Forwards Safety Insp Repts 50-454/90-12 & 50-455/90-11 on 900401-0512 & Notice of Violation.One Open Item Re Method of Obtaining Specified Gravities & Frequent Performance of Equalizing Charges for 125-volt Dc Station Batteries Noted
ML20043C293
Person / Time
Site: Byron  
Issue date: 05/29/1990
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML20043C294 List:
References
NUDOCS 9006050019
Download: ML20043C293 (2)


See also: IR 05000454/1990012

Text

p

-

"

n

.

.

Q t/O

"

{P

3

,

3:.

.

v

i

MAY t 9 %00

j

i

I

Docket No. 50-454

!

l

Docket No. 50-455

' Commonwealth Edison Company

3

ATTN: Mr. Cordell-Reed

!'

Senior Vice President

Post Office Box 767

l

Chicago, IL 60690

Gentlemen:

f

This refers to the routine safety inspection conducted by Messrs. W. J. Kropp,

l

R. N. Sutphin, T. E. Ploski, and Ms. D. R. Calhoun of this office from

i

April 1 through May 12, 1990, of activities at the Byron Station, Units 1

1

and 2, authorized by NRC Operating cicenses No. NPF-37 and No. NPF-66, and

!

to the discussion of our findings with Mr. R. Pleniewicz and others of your

l

'

staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

!

the inspection.

Within these areas, the inspection consisted of a selective

j

examination of procedures and representat've records, observations, and

!

interviews with personnel,

j

1

During this inspection, certain of your activities appeared to be in violation

f

of NRC requirements, as specified in the enclosed Notice. A written response

{

is required. However, one violation was a licensee identified item as

a

described in Section 7 of this report and,-in accordance with 10 CFR Part 2,

Appendix C.Section V.G.1, a Notice of Violation was not issued.

.

An Open Item was identified in Paragraph 6.b that pertained to the method

>

of obtaining specific gravities and the frequent performance of equalizing

l

charges for the 125 Vdc station batteries.

To facilitate a timely resolution

of this item, a written reply, accompanying the written response to the

Notice of Violation, is requested.

L

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosed inspection report will be placed in the NRC

Public Document Room.

The responses directed by this letter and the accompanying Notice are not

subject to the clearance procedures of the Office of Management and Budget

as required by the Paperwork Reduction Act of 1980, PL 96-511.

i

.

g\\

'

900605001

e

n x9 900529

cc_

,

PDC

{

l

,

t

r

{

.

..?.

'

'

'

,

. [*

..

-

.

Commonwealth Edison Company

2

MW I 9 iPo

b

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

.'y

!

ORIGINAL SIGNED BY W. L T0ll! LEY

,

W. D. Shefer, Chief

Reactor Projects Branch 1

.1

.

Enclosures:

1.

Notice of Violation

2.

Inspection. Report

No.50-454/90012(DRP);

No. 50-455/90011(DRP)

l

cc w/ enclosures:

T. J. Maiman, Vice President,

,

PWR Operations

P. Kovack, Nuclear

Licensing Manager

R. Pleniewicz, Station Manager

DCD/DCB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Byron

',

Resident Inspector, RIII Zion

- Resident Inspector, RIII Braidwood

P. Shemanski, NRR PM

J. W. McCaffrey, Chief, Public

Utilities Division

' H. Taylor, Quality Assurance

Division

D. Cassell, Jr. , Esq.

Diane Chavez, DAARE/ SAFE

Richard Hubbard

i

>

R

RIII

RII

tohS

Kropp/

Jhoun

br

Snell

er

'

.05/f

gg

g

gj,,jyo

s

,