ML20042G815
| ML20042G815 | |
| Person / Time | |
|---|---|
| Site: | Catawba |
| Issue date: | 05/08/1990 |
| From: | Owen T DUKE POWER CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| NUDOCS 9005160126 | |
| Download: ML20042G815 (4) | |
Text
g,-
_3 l
.p Duke Ibutt Company.
- (803) 831 3 000
~ ':Catwrt>a Nuclear Station.
PO Bas 256; Clawr, S C 29710 :
^ DUKEPOWER May 8, 1990-Document. Control' Desk U
S. Nuclear Regulatory Commission Washington, D. C.
20555
Subject:
Catawba Nuclear Station Docket'No. 50-414 Special. Report - Unit 2.
PIR-2-C90-0130;rIIR-C90-039 Gentlemen:
pursuant.to' Technical Specifications 6.9.2 and 4.8.1.1.3 please find attached a.
1 Special Report'concerning-Unit 2' Diesel Generator 2B Valid Failure on April 11,l
.]
1990.
j l
Very truly yours,
' I 6'on}7n A
Tony B. Owen Station Manager keb\\ REPORT.SP-xc:
Mr. S. D. Ebneter
'American Nuclear Insurers Regional Administrator, Region II
- c/o Dottie Sherman, ANI Library.
p.
U. S. Nuclear Regulator Commission The Exchange,: Suite.245.
101 Marietta Street, NW, Suite 2900.
'270 Farmington Avenue-Atlanta, GA 30323 lFarmington,. CT :.06032'
-d
'I M & M Nuclear Consultants Mr. K. Jabbour-i 1221 Avenues of-the Americas-
-U..S. Nuclear' Regulatory Commission New York,-NY 10020' Office of. Nuclear Reactor Regulation Washington,: D. C.
- 20555--
INPO Records Centor~
r Suite 1500 Mr. W. T. Orders q
1100LCircle 75 Parkway NRC Resident Inspector Atlanta, GA 30339 Catawba Nuclear Station-l i
. \\['
9005160126 900508
.A f-
~
PDR ADOCK 05000414
/
j 3 {
q i'
s, PDC i
g G
~
~
,c s-
'SPECIAL REPORT CATAWBA NUCLEAR STATION.
DIESEL GENERATOR 2B VALID FAILURE DURING-MONTHLY OPERABILITY TESTING OF ENGINE PROBLEM INVESTIGATION REPORT SERIAL No. 2-C90-0130 INCIDENT INVESTIGATION REPORT C90-039-2 A valid failure (start # 573) of Diesel Generator (D/G)128 occurred'on-April 11,.1990 at'0159 hours0.00184 days <br />0.0442 hours <br />2.628968e-4 weeks <br />6.04995e-5 months <br />. The failure occurred in the start attempt for the normal. monthly. operability performance test', _.
(PT/2/A/4350/02B).-D/G 2B was on-a monthly operability. test schedule.
at the time of this valid failure. There has been 1 valid failure in-the past 20 valid starts and 3 valid failures in the past'100 valid starts for D/G 2B..
l Following the initial 1 failure, Instrument, Electrical, and Mechanical 4
craft along with Engineering personnel looked to determine'theicause
]
of.the D/G not starting. Thoro-were no obvious' problems.' indicated or observed that1would'have prevented a. successful start' After review of-the findings and further' discussion with1the operators, the decision to restart the D/G to troubleshoot was made. Personnel'were placed at:
.1 strategic locations to observe panel,. controls, and engine functions.-
The D/G was auto started..The D/G started. It started in-the normal time of 6.2 seconds. No abnormal' indications were seen or reported ~
i
~
D during the start and run. In the same manner, observed start #2 was conducted'as a key start, with the same satisfactory ~results.
After the two successful normal' starts, the following were inspected;
-Fuel filters Fuel strainers Fuel rack _ linkages from governor to the fuel pungs for alignment j
All fuel rack linkages for free movement j
s 2L fuel pump was found sticking. The heim joint was removedLand the l
injection pump was verified to have smooth and non-sticking movement.
l i
The.'2L heim joint was original. equipment. It had been in servicef some ten years and had seen more than 670 hours0.00775 days <br />0.186 hours <br />0.00111 weeks <br />2.54935e-4 months <br /> of service. A new heim.
)
joint, from spares, was. adjusted to the. replaced joint length and 1
installed. The pump and'new heim joint. assembly was-then rechbcked to verify movement to be smooth and non-sticking.
1 The force required to move the' complete fuel. rack:was checked and,was d
found to be consistent with previous-tests of thisland the other unit
- {
2 engine. Then as an~added measure, the fuel rail-bearings were..
l lubricated even though they were scheduled for the-following month.
}
l-
')
1 of 2 L
f 1
J
F o
6
.J After completing the above maintenance activities, personnel were strategically placed and the D/G started uneventfully. Following, the operability test wasTsatisfactorily performed and the D/G declared operable.
1 Cencurrently with the above inspection activities, MES contacted WW j
Gallman, General Office, to inform and request assistance in
-4 researching for other failures-involving sticking fuel racks d
I attributable to heim joints. Conversations-_with a. Senior. Design
)
Engineer of Energy Services Group, Cooper-Industries informs us that
. l no failures have been reported concerning binding heim joints as the-source of failure. This was borne out in conversations with two
-l neighboring utilities, in-that;they had not, nor had they heard of a similar failure mechanism.
Physically, a bound heim joint will prevent'the fuel racks;from.
opening, effecting the start, however it will not prevent the D/G'from i
shutting down. All heim joints are checked for free movement each outage. All joints were satisfactory at the last inspection.
i Detailed inspection of the bound ball and retainer showed that the ball retainer had a pinch mark. The pinch mark was approximately-one quarter inch long and caused a-slight protrusion of metal, about an
]
eighth inch long by one sixty-fourth inch wide...The. pinched area j
probably caused some slight closure of the normal ball to housing l
clearance at the pinch site. The pinch by itself was not aLproblem.
The failure was caused by a particle (or particles) of grit that had j
gotten into the joint and in time worked around and collected at the l
reduced clearance area to ultimately cause binding and prevent the.
- j fuel racks from opening.
l 4
To verify that no-other problem had caused the failure to-start, the I
diesel generator was allowed.to sit for_ a week, then with personnel l
strategically placed, satisfactority tested again.
This valid failure is considered an isolated incident--in that;
]
- No other failures were caused by this' mechanism-l
- All information'and evidence evalua'ted indicates less.than sterile housekeeping conditions coupled with an insignificantly (by itself) damaged heim joint housing and-time to concentrate 3
the dust caused the' failure of 2B diesel generator to~ start.
.{
.Near future activities to. prevent this condition from again causing a failure are:
q 1.
In the upcoming outage, 2EOC3, tho'heim joints will receive 4
an inspection for freedom of movement and clearance.
2.
The ventilation system will be evaluated to determine if more efficient filters can be used to reduce dust introduction'into the diesel generator rooms and not j
adversely impact current ventilation design considerations.
{
2 of 3 O
1
~ j q,,
}!
_.,-o*.
N t
'?
Finally,~although-existingidocuments used to: classify Diesel ~ Generator testing
- Adentify.this as a valid 1 failure,-new draft: guidance indicates thatteventsiof 9-s
> this sort in.theLfuture.may: not classify this ~ as a f valid failure. As:this
~
4
. guidance ~ is formalized ' Duke may ask that It be reclassified :as 'an" invalid :
failure' consistent with'the guidelines-and technical bases of:
1.'-
NSAC-198'(The Reliabilit'y of, Emergency Diesel Generators!at;U.S.
-Nuclear' Power plants);
2.
INPO-(Institute of-Nuclear power ~ Operations),'and 3.
.NUMARC (Nuclear. Management.and Resources Council), and specifically,'
i 4.
.NUMARC 87-00-(Guidelines and. Technical Bases.for NUMARC Initiatives' AddressingLStation Blackoutfat Light Water Reactors) Revision 1,
,j Dated April-6,'1990, AppendixL-D',Eand page 4; EXCEPTIONS;J i
.t
" Unsuccessful attempts'to start or load-run should~not be counted as 7
valid demands-ornfailures when they can be-definitelyTattributedito 4
.any.of the following..
-l "o.
component malfunctions'or operating errors.that,did.not^
h prevent the emergency generator frem being' restarted and brought to load :within a few minutes (i.e., without J
-corrective maintenance or significant problem' diagnosis)"1
-f 3
s I
4
~f i
~
b 3 of.3 q
'}
-