i May 25, 1993 o

s Docket No.

50-483 DISTRIBUllpB Docket File NRC & Local PDRs JRoe PDill-3 Reading Mr. Donald F. Schnell JZwolinski CMcCracken Jllannon AMasciantonio Senior Vice President - Nuclear MRushbrook EGreenman Union Electric Company LRWharton ACRS (10)

Post Office Box 149 OGC PDlll-3 Gray St. Louis, Missouri 63166

Dear Mr. Schnell:

SUBJECT:

CALLAWAY NUCLEAR PLANT - RESPONSE 10 NRC BULLETIN 92-01, SUPPLEMENT 1, " FAILURE OF THERMO-LAG 330 FIRE BARRIER SYSTEM" (TAC NO. M83855)

By letter dated September 30, 1992, you provided a response to NRC Bulletin l

92-01 for the Callaway Nuclear Plant.

Your response stated that compensatory measures have been implemented consistent with the plant Technical Specifi-cations.

You also stated that you would continue to monitor industry testing for new data that should be applied to your Thermo-Lag installations and would actively participate in NUMARC efforts to reach a final resolution.

We have reviewed your response and find it acceptable.

Please inform us of the completion of any additional corrective actions that are taken.

Further NRC review, if any, will be performed by inspection or audit, i

The information requested by this letter is within the scope of the overall l

burden estimate in Generic Letter 92-08, which was an average of 300 person-I hours for each addressee's response, this request is covered by office of Management and budget Clearance number 3150-0011, which expires June 30, 1994.

This action closes TAC No. M83855.

Sincerely, Origitml Signed 11y :

L. Raynard Wharton, Project Manager Project Directorate 111-3 Division of Reactor Projects - Ill/lV/V Office of Nuclear Reactor Regulation cc:

See next page

(

l OFFICE PD3-3:LA4 PD3-3:PM SPJb,BCg PD3k:[D MRushokk-

,,.LRWh a rt on dicCrab Jllannon NAME DA1E

$/)I93

[fS/24 /93

(/,23[93

[/I 93

/

OFFICIAL RECORD l

Document Name: G:\\CALLAWAY\\ CAL 83855 270123 E{@EC.L.hWPy 9306070041 930525 20\\

i PDR ADOCK 050004B3

{

G PDR 4

f(

UNITED STATES NUCLEAR REGULATORY COMMISSION y

)#(' g y

WASHINGTON, D. C. 20555

=

g May 25, 1993 Docket No. 50-483 Mr. Donald F. Schnell Senior Vice President - Nuclear Union Electric Company Post Office Box 149 St. Louis, Missouri 63166

Dear Mr. Schnell:

SUBJECT:

CALLAWAY NUCLEAR PLANT - RESPONSE TO NRC BULLETIN 92-01, SUPPLEMENT 1, " FAILURE OF THERM 0-LAG 330 FIRE BARRIER SYSTEM" (TAC NO. M83855)

By letter dated September 30, 1992, you provided a response to NRC Bulletin 92-01 for the Callaway Nuclear Plant.

Your response stated that compensatory measures have been implemented consistent with the plant Technical Specifi-cations.

You also stated that you would continue to monitor industry testing for new data that should be applied to your Thermo-Lag installations and would actively participate in NUMARC efforts to reach a final resolution.

We have reviewed your response and find it acceptable.

Please inform us of the completion of any additional corrective actions that are taken.

Further NRC review, if any, will be performed by inspection or audit.

The information requested by this letter is within the scope of the overall burden estimate in Generic Letter 92-08, which was an average of 300 person-hours for each addressee's response.

This request is covered by Office of Management and Budget Clearance number 3150-0011, which expires June 30, 1994.

This action closes TAC No. M83855.

Sincerely, El y

L. Raynard Wharton, Project Manager Project Directorate III-3 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation cc: See next page

>8 Mr. D. F. Schnell Callaway Plant Union Electric Company Unit No. I cc:

Cermak Fletcher Associates Mr. Bart D. Withers i

18225 Flower Hill Way #A President and Chief Gaithersburg, Maryland 20879-5334 Executive Officer Wolf Creek Nuclear Operating Corporation Gerald Charnoff, Esq.-

P.O. Box 411 i

Thomas A. Baxter, Esq.

Burlington, Kansas 66839 Shaw, Pittman, Potts & Trowbridge 3

2300 N. Street, N.W.

Mr. Dan I.. Bolef, President.

Washington, D.C.

20037 Kay Drey, Representative Board of Directors Coalition Mr. S. E. Sampson for the Environment-Supervising Engineer, 6267 Delmar Boulevard Site Licensing-University City, Missouri 65130 Union Electric Company y

Post Office Box 620 Fulton, Missouri 65251 U.S. Nuclear Regulatory Commission Resident Inspectors Office RR#1 Steedman, Missouri 65077 Mr. Alan C. Passwater, Manager Licensing and fuels Union Electric Company Post Office Box 149 St. Louis, Missouri 63166 Manager - Electric Department Missouri Public Service Commission 301 W. High Post Office Box 360 Jefferson City, Missouri 65102 Regional Administrator U.S. NRC, Region III l

799 Roosevelt Road Glen Ellyn, Illinois 60137 Mr. Ronald A. Kucera, Deputy Director Department of Natural Resources P.O. Box 176 Jefferson. City, Missouri ~65102

- - -. - -