ML20042F320

From kanterella
Jump to navigation Jump to search
Insp Rept 50-298/90-15 on 900326-30.Violation Noted.Major Areas inspected:safety-related Piping Supports & Restraint Sys Testing & Review of Pipe Support Qualification Program
ML20042F320
Person / Time
Site: Cooper Entergy icon.png
Issue date: 04/25/1990
From: Clay Johnson, Stetka T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20042F317 List:
References
50-298-90-15, NUDOCS 9005080165
Download: ML20042F320 (8)


See also: IR 05000298/1990015

Text

,

.

\\

.

.

.

,

APPENDIX _B

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-298/90-15

Operating License: DPR-46

Docket: 50-298

Lice.nsee: Nebraska Public power District (NPPD)

P.O. Box 499

Columbus, Nebraska 68602-0499

Facility Name: CooperNuclearStation(CNS)

Inspection At: CNS..Brownv111e, Nebraska

Inspection Conducted: March 26-30, 1990

Inspector:

_

W~

4/2f/90

,

C. E. Whnson, Reactof Inspector, Plant

Da".e

Systems Section, Division of Reactor Safety

'

Approved:

4M

f/2f/90

T. F. Stena, Chief, Plant Systems Section-

Date

Division of Reactor Safety

l

'

Inspection Summary

-

Inspection Conducted March 26-30,1990(Report 50-298/90-15)

Areas Inspected:

Routine, unannounced inspection of safety-related piping supports

and restraint system _ testing and review of the pipe support qualification program.

Results: One violation was identified in paragraph 2.2.3 involving a failure to

comply with the intent of the American Society of Hechanical Engineers (ASME) code

requirementspertainingtotheSectionXIinserviceinspection(ISI) program

for Class 3 nonintegral component supports. This finding indicates a weakness

in the ISI program. Management-involvement should be increased in the ISI area

to assure that required ~ASME code requirements are met and interpretations of

those requirements are adequate.

Review of the pipe restraint (snubber) program indicated that this program is

adequate and encompasses all requirements.

The pipe support qualification program is-a well planned and organized effort

which is considered a strength in the upgrade of safety-related pipe supports.

9005080163 900430

{DR

ADOCK 05000298

PDC

__

.

=

.

4

.

.

,

-2-

DETAILS

1.

PERSONS CONTACTED

NPPD

' *Y. Armstrong, Administrative Secretary

  • R. Beilke, Radiological Support Supervisor
  • B. Crow, Lead Mechanical Engineer

B. Frehrman, Project Manager, Pipe Supports

  • J. Flaherty, Engineering Manager-
  • S. Freborg . Assistant Plant Engineering Supervisor
  • R. Foust, Engineering Program Supervisor
  • R. Gardner, Maintenance Manager
  • R. Gibson, Quality Assurance Supervisor
  • B. Hall, Health Physicist
  • G. Horn, Division Manager, Nuclear Operations
  • J. Sayer, Radiological Manager
  • R. Schultz, ISI/IST Engineer
  • G. Smith, t.icensing Supervisor

NRC

  • W. Bennett, Senior Resident inspector
  • G. Pick, Resident Inspector
  • Denotes those present during the exit interview conducted on March 30, 1990.

The inspector also interviewed other licensee employees during the inspection.

2.

TESTING OF PIPING SUPPORT AND, RESTRAINT SYSTEMS (70370)

The purpose of this inspection was to determine that adequate programs and

procedures are established in the area of safety-related pipe supports and

restraint systems for proper installation, examination, testing, surveillances,

and records retention and whether they are in compliance with regulatory

requirements. Technical Specifications (TS), and license commitments.

'

2.1 PipeRestraint(Snubber) Program

2.1.1 Procedure Review

i

The inspector reviewed seven procedures pertaining to inspection, operability,

removal and installation, disassembly and assembly, and the functional testing

of hydraulic and mechanical snubbers. These procedures contained adequate

-instructions and sufficient acceptance criteria. The inspector also reviewed

-TS Sections 3.6.H and 4.6.H, which provide instructions on limiting conditions for

j

operation and surveillance requirements respectively. Procedures reviewed are

!

listed in the attachment.

- _ _

.

,

i

,,

!

-3-

2.1.2 Observation of Functional Testing

.

,

The inspector observed the functional testing of two snubbers (mechanical and

[

hydraulic). The operator performing the testing was knowledgeable of procedural

requirements and acceptance criteria. Observations by the insp3ctor indicated

that both snubbers met the drag test, activation test, and bleed rate. The

operator performing the test followed procedural instructions as required. No

deficiencies were observed.

Snubbers observed for functional testing were:

MS-SNUB-MS-S-9B; Serial No. 449

W/H; Serial No. 8086

'

2.1.3 Field Observations

The inspector performed an independent visual inspection of various size

snubbers inside containment. Attributes that were selected for observations in

the visual examination were:

,

Deterioration, corrosion, physical damage, or deformations were not

evident;

Threaded connections were secured by locknuts, fasteners, and cotter pins;

Snubber settings;

Extension rods, support plates, and connecting joints were not bent,

deformed, or loose; and

,

All required bolts, locking devices, nuts, and washers were installed.

No significant deficiencies were identified.

The supports examined are listed in the attachment.

2.1.4 Records Review

'

The inspector reviewed records of snubbers that were visually examined in the

field by NPPD, functional testing performed by NPPD, calibration records of the

functional test equipment, and surveillances of the snubber program conducted

during the refueling outage.

Records reviewed indicated the following:

Equipment was calibrated as required.

Surveillances are performed as required by TS.

Sample size was selected as required by TS.

'

Functional test of snubbers were within established acceptance criteria,

i

i

.

..

,

,

-4

Identified deficiencies were noted end documented on the visual

examination records.

No deficiencies were identified.

,

Records reviewed are listed in the attachment.

2.2 InserviceInspectionProgram(ISI)

2.2.1 Procedure Review

The inspector reviewed the following two procedures pertaining to visual

examinations of pipe supports and restraint systems included in the 10-year 151

plan (secondinterval). These procedures were written by General Electric (GE)

Nuclear Energy and included VT-3 and VT-4 visual examination attributes and

acceptance criteria.

/

Visual Examination Procedure (VT-3), Revision 3, February 8,1988.

'

VisualExaminationProcedure(YT-4), Revision 2, September 18, 1987.

Procedures reviewed by the inspector were adequate.

2.2.2 Visual Examination

The inspector observed GE inspectors perform their VT-3 and VT-4 inspections on

several supports included in the ISI plan for this outage.

In each case, the

GE inspectors performed the visual inspections in accordance with established

procedures. Any deficiencies identified were noted on the inspection

'

checklist. Discussions with the visual examiners indicated that they were

,

knowledgeable of the required inspection attributes and acceptance criteria.

<

The inspector also performed an independent visual inspection of 151 supports.

Some supports examined by the inspector were not included for ISI inspection by

the licensee, The supports examined indicated no significant deficiencies.

Supports examined by GE inspectors and the inspector are listed in the

attachment.

2.2.3 ISI Program Review and Pipe Support Selection

,

The inspector rev'iewed the 10-year ISI program and had several discussions

regarding program establishment, ASME code requirement commitments made in the

,

Safety Evaluation Report (SER), and the selection process for pipe supports

examined under this program.

'

As the result of these discussions and reviews, two concerns were identified.

The first concern was that the number of Class 1 supports selected for

examination appeared to be low in number. This concern ~was expreised to the

licensee. The licensee reviewed the inspector's concern and later determined

'that 20 supports were inadvertently omitted from the schedule for this outage.

-

The 20 supports were then added for. inspection this outage. The inspector then

r

- - -.

.

'

'.

.

-5-

questioned the number of supports selected the previous outage.

Following a

review, the licensee subsequently informed the insr,ector that the supports from

the previous outage were verified and that no other supports had been omitted.

Since this discrepancy was identified prior to the end of the second 10-year

L

interval, the licensee was not considered to be in violation of the ASME code.

'

As the result of this discussion, the licensee committed to add an engineering

checklist to a procedure that will preclude the inadvertent omission of

supports for future outages. This commitment will be considered an inspector

follovep item pending the addition and implementation of the checklist.

Inspector Followup Item (298/9015-01): Review the implementation of an

j

engineering checklist to a procedere to preclude the inadvertent omission of

pipe supports in future outages.

The second concern raised by the inspector pertained to ASME Class 3 supports.

Review of the 151 program for the first and second 10-year interval indicated

that no Class 3 nonintegral supports were included in the program for VT-3

,

examinations,

q

Paragraph IV0-1220, " Items Exempt From Examination," winter 1980 Addendum,

addresses the exemption of " integral attachments" only.

It does not exempt

nonintegral attachments such as snubbers and other pipe supports.

Subsection IWF, paragraph IWF-1300 " Support Examination Boundaries," specifies

the support examination boundaries for both integral and nonintegral supports.

Paragraph IWD-2620. " Visual Examinations VT-3." specifies that component

supports and restraints within the boundary of each system specified in

i

examination categories of Table IWD-2500-1 shall be subject to the Visual

Examination VT-3. This specification includes non %tegral supports. The

licensee has interpreted paragraph IWD-1220.2a and b, in conjunction with

interpretation X1-1-83-12R-2 to exempt integral and nonintegral attachments

from ASME code examination.

Further investigation by the inspector and several meetings with the licensee

indicated that the licensee had misinterpreted the ASME code requirements on

Class 3 nonintegral supports. A telephone conference call between the NRC and

licensee as held March 29, 1990, to discuss this issue. As the result of this

conference call the NRC informed the licensee that they had misinterpreted the

code requirements for Subsection IWD, " Requirements for Class 3 Components of

Light-Water Cooled Power Plants," winter 1980 Addendum, and that the ASME code

interpretation (X1-1-83-12R-2) did not apply in this case.

Failure to meet the intent of the ASME code requirements for the examination of

Class 3 nonintegral component supports is considered to be contrary to the-

requirements of Section XI of the ASME Boiler and Pressure Vessel Code and

TS 4.6.G.

Violation (298/9015-02):

FailuretoincludeASMEClass3(nonintegral)

component supports for examination in both the first and second 10-year ISI

program.

___

.

I

  • .

.

'

-6-

'

3.

PIPE SUPPORT UPGRADE OVAL.lFICATION PROGRAM

The inspector received a complete overview and status of the pipe support upgrade

program by the licensee's project manager. The project manager informed the

inspector of the following:

As-built packages are 100 percent complete;

,

Final drawing changes are in progress;

Pipe support stress analysis is 100 percent complete by their consultants;

NPPD's engineering has enmpleted 90 percent of the review of the

consultants analysis; and

Modifications are 30 percent complete.

The project manager informed the inspector that all operability concerns have

been taken into consideration pertaining to modification changes. This program

appears to be well planned and organized and is considered to be an enhancement

to the site's pipe support upgrade program.

4.

EXIT INTEPNIEW (30703)

An exit interview was conducted on March 30, 1990, with the licensee

representatives identified in paragraph 1.

During the interview, the inspector

reviewed the scope and findings of the inspection as discussed in this report.

Other meetings between the inspector and licentee management were held

periodically during the inspection period to discuss identified concerns. The

licensee did not identify as proprietary any information provided to, or

reviewed by, the inspector.

,

.

l'

c.-

.

i

ATTACHMENT

,

Snubber Procedures

7.2.34.1, " Snubber Inspections," Revision 2, January 4,1990

,

7.2.34.2, " Pipe Snubbers Removal and Installation," Revision 2, January 4,

.

1990

7.2.34.3, "Grinnell Figure 200/201 Hydraulic Snubber Disassembly and

Assembly," Revision 1, November 9, 1988

7.2.34.4, " Pacific Scientific PSA-3 and PSA-10 Snubber Disassembly Overhaul

and Assembly," Revision 0, March 30, 1989

7.2.34.7, 'Grinnel Figure 200/201 Hydraulic Snubber Functional Test,"

.

Revision 1, February 22, 1990

7.2.34.8, " Pacific Scientific Snubber Functional Test," Revision 1,

'

February 8,1990

6.3.10.9.1, " Snubber Operability," Revision 16, September 7, 1989

S_nubbers Visually Examined (Independent)

VR-57B SerialNo.12644)

VR-512 SerialNo.6877)

VR-57A Serial No. 336)

RH-S8C SerialNo.8139M)

RH-S8A Serial No. 6997)

RH-58B Serial No. 5230)

VR-60-7-2(SerialNo.404)

VR-S23B (Serial No. 484)

VR-S32(SerialNo.17204)

VR-56 (Serial No. 17201)

VR-S24B Serial No. 5892

VR-S23A Serial No. 5887

VR-524A Serial No. 4884

RF-SIO Serial No. 15142

RF-S17 SerialNo.5891)

SS-3A2 Serial No. 338)

SS-382(SerialNo.5308)

.

SS-3Al (Serial No. 5312)

VR-61-17-X(SerialNo.5310)

ISI Supports Examined (Independent)

RH-H123

VRH-64C

VRR-50-1.1

RF-H70

VR-G21

n-

_.

'

,

..,t'

'

.

-2-

t:S-132

RCC-H10

RH-H-32A

RH-H3-X225

VRS-27

VPS-13-1A-1

VR-56-24-X

H-4

VRR-30

H-9

VRH-53

VRS-915

ISISupportExaminationsObserved(GEVT-3 Examination)'

RR-H7-6

RR-H7-A

RF-HIS

Functional Test Records Reviewed

i

Hydraulic Snubbers (Grinnell)

l

RHR-SNUB-RH-S43(SerialNo.10058

RHR-SNUB-RH-S78A (Serial No. 8565

RHR-SNUB-RH-523 (Serial No. 10053

,

'

RHR-SNUB-BS-S116B(SerialNo.8075)

i

CS-SNUB-CS-51(SerialNo.10062)

MechanicalSnubbers(PSA)

RF-SNUB-RF-59 (Serial No. 456)

MS-SNUB-MS-S63 (Serial No. 463)

'

MS-SNUB-VR-S1 (Serial No. 17207)

MS-SNUB-VR-60-7-X(SerialNo.15144)

MS-SNUB-VR-62-8-2(SerialNo.406)

,

,

b

I

l

_