Monthly Operating Rept for Mar 1990 for Jm Farley Nuclear Power Plant Unit 1.W/900412 Ltr
ML20042E381
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/31/1990
From: Hairston W, Dennis Morey
ALABAMA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9004200710
Download: ML20042E381 (5)


Text

, . - _

7-

,*- .' AlIbama Power'Comptny 40 inverress Cont:r Parkway

' Wst Office Box 1295

  • B#rmingham, Alabama 35201 j Telephone 205 868 5581 l

W,- G. Hairston, til l Senior Vice President.-

Nuclear operations - AlabamaPower.  ;

thesouthem electrcsystem J April 12, 1990 l

Docket No. 50-348 ,

i

-U.-S. Nuclear Regulatory Commission ATIN: Document Control Desk l -Washington,;D. c. 20555-l l

Joseph M. Farley Nuclear Plant ^

Unit 1 Monthly Operating Data Report Attached is the March 1990 Monthly Operating Report for Joseph M. Farley-Nuclear Plant Unit 1, required by Section 6.9.1.10 of the Technical Specifications.

l If you have any questions, please advise.

l-L- Respectfully; submitted,

.- . on, II JGS:sme/1.6 l

Attachment l cc: Mr. S. D. Ebneter Mr. S. T. Hoffman Mr. G. F. Maxwell

~

9004200710 900331 PDR ADOCK 05000348 R PNV

') .

. -i

. . OPERATING DATA REPORT .

DOCKET NO. 50-348

, DATE Apn1 y, 1syv l' COMPLETED BY D. N. Morey L TELEPHONE (205)B99-5156 ,

i OPERATING STATUS Notes

-1. Unit Name: Joseph M. Farley - Unit 1 1) Cumulative data since

2. Reporting Period: March 1990 12-1-77, date of I

3.. Licensed Thermal Power (MWt): 2,652 commercial operation- .

L 4. Nameplate Rating (Cross MVe): 860  ?

L 5. Design Electrical Rating (Net MWe): 829-  ; g; l 6. Maximum Dependable Capacity (Gross MWe):- 866.1 :6

7. Maximum Dependable Capacity (Net MVe): 823.7
8. If Changes Octir in Capacity Ratings (Items Number 3 Through 7) Since Last Report,' -

Give Reason' 4/A -

9. Power. Level To.Which Restricted, If Any (Net MWe): N/A
10. Reasons For Restrictions, If Any: N/A This Month- Yr-to-Date Cumulative
11. Hours In Reporting Period 744.0 2,160.0 108,096.0 '
13. Number Of Hours Reactor Vas Critical 744.0 2,160.0 82,418.4 y 13. Reactor Reserve Shutdown Hours 0 0 3,650.0
14. Hours Generator On-Line 744.0 2,160.0 80,870.2 ,

( 15. Unit Reserve Shutdown Hours 0 0 0 l- 16. Gross Thermal Energy Generated (MVH) 1,962,103 5,584,862 206,738,778

17. Gross Electrical Energy Generated (MVH) 641,652 1,826,440 66,591,590^

l

18. Net Electrical Energy Generated (MWH) 609,578 1,733,520 62,828,486
19. Unit Service Factor 100- 100 74.8
20. Unit Availability Factor 100 100 74.8
21. Unit Capacity Factor (Using MDC Net) 99.5 97.4 72.0
22. Unit Capacity Factor (Using DER Net) 98.6 96.8 70.1
23. Unit Forced Outage Rate 0 0 7.9-
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration,of Each):

N/A

25. If Shut Down At End Of Report Period, Estimated Date of Startups. N/A
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved -

INITIAL CRITICALITY 08/06/77 08/09/77 INITIAL ELECTRICITY 08/20/77 08/18/77 COMMERCIAL OPERATION '12/01/77 12/01/77 E

t

JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1.

NARRATIVE

SUMMARY

OF OPERATIONS ,

March, 1990  ;

Th2re vere no unit shutdowns or signiticant power reductions during the month of March.

Th2 following major safety-related maintenance was performed in the month of Marcht

1. Repaired the IB inverter by replacing the ferroresonant transformer. h
2. Inspected and cleaned the service water side of the 10 charging pump room cooler.
3. Repaired minor leaks and the cooler relief valve for-the 1A motor driven I auxiliary feedvater pump.
4. Repaired the drain valve on the 1A containment spray pump,
5. Performed miscellaneous corrective and preventive maintenance on the diesel generators.

l i

1 i

r l

DOCKET No. 50-348 ,

UNIT 1 DATE April 9, 1990 -

COMPLETED BY,D. N. Morey-TELEPHONE (205)899-5156 .$

1 MONTH March i

DAY' AVERAGE DAILY POVER LEVEL DAY AVERAGE DAILY POWER LEVEL

-(HWe-Net) (MVe-Net).

1 825 723 2 822 18 722 I 3 825 19- 826 4 828 20 830 5 826 21 830 6 824 22 -826

'7 825 23 826 8 825 24 826 9 822 25 825 10 822 26 825 11 ,

821 27 828 12 821 28 825 13 820 29 823- .

14 822 30 821 15' 819 31 779 16 815 INSTRUCTIONS On this format, list the average daily unit power level in MVe-Net for each day in ths reporting month. Compute to the nearest whole megawatt.

l l

=IT SRUTDutRS AND 10ER REDUCTICEES DocIET No. 50-348

~

GEIT NME . J. M. FNtIET - tErrT 1 DM Jeril 9,1990 CEMPIETED ET D. N. IERET ' ..

REPORT JoNTH ftMtCB TELEPHONE (2051899-5156- .

1 I I i' l I nETM m or iLrcaisEE I i 1 cast & cratnerzvE I I I I I ouanza I isnurr:m lEvEsr I scrze To' I iTrrE I auxRs) I nAs=2 ,go,,,,y ,,3 ; ,,,,, i srsToi I,c ,,,s aMemore 2

I=- Inm , , ,,,4 , ,,,,,,, ,c, ,,,c, ,

I I I I I I I I I I I immE wen No varT sauroo.as on simirzcurr power mEnoCT:=s ouRrm TnE rom or mRcs.1 1 I I I I I I I I I I I I I I I I I I I I I I I

I I I I I I I I I I I I I I I I I I .I I I I I I I I I I I -l I I i l i I I I I I I I I I I I I I I I I .I I I I I I I I I I I i i i I I I I I I I I l- 1 I I I I I I I I I I I I I I I I I I I I I I I .I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I l I l- 1 I I I I I I I I I l l I I I I I I I I I l' I .I I I I I I I I I I I I I i i i i i l i l I I i i 1 I I I I I I I I I I I i I I I I i l 1 1 I I I I I l- l' I I I 'l I-1 I I I I I I -l i I l-1 I I i 1. I 1: i I I I F: Forced Reason: Petinod: Exhibit G-Iristructions S: Scheduled A-Equigeant Failure (Explain) 1-4tantsal for Properation of beta

- B-Maintenance or Test ~2-etenual Scram. Entry Shoots for Licensee C-Refueling .

3-Antomatic Scram. . Event mopect(IJut) File (someG-D-Regulatory Restriction 4-Other (Explain) ' 0161)

E-operator Training & License Examination F-Administrative Exhibit I -Same Source G-operational Error (Explain)

(9/77) H-Other (Explain) b p ,4 -

q M .)-b, , . y +" * . * * * ' ' * 'D # "'

$ 'T D ' '

D# "' '"

% ' '9N '#' "