Informs That Rl Dickherber Submitted Answer to Orders Issued to Util & Dickherber on 900413.Requests Util Provide Views Re Adequacy of Company Controls for Work Hours in View of Info Provided by Dickherber at Page 13 of Answer
ML20042E885
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 05/01/1990
From: Lieberman J
NRC OFFICE OF ENFORCEMENT (OE)
To: Reed C
COMMONWEALTH EDISON CO.
References
EA-90-031, EA-90-032, EA-90-31, EA-90-32, NUDOCS 9005030362
Download: ML20042E885 (2)


Text

-

K$

e vs toq'o,

\\

4 UNITED STATES

[,,.;

g NUCLEAR REGULATORY COMMISSION

j W ASHINGTON,0. C. 20655 4.....*

MAY 011990 4

L Commonwealth Edison Company-i L

ATTN:

Mr. Cordell Reed Senior Vice President l

Post Office Box 767 Chicapc. Illinois 60690

\\

Dear Mr. Reed:

i Re:.In the Matter of R. L. Dickherber, License No. 50P-2365-8, Docket No. 55-5043, EA 90-031 and In the Matter of Commonwealth Edison Company, Quad Cities Nuclear Power Station, Docket Nos. 50-254 and 50-256,-License j

Nos. DPR-29 and DPR-30 and EA 90-032 g6 On April 13, 1990, Mr.-R. L. Dickherber submitted his answer to the above orders issued to Commonwealth Edison Company and to Mr. Dickherber.

The staff is in the process of considering his answer.

As be helpful to obtain Commonwealth Edison Company'part of our review it would s views on the statements-made by him in his response and views on Mr..Dickherber's performance in the past and why we should ;. ave confidence in his performance in the future.

As a separate matter, please provide to the Regional Administrator, Region III, your views concerning the adequacy of the company's controls for work hours in view of the information provided by Mr. Dickherber at page 13 of his answer.

We would appreciate it if Commonwealth, as a company, would provide this response within the next 30 days so that we can promptly resolve this matter.

We intend to schedule an enforcement conference with Mr. Dickherber and Commonwealth Edison Company following the completion of our review of his response and your additional submittal.

Sincerely, bh p

James Lieberman, Director 4

ffice of Enforcement cc:

Stuart Lefstein, Esq.

Sheldon Trubatch, Esq.

9005030362 900501 PDR ADOCK 05000254 V

PDC I 0-a

MAY 011990 i

3 Commonwealth Edison _ Company DISTRIBUTION:

PDR SECY-CA HThompson, DEDS JHSnierek,'DEDR JLieberman, OE ABDavis, RIII JGoldberg, OGC TMurley, NRR JPartlow, NRR 3

Enforcement Coordinators RI, RII, RIII, RIV, RV Resident Inspector l

FIngram, GPA/PA l

BHayes, 01-l-

EJordan, AE00 WTroskoski, OE OE:Chron OE: EA DCS N

DE M RA:RIII NRR: ADPR D:

eLi[eberman WTroskoski ABDavis JPartlow S// /90 5/ //90 5// /90 5/ /90 u/464 7,s

~

A n y,qu