Management Agency (MEMA) to resolve the issues of a replacement facility before December 1993.

I know your staff is working to effect a timely solution to this issue, and I would request that your staff provide me with a schedule of your progress to date, and monthly updates until the new reception center is functional.

1 feel it is important to emphasize to you the concern we share with FEMA that an alternate reception center be identified, that trained personnel be available, and that appropriate plan and procedure changes be made at the time the WRC is no longer available.

Sincerely, Original signed by:

Ron'ald B. Eiiton, 3enior Project Manager Project Directorate I-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Enclosures:

1.

Ltr. 6/9/93 FEMA to NRC 2.

Ltr. 6/8/93 FEMA to MEMA 3.

Ltr. 4/27/93 MASS Highway to BECO cc w/ enclosures:

See next page DISTRIBUTION:

PDI-3 Reading WButler OGC RErickson, 9H15 Docket File SVArga Slittle ACRS (10)

NRC & Local PDRs JCalvo REaton JLinville. RI 0FFICE PDI-3:LA PDI-g;J'M PEPN/

PDI-3:Df NAME SLitbb REathn:dt REhson WButler DATE 6//f/93 h /28/93 h/93 b/6/93 0FFICIAL RECORD COPY I

DOCUMENT NAME: A:\\WRC.LTR I"?h" fh k'-* "

Y 9307070184 930629 PDR ADOCK 05000293 P

PDR p

,. ~

s * 'ico s

p

[w d

% iM{f@jl s' ef "

E UNITED STATES NUCLEAR REGULATORY COMMISSION t[i (,/

WASHINGTON, D.C, 20555-0001 June 29, 1993 1

Docket No. 50-293 Mr. E. Thomas Boulette, Ph.D Senior Vice President - Nuclear Boston Edison Company Pilgrim Nuclear Power Station RFD #1 Rocky Hill Road Plymouth, Massachusetts 02360 t

Dear Mr. Boulette:

SUBJECT:

REPLACEMENT FACILITY FOR THE WELLESLEY RECEPTION CENTER Enclosed are three letters related to the impending loss of the Wellesley Reception Center (WRC), currently scheduled for December 1993.

In the letter to Mr. Congel, dated June 9, 1993, the Federal Emergency Management Agency (FEMA) asked the U.S. Nuclear Regulatory Commission (NRC) to coordinate with you and the Seabrook licensee to provide whatever assistance is needed by the Massachusetts Emergency Management Agency (MEMA) to resolve the issues of a replacement facility before December 1993.

I know your staff is working to effect a timely solution to this issue, and I would request that your_ staff provide me with a schedule of your progress to date, and monthly updates until the new reception center is functional.

I feel it is important to emphasize to you the concern we share with FEMA that an alternate. reception center be identified, that trained personnel be available, and that appropriate plan and procedure changes be made at the time.

the WRC is no longer available.

Sincerely, gf C

onald B. Eaton, Senior Project Manager

')roject Directorate I-3 Division of Reactor Projects - I/II Office of Nuclear P.eactor Regulation

Enclosures:

1.

Ltr. 6/9/93 FEMA to NRC 2.

Ltr. 6/8/93 FEMA to MEMA 3.

Ltr. 4/27/93 MASS Highway to BECO cc w/ enclosures:

See next page I

s Mr. L. Thomas Boulette Pilgrim Nuclear Power Station cc:

i Mr. Eoward S. Kraft, Mr. H. Vernon 0heim Vice President of Nuclear Manager, Reg. Affairs Dept.

I Operations & Station Director Pilgrim Nuclear Power Station i

Pilgrim Nuclear Power Station RFD #1 Rocky Hill Road RFD #1 Rocky Hill Road Plymouth, Massachusetts 02360 Plymouth, Massachusetts 02360 Mr. David F. Tarantino Keslaent inspector Nuclear Information Manager U. S. Nuclear Regulatory Commission Pilgrim. Nuclear Power Station Pilgrim Nuclear Power Station RFD #1, Rocky Hill Road Post Office Box 867 Plymouth, Massachusetts 02360 Plymouth, Massachusetts 02360 Mr. Thomas Rapone Chairman, Board of Selectmen Secretary of Public Safety r

11 Lincoln Street Executive Office of Public Safety Plymouth, Massachusetts 02360 One Ashburton Place Boston, Massachusetts 02108 i

Office of the Commissioner Massachusetts Department of Mr. David Rodham, Director Environmental Protection Massachusetts Emergency Management One Winter Street Agency Boston, Massachusetts 02108 400 Worcester Road P.O. Box 1496 Office of the Attorney General Framingham, Massachusetts 01701-0317' One Ashburton Place Attn:

James Muckerheide 20th Floor Boston, Massachusetts 02108 Chairmen, Citizens Urging Responsible Energy Mr. Robert M. Hallisey, Director P. O. Box 2621 Radiation Control Program Duxbury. Massachusetts 02331 Massachusetts Department of Public Health Citizens at Risk 305 South Street P. O. Box 3803 Boston, Massachusetts 02130 Plymouth, Massachusetts 02361 I

Regional Administrator, Region I W. S. Stowe, Esquire U. S. Nuclear Regulatory Commission Boston Edison Company 475 Allendale Road 800 Boylston St., 36th Floor King of Prussia, Pennsylvania 19406 Boston, Massachusetts 02199 Mr. Paul J. Hamilton Licensing Division Manager Boston Edison Company 25 Braintree Hill Park l

Braintree, Massachusetts 02184

{

I i