Discusses Special Audit of Control Processes for Commitments That Affect Facility Current Licensing Basis
ML20044G054
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 05/20/1993
From: Nerses V
Office of Nuclear Reactor Regulation
To: Mcmeekin T
DUKE POWER CO.
References
GL-88-14, GL-89-13, NUDOCS 9306010368
Download: ML20044G054 (3)


Text

.

I

[paatct l

6 4

UNITED STATES l

[

j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 205M4001

\\...../

May 20, 1993 Docket No. 50-369 l

j and 50-370-l j

Mr. T. C. McMeekin Vice President, McGuire Site Duke Power Company l

12700 Hagers Ferry Road Huntersville, North Carolina 28078-8985 Dear Mr. McNeekin.

SUBJECT:

SPECIAL AUDIT OF CONTROL PROCESSES FOR COM>ilTMENTS THAT AFFECT THE MCGUIRE STATION CURRENT LICENSING BASIS l

The Office of Nuclear Reactor Regulation is conducting audits at several reactor plants to assess the processes used by licensees in controlling i

commitments that affect their facility's current licensing basis. The staff's i

study of current licensing basis is.important to the Nuclear Regulatory l

Commission (NRC) with respect to activities involving license renewal. This effort follows up on earlier NRR audits that recognized variations in the l

methods licensees use to manage their current licensing basis and their i

commitments made to the NRC. The current audits will-assess the processes in more depth and evaluate the safety significance of any process weaknesses l

identified. McGuire Station was selected as one of several stations that we are auditing.

In an attempt to minimize the impact on your staff, the selection of McGuire Station and the audit plans and schedule were discuss 2d with Mr. R. Sharpe, McGuire Compliance Manager, and June 7 was agreed upon for l

beginning the audit.

i The audit team will arrive on site June 7, 1993, and the audit is expected to take five days. The team is comprised of Eric Leeds (Team Leader), Steve Stein and Rebecca Ncase. The team will conduct an entrance meeting on the i

afternoon of June 7, during which the team would appreciate a brief presentation on your programs and processes for controlling the McGuire Station licensing basis. Specifically, the presentation should address maintaining and updating your FSAR, managing commitments made to the NRC, and reporting changes to commitments made to the NRC.

Emphasis should be placed on how you determine the basis for reporting changes to the plant, procedures, and previously made commitments.

The team will evaluate the control programs for your licensing basis by reviewing several previously selected issues. These issues are:

1.

10 CFR 50.62 ATWS 2.

Generic Letter 88-14:

Instrument Air System Problems Affecting Safety-Related Equipment 3.

Generic Letter 89-13:

Service Water System Problems Affecting Safety-Related Equipment 1

9305,010368 930520 PDR ADOCK 05000369 yn^r m:;r m yp,y pp y

'-r l Q p

PDR

+-

s h

/

e, Mr. T. C. McMeekin May 20, 1993 4.

NUREG 0737 - I.C.5:

Procedures for Feedback of Operating Experience to Plant Staff 5.

Bulletin 85-01:

Steam Binding of Auxiliary Feedwater Pumps 6.

NOVs identified in Inspection Reports 50-369/50-370-86-21, 50-369/370-88-33, 50-360/50-370-89-11, 50-370/87-35, 50-369/50-370-90-11 7.

LERs 369-87-14-1, 370-87-04-01, 369-88-02, 370-89-03-01, and 370-90-06.

In order to expedite our review and possibly reduce audit time, we ask that you have the documentation associated with these issues prepared for the team to review upon their arrival.

At the conclusion of the audit, the team will conduct an exit meeting and share its findings with your staff.

If you have any questions regarding this effort, please call me (301-504-1484) or Mr. Eric Leeds at (301) 504-1133.

Sincerely, ORIGINAL SIGNED BY:

Victor Nerses, Project Manager Project Directorate 11-3 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation cc:

See next page DISTRIBUTION Docket File-NRC & Local PDRs PDII-3 R/F S. Varga G. Lainas D. Matthews L. Berry V. Nerses OGC p

f ACRS (10)

I j E. Merschoff, RII g

3 P

1-3 NRR/DRP Ih 11-3 LA:PDIIN[+

LBerry e rst Eleeds /

DMatthews l

SBc/93 7 /4 /93

(/2o/93 g/g/33 0FFICIAL RECORD COPY DOCUMENT NAME:

G:\\MCGUIRE\\MCGUIRE.LTR l

~..

t l

.t Mr. T. C. McMeekin i

Duke Power Company McGuire Nuclear Station j

cc-l Mr. A. V. Carr, Esquire Mr. Dayne H. Brown, Director Duke Power Company Department of Environmental, 422 South Church Street Health and Natural Resources Charlotte, North Carolina 28242-0001 Division of RadiationLProtection P. O. Box 27687 County Manager of Mecklenberg _ County Raleigh, North Carolina 27611-7687

)

720 East Fourth Street l

Charlotte, North Carolina 28202 Mr. Alan R. Herdt, Chief Project Branch #3 J

Mr. R. O. Sharpe U. S. Nuclear Regulatory Commission 1

Compliance 101 Marietta Street, NW. Suite 2900 l

Duke Power Company Atlanta, Georgia 30323 l'

McGuire Nuclear Site 12700 Hagers Ferry Road Ms. Karen E. Long l

Huntersville, NC 28078-8985 Assistant Attorney General l

North Carolina Department of J. Michael McGarry, III, Esquire Justice Winston and Strawn.

P. O. Box 629 1400 L Street,'NW.

Raleigh, North Carolina ' 27602 Washington, DC 20005 Mr. G. A. Copp Senior Resident Inspector Licensing - EC050 I

c/o U. S. Nuclear Regulatory Duke Power Company l

Commission P. O. Box 1006

)

12700 Hagers Ferry Road Charlotte, North Carolina 28201-1006 Huntersville, North Carolina 28078 1

Regional Administrator, Region II Mr. T. Richard Puryear U.S. Nuclear Regulatory Commission Nuclear Technical Services Manager 101 Marietta Street, NW. Suite 2900 Carolinas District Atlanta, Georgia 30323 Westinghouse Electric Corporation P. O. Box 32817 Charlotte, North Carolina 28232 l

Dr. John M. Barry Mecklenberg County Department of Environmental Pr'otection 700 N. Tryon Street Charlotte, North Carolina 28202 1