ML20043H149

From kanterella
Jump to navigation Jump to search
Insp Rept 50-395/90-16 on 900515-16.No Violations or Deviations Noted.Major Areas Inspected:Control of Fuel Assembly Operations in Spent Fuel Pool,Response to NRC Bulletin 89-003 & Exams of Used Fuel Assemblies
ML20043H149
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 05/31/1990
From: Belisle G, Burnett P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20043H144 List:
References
50-395-90-16, IEB-89-003, IEB-89-3, NUDOCS 9006220080
Download: ML20043H149 (9)


See also: IR 05000395/1990016

Text

~

r

.

n'

,

[p* b40s,q'o

UNITEG STATES

NUCLEAR REGULATORY COMMisslON

'

' f

RtGION ll

101 MARIETTA STREET,N.W.

g

g

2

ATLANT A, GEORGI A 30323

e...+$

Report No.:

50-395/90-16

Licensee: South Carolina Electric and Gas Company

Columbia, SC 29218

Docket No.:

50-395

License No.: NPF-12

j-

Facility Name:

V. C. Sunrner

Inspection Conducted: ' May 15 - 16, 1990

i

Inspector:

ed

.,2#

~///s~sf

P

T. EfuFnett

Date pRjned

AccompanyingPersonnyl:,,G.A.Belisle

Approved by:

O

7(

( ef

f!?/!/d

G. A. BelislerUhief

Date Signed

I

Test Programs Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine ' announced inspection addressed the areas of control of fuel

assembly o)erations in the spent fuel pool, response to NRC Bulletin 89-03,

Potential

Loss of Required Shutdown Margin During Refueling Operations, and

final' core 6 verification; examinations of used fuel- assemblies; control of

debris in the primary system; and fuel cycle 6 core analyses.

Results:

Management attention and initiatives in response to mislocation of_ four fuel

assemblies in the spent fuel pool were prompt and thorough.

The immediate

corrective actions were appropriate, and the completion dates for reviews of

potential. additional, long-term corrective actions are consistent with the

current schedule for-the next refueling. No violations of reactivity limits in

the spent fuel pool were created by the mislocations.

(Paragraphs 2.aand2.b)

Control of fuel assembly locations, during fuel loading into the core, to

preclude creating an unanalyzed critical array was addressed satisfactorily in

the fuel shuffle- procedure.

The loading of core 6 was verified to be correct

,

by video examination of the completed core.

(Paragraph 2.c)

l

2

l.

Examinations of fuel discharged from core 5, using ultrasonic testing and

high-definition video, identified five-failed fuel pins.

No mechanism has been

positively identified for the failure. of one pin in a VANTAGE 5 fuel assembly.

.

Failures of' the pins in other assemblies, without lower debris filters, are

'

'

9006220000 900604

,

PDR

ADOCK 05000395

3

O.

PNV

l

b

-

.

.

x

. ..

8 .

-

,

.

%

i

t

  • .

.

,

!

.:

2

i

!

consistent with debris-induced fretting of the lower portion of the pin and

>

subsequent secondary hydriding of the cladding. (Paragraph 3)

i

.

?

Potential sources of debris in the reactor coolant system include material torn

from fuel assembly grids.

Control of material to avoid adding debris to the-

i

reactor coolant . system, during the rece it removal of the bypass loops for

resistance thermometers and installation of thermal wells, appeared to be

adequate.-(Paragraph 4)

No violations' or deviations were identified.

!

!

,

9

!

s

t

D

!

!

.

B

,

4

t

t

i

,

'

t

^'

s

-

n

-y

- - ,

,, . - - - -

-

--_.y

^~

p

.

'

.

.,

.

i

i

REPORT DETAILS

'

1.

Persons Contacted

L

Licensee Employees

  • L. Cartin, Senior Engineer, Margin Management
  • R. Clary, Manager, Design Engineering
  • H. Donnelly, Senior Engineer, Regulatory Interface

"

  • B. Johnson, Supervisor, Core Engineering
  • A. Koon, Manager, Nuclear Licensing
  • G. Liu, Engineer Independent Safety Engineering Group

$

'

  • K. Nettles, General Manager, Nuclear Safety
  • C

Price, Manager, Technical Oversight

1

  • J. Skolds, General Manager, Nuclear Plant Operations
  • M. Williams, General Manager, Nuclear Services

.

Other licensee employees contacted included engineers and office person-

nel.

NRC Inspectors

  • L. Modenos, Resident Inspector

i

R. Prevatte, Senior Resident Inspector

,

  • Attended exit interview on May 16, 1990.

,

A list of acronyms and initialisms used in this report is given in the final

paragraph.

i

,

2.

Fuel Handling Activities (60710)

a.

The fuel Mislocation Event

l

The spent fuel pool is divided into three regions,1. 2, and 3.

L

Region 1 is for the most reactive fuel, and all fuel from the reactor

is first unloaded into region 1 until burnup calculations are com-

'

plete and a determination is made that allows movement into the lower

reactivity regions, 2 and 3.

During the morning of April 23, 1990,

,

while performing fuel bundle / fuel rack position verifications to

'

confirm the fuel was properly positioned for reloading the core, the

licensee determined that two bundles that should have been in region

1 were in region 2 and region 3.

In addition, two other bundles were

conservatively mislocated.

They were in region 1 and should have

been in regions 2 and 3

i

+

..

,

.

..

,,

,

w

2

The SFP region burnup requirements, in MWD /MTV, are 34,546 and

14,804, for regions 3 and 2 respectively.

Fuel assembly G35, which

was incorrectly placed in region 2, had a burnup of 17,623 MWD /MTV and

did not violate the region 2 exposure requirements.

Fuel assembly

G28 had an exposure of 18,287 MWD /MTV and did violate the region 3

exposure threshold, when placed there. The design basis for region 3

is that k-effective will be less than 0.95 with one unexposed, 4.25

w/o U-235, fuel bundle optimally located within it, with a SFP boron

concentration of 2000ppmB. The actual boron concentration in the SFP

was over 2000 ppmB and the initial enrichment of G28 was 3.79 w/o

U-235.

Hence, there was no criticality concern at that time.

However, the failure of the material and administrative controls was

of concern.

After reviewing completed procedures and fuel movement data sheets,

the licensee concluded that a transcription error, rack location

18-23 was written down as 18-33, led to moving a region 1 fuel

assembly to region 3.

The concomitant error was that the bundle in

18-23, which was destined for region 3, was left in region 1.

The

source of the second error was less certain.

The bundle in 11-25

should have been moved from region 1 to 2.

Instead, the bundle in

10-25 was picked. -The licensee speculated that the crane was mis-

indexed or the index mark misread. Again, the concomitant error was

that the bundle in 11-25 was left in region 1.

Two hours after the mislocations were identified, all fuel bundles

were verified by the licensee to be in their proper locations. The

immediate corrective actions were to install a chalk board in the SFP

area, so that rack positions could be written for all concerned to

see and verify when a fuel assembly was selected for movement, and to

require that manual changes to the fuel transfer forms receive

independent verification,

b.

Inspection Activities

The inspector toured the SFP area and observed the index marks for

both the bridge and the hoist,

indexing of the bridge appeared to be

unambiguous.

There are two sets of numbered index marks for the

hoist on the bridge railing. Those on the horizontal surface are for

the fuel racks without neutron absorbing material.

Numbered index

marks for the racks with neutron-absorbing material built in are on

the vertical surface of the railing and are prefixed with a P.

It

does not seem likely that an attentive operator would misindex the

hoist, and a miscommunication error seems the more likely source of

the second mislocation error.

The inspector reviewed the Off-Normal Occurrence Report and two Core

Engineering reports, one on consequences and one on corrective

actions, which were issued shortly after the April 23, 1990, event.

In addition, the Material Transfer Forms in use at the time of the

l

<

.

.

.

..

-

,

.

.

I

3

fuel mislocations were reviewed.

These documents adequately

l

described and evaluated the event.

The event was also addressed in MRB

t

Meeting- 90-06 on May 8,1990.

At the end of the meeting, the MRB

issued the following open items related to this event:

90-06-04: Evaluate the ability to identify region 1 in the SFP by

color coding or other possible means for physical identifi-

cation. (Due date: July 31, 1990)

90-06-05: Identify long term corrective actions and incorporate these

findings into procedures to address both verbal and physi-

cal communications during the movement of fuel.

This

should address both SFP transfers as well as core trans-

fers.

(Due date: July 31, 1990)

,

90-06-06: Evaluate the indexing iocated in the fuel handling bridge

crane (on the railing.' for possible human factor improve-

'

ments.

(Duedate:

prior to refueling 6)

90-06-07: Core Engineering personnel involved in this event are to

provide a " lessons learned" training session to personnel

in their department.

(Due date: June 10, 1990)

90-06-08: Review the numbers of hours worked by Core Engineering

personnel and evaluate the desirability to add contract

personnel during future outages.

(Due date:

prior to

refueling 6)

These action items reflect appropriate management concern for the

event and for preventing a recurrence,

c.

Refueling for Com 6

Refueling was controlled by REP-107.002 (Revision 4), Core Shuffle,

and the completed copy of the procedure was reviewed by the inspec-

tor, with no procedure deviations or deficiencies identified.

The

arocedure contains steps to control temporary storage of fuel assem-

.

r

'

) lies both in the core and in the SFP.

No temporary arrays are

allowed in the core.

If- a change in loading sequence is required to

'

box in a location to guide in a bowed fuel assembly, only the fuel'

-

assemblies assigned to the locations are used for the boxing in.

These changes to the procedure satisfy requested actions I and 2 of

l

NRC Bulletin No. 89-03.

The licensee stated that use of a device called a shoe had eliminated

the need for boxing in during the most recent refueling,

ibe shoe

fits into a grid position adjacent to the assembly to be insulled

and guides the bottom nozzle into place during the last few incias of

travel.

'

.

!

,

.

..

.

1

4

i

The inspector reviewed portions of the video tape made of the core

verification following refueling.

Definition of the fuel assembly

numbers on the tape was excellent for even twice-burned fuel; thus,

there should have been no difficulty in confirming the assemblies

1

were properly located.

There was no narration on the tape; so it

1

could not be used alone to verify proper loading. The independently

verified data sheets, filled out dt.'ing the video inspection, did

confirm that the core was loaded according to design.

J

,

In reviewing procedure REP-107.002, the inspector noted that the

source of the final core design loading is not identified or clearly

documented in the procedure.

This administrative control is neces-

-

sary because core design can and has changed up to the time reloading

begins.

The correct loading design was used in cycle 6 as a result

l

1

of individual initiative rather than procedural control. The licen-

,

l

see agreed additional procedural control was necessary and issued an

internal tracking number to assure the necessary revision was per-

formed prior to the next refueling.

No violations or deviations were identified.

3.

Fuel Pin Examinations (60710)

,

Five failed fuel pins have been identified in four fuel bundles.

Using

the licensee's terminology, two fuel pins were identified as fully failed

by UT.

Two other were identified as suspect (failed in the licensee's

judgement) by UT.

The fifth failure was in a VANTAGE- 5 fuel assembly

'

(G08), which passed UT examination, one of three times, but later HDTV

inspection showed to be blistered, a sign of hydriding.

The VANTAGE 5

fuel has debris filters at the bottom.

Hence, the blisters may be from

primary hydriding.

(Primary hydriding means the water or hydrogen source

entered the fuel pin during the manufacturing process.) This fuel bundle

>

was -reconstituted, with a solid SS rod replacing the fuel rod, and . reload-

ed into core 6.

The licensee is continuing discussions with the UT

,

inspection vendor regarding the failure to positively identify the VANTAGE

5 pin as failed.

'

The inspector viewed the HDTV video tapes of the VANTAGE 5 assembly.

The

blisters were clearly defined by the imaging system and were observed

below grids 7, 6, and 4.

This distribution of blister locations is

different from other hydriding failures observed by the inspector.

In the

other cases the hydriding effects were all at or near the top of the fuel

pins.

The blisters were about 3/16th inch in diameter.

In the two cases-

in which there was an obvious hole in the clad, the hole was about 1/16th

inch in diameter.

The lighting and depth resolution did not permit visual

confirmation that the clad was fully penetrated.

The third location

appeared as only a raised area on the cladding with a different metallur-

gical structure from the cladding.

There was no visible evidence of

penetration.

~

.

- .

4

.

.

.

.

5

During the inspection, the licensee received word by telephone from the

fuel vendor that a review of the manufacturing records for the pin in G08

did not reveal any problems in the manufacture of the pin.

The inspector

is not convinced that the pin damage did not originate on the outside of

the cladding rather than the inside.

The licensee agreed to keep the

inspector Informed of the results of any further inspections or evalua-

tions of that fuel pin.

The remaining four failures were in older fuel. Two were in adjacent pins

i

in the same bundle, which makes debris induced fretting failure, with

secondary hydriding, the most likely failure mode.

No violations or deviations were identified.

4

Control of Debris in the Reactor Coolant System (92705)

Other than the usuoi steam generator inspections, tube plugging, and

hot-end tube peening, the licensee had not performed any significant

primary side maintenan:e to introduce debris during previous outages.

However, with four pin failures possibly attributable to debris-induced

fretting, the licensee has attempted to characterize the current condition'

l

of the RCS.

The licenseo has identified some debris in the RCS, with one

'

piece, apparently, from a intermediate fuel assembly grid strap.

HDTV

inspection of fuel removed from cycle 5 showed that grid straps on four

fuel assemblies had received some damage.

On three, the damage, although

visible, did not appear extensive to the inspector, and all fuel pins were

still supported by the straps in the area of damage.

Two of the assem-

blies were reinserted in cycle 6.

The fourth assembly, 001, had part of

grid 6 totally missing to the extent that five pins were unsupported by

it.

That assembly was not scheduled for any further use.

The licensee

stated that their review of fuel handling records from previous cycles did

I

not reveal any problems, such as hoist overload, with D01.

One of the activities completed during the current outage was the removal

!

of the RTD bypass manifolds from the pri. nary loops, and the installation

of thermal wells directly into the loops. This work had the potential for

introducing debris into the RCS.

The inspector reviewed WCAP-12189, RTD

'

Bypass Elimination Licensing Report for V. C. Summer Nuclear Station

( April .1989) and the completed work package.

In addition,- the inspector

l

interviewed the licensee's proje:t engineer for the work.

Cleanliness and

i

debris control appeared to be adequate to preclude the entry of fuel

,

cladding threatening material into the RCS.

!

No violations or deviations were identified.

l

5.

Core Analyses for Cycle 6 (92705)

By letter dated May 3, 1990, the licensee informed the NRC that in per-

forming final calculations for the Reload Safety Evaluation Report for the

i

L

.

.

.

4

.

.

'

6

Virgil C. Sumer Nuclear Station, Cycle 6

the licensee had discovered

that the calculated boron worth for operating modes 3 and 4 were more

negative than those previously assumed in the boron dilution accident

analysis.

The licensee's imediate corrective, to use shutdown margin

curves more conservative than TS Figure 3.1.3, was acceptable.

The

inspector attempted to learn through discussions with the responsible

,

personnel the reason for the seemingly late discovery of this problem.

,

From discussions with Core Engineering personnel, the inspector learned

that redesign of the cycle 6 core became necessary when management made

the decision t) terminate cycle 5 about 80 EFPD earlier than planned. The

short notice placed the redesign work on the critical path of activities.

Nevertheless, the design process received all scheduled interim reviews,

,

but the problem was sufficiently subtle that only the final, in-depth

review could identify it.

The proposed, long-term corrective action of

'

placing the shutdown margin curves (now TS Figure 3.1-3) in the Core

Operating Limits Report would focus sufficient attention on this problem

to assure it is addressed early in the design cycle in the future.

'

Other documents reviewed in the inspection of this area included:

a.

Startup Physics Package for the V. C. Summer Nuclear Power Plant,

Cycle 6.

'

b.

Cycle 6 Core Operating Limits Report (Draft dated May 7, 1990).

'

No violations or deviations were identified.

6

ExitInterview(30703)

The inspection scope and findings were summarized on May 23, 1990, with

those persons indicated in paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings.

No

dissenting comments were received from the licensee.

Proprietary material

was reviewed in the course of the inspection, but is not included in this

report.

7.

Acronyms and Initialisms Used in This Report

t

EFPD

effective full power days

,

'

HDTV

high defirition television

ISEG

Independent Safety Engineering Group

MRB

Nanagement Review Board

MTU

metric tons of uranium

l

MWD

megawatt days

i

ppmB

parts per milliol boron

-RCS

reactor coolant system

REP

Reactor Enginsering Procedure

RTD

resistance temperature device

SFP

spent fuel pool

'

3

,.

.;<

.

,,

7

SS

stainless steel

TS-

Technical Specifications

UT

ultrasonic testing

,

i

i

l

-

l.

l

l

l --

!

l-

l