IE Insp Rept 50-369/82-04 on 820216-19.No Noncompliance Noted.Major Areas Inspected:Implementation of Environ Monitoring Program Review of Licensee Interlaboratory Comparison Program & Response to IE Bulletin 81-03
ML20042B634
Person / Time
Site: McGuire 
Issue date: 03/04/1982
From: Cunningham A, Montgomery D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20042B617 List:
References
50-369-82-04, 50-369-82-4, IEB-81-03, IEB-81-3, NUDOCS 8203250471
Download: ML20042B634 (6)


See also: IR 05000369/1982004

Text

,

.

.

ynnotiq'o

UNITED STATES

~g

8 '^

NUCLEAR REGULATORY COMMISSION

o

$3

E

REGION 11

101 MARIETTA ST., N.W., SulTE 3100

o,

-

%

ATLANTA, GEORGIA 30303

s

4. . e

'

Report No. 50-369/82-04

Licensee:

Duke Power Company

P. O. Box 2178

Charlotte, NC 28242

Facility Name: McGuire Nuclear Station

Docket No. 50-369

License No. NFP-9

Inspection at McG f re si.te,near Corneli

NC

uffg29gg

4?

.7

3

Inspector:_

,,

4. L. Cun in

m'

tate digned

g

Approved by:

d._

_

3 ([_ [1

D. M/Mofit omeFy, Section Chief, IM&EP Section

t6

igned

POS(Division

SUMMARY

Inspection on February 16-19, 1982

Areas Inspected

This routine, unannounced inspection. involved-27 inspector-hours on site in the

area of radiological environmental monitoring including management controls;

implementation of the environmental monitoring program;- review of licensee

interlaboratory comparison program; assessment of licensee's response to NRC

Bulletin 81-03; review of licensee's program for quality control of analytical

measurements.

Results

e

Of the five areas inspected, no violations or deviations were identified.

!

!

8203250471 820304

QDRADOCK 05000369

PDR

l

- - - .

_.

.

. . _

.

. ,._

.

_

_

l

.

,

,

o

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • M. D. McIntosh, Station Manager
  • H. B. Tucker, Manager, Nuclear Production Division
  • J. W. Foster, Health Physics Coordinator
  • D. H. Franks, Quality Assurance Supervisor
  • W. M. Sample, Projects and Licensing Engineer
  • D. D. Lampke, Licensing Engineer

T. J. Keane, Station Health Physicist

J. Isaacson, Radiochemist

  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on February 19, 1982, with

those persons indicated in paragraph 1 above.

3.

Licensee Action on Previous Inspection Findings

No previous inspecthn findings remained outstanding.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Management Controls

a.

Management and administrative controls defined in Section 6 of the

Technical Specifications for Unit 1, were reviewed by the inspector

with respect to the following items:

(1) organizational and management

responsibility for implementation of the radiological environmental

monitoring program required by Technical Specification 3/4.12; (2)

periodic audit of the environmental monitoring program; (3) radio-

logical environmental procedures. These items are discussed below,

b.

Technical Specifications 6.1 and 6.2 assign management and organiza-

tional responsibility for implementation of the offsite radiological

monitoring program. The inspector conducted a comprehensive review,

including discussions with cognizant licensee representatives, of

specific management responsibility for assuring implementation of the

-

.

.

,

2

monitoring program.

Management of the offsite radiological environ-

mental monitoring program is the direct responsibility of the Station

>

Health Physicist. Sample collection and environmental surveillance is

implemented by an assistant health physics technician under the

direction of an assigned health physics supervisor.

Management

responsibility for. radiochemical analysis of environmental samples is

an offsite function assigned to the Technical and Environmental Service

Group.

The System Health Physicist is assigned management responsi-

bility for radiochemical analysis of samples listed in Table 3.12-1 of

Technical Specification 3/4.12.1.

Analyses are implemented by the

Environmental Radiological Laboratory staff under the direction of the

Laboratory Services Supervisor.

Inspection disclosed that organiza-

tional responsibility for and management of the radiological environ-

mental monitoring program 'were consistent with requirements of the

above cited specifications.

c.

Technical Specification 6.5.2.9.k requires that a periodic audit of the

environmental monitoring program shall be conducted, at least, once per

12 months.

The inspector reviewed the section of licensee Audit

Report No. SP-81-9(MC) dated September 29, 1981, which addressed the

sampling and surveillance requirements of the radiological environ-

mental monitoring program defined in Table 3.12-1 of Technical

Specifica* ion 3/4.12-1. The audit disclosed no findings regarding the

referenced program. The inspector had no questions.

d.

Technical Specification 6.2.5.9.n requires., at least, once per 12

months, an audit of the performance of ae.ivities required by the

quality assurance program to meet the criteria of Regulatory Guide 4.15

(December 1977).

The inspector reviewed licensee Audit Report No.

SP-81-10(GO) dated November 3,1981.

The audit was conducted during

the period September 21, 1981 through October 7,

1981.

Inspection

included the following:

(1) discussion with _ a cognizant _ licensee

representative of the audit and it's . respective findings and recom-

mendations;. (2) review of licensee or'ganization's re'sponse to _ such -

findings; (3) verification of adequacy of corrective actions imple-

mented. Inspection disclosed that required followup and completion of

corrective actions in response to audit findings were implemented with

the exception of those findings which addressed procedures, viz.: (1)

SP-81-10(GO)9 and SP-81-10(GO)10 regarding approval and review,

respectively,

of environmental

radiological

laboratory control

procedures; (2) SP-81-10(G0)11 addressing failure of referenced

procedures to use the terms "shall", or its equivalent, to indicate

mandatory compliance, where such compliance is required.

Inspection

disclosed that the subject procedures were revised as required and were

submitted for review and approval .

The inspector informed licensee

representatives

that

the

environmental

radiological

laboratory

procedures would be reviewed during a subsequent inspection te verify

that review and approval were implemented as required (Su-369/

82-04-01).

.

.

.

3

e.

Technical Specification 6.8.1.1 requires that written procedures which

address the quality assurance program for effluent and environmental

monitoring using guidance in Regulatory Guide 4.15 (December 1977)

shall be established, implemented and maintained.

Inspection

included a detailed review of radiological environmental sampling and

surveillance procedures complied under Procedure PT/0/B/4600/26 (Rev.

O, 9/22/80) which addresses all sampling and surveillance requirements

listed in Table 3.12-1 of Technical Specification 3/4.12.1. Inspection

disclosed that the procedures were reviewed and approved as required.

Inspection also disclosed, however, that the subject procedure required

the following changes:

(1) update to reference Technical Specification

3/4.12 and applicable tables therein; (2) required submission of

environmental samples to environmental radiological laboratory for

radiochemical analysis following scheduled sample collection. The

above procedures will be reviewed during a subsequent inspection

(50-369/82-04-02).

f.

Inspection also included a detailed review of the environmental

radiological laboratory control procedures. These procedures and the

findings related thereto are discussed ;n paragraph 5d, above. The

scope and contents of monitoring and laboratory control procedures were

consistent with guidance regarding operating procedures and quality

catrol defined in Sections C.3 (0perating Procedure and Instructions),

C.S (Ouality Control in Sanpling (Including Packaging, Shipping, and

Storage of Samples), and C.6 (Quality Control in the Radioanalytical

Laboratory (including calibration reference standards, performance

checks of radiation measurement systems, analysis of QC samples,

inter-and-intralaboratory analyses, computational checks, review and

analysis of data)) of Regulatory Guide 4.15 (December,1977). The

series of environmental radiological laboratory procedures reviewed are

listed below.

(1)

1000 Series - General Administrative Procedures

(2) 2000 Series --Environmental Radiological Laboratory Procedures

(3)

3000 Series - Ouality Control Procedures

(4)

4000 Series - Radiological Instrumentation Procedures

(5) 5000 Series - Non-Radiological Instrumentation

(6) 6000 Series - Radioactive fiaterial Control Procedures

(7)

7000 Series - flaintenance Procedures

.

b

.

.

.

4

6.

Analytical Quality Control *

Inspection included a detailed review of the licensee's quality control

procedures, related administrative procedures, and analytical quality

control program data compiled during the period January 1 - December 31,

1981. The procedures reviewed included Procedure Nos. 3000/01(Daily

Instrument Linearity, Source and Background Check), 3000/02 (Radioactive

Standard Preparation), 3000/03 (Analysis of EPA Cross-Check Samples),

1000/04 (Administration ,of Interstation Cross-Check Program). The 2000 and

and 4000 Series Procedures, listed in the preceeding paragraph, were also

reviewed. Available EPA Cross-Check Program data, compiled during calendar

year 1981 was reviewed and discussed with a cognizant licensee representa-

tive.

Inspection disclosed that the analytical quality control program was

~

consistent with the guidance defined in Section C.6 of Regulatory Guide 4.15

(December 1977).

Inspection further disclosed close and consistent

agreement of licensee cross-check analytical results with those of EPA in

the assigned cross-check program. The inspector had no questions regarding

this item,

7.

Status Review of Radiological Environmental Monitoring Program

a.

Technical Specification 3/4.12 defines all requirements for the

radiological environmental monitoring program which includes the

following:

(1) specific sampling / analytical 1 parameters and. schedule _s; _

(2) reporting levels for specific radionuclide concentrations in the

environment associated with plant operation; (3) maximum values of

lower limits of detection (LLD's) for required . analytical parameters;-

(4) land use census; (5) interlaboratory comparison program discussed

in paragraph 6, above.

b.

Inspection included a review of program organization and management

control to assure that all program requirements were implemented as

required by the technical specifications.

Inspection also included the

following:

(1) a review of sampling records and data compiled during

the 1981 calendar year; (2) inspection of all air particulate

monitoring stations and verification of required quarterly calibration

of the nonitors inspected; (3) inspection of all surface and service

water monitoring stations; (4) inspection of ten randomly selected TLD

stations (excluding those TLD's located at air particulate /radiofodine

monitoring stations); (5) review of land census data for calendar year

1981, (6) inspection of milk sampling stations.

c.

Inspection disclosed that the radiological environmental monitoring

program was adequately managed to assure implementation of the

technical specification requirements.

Inspection further disclosed

'

that environmental sanpling and radiochemical analysis of samples

collected were consistent with all requirements defined in Section

3/4.12 of the Technical Specifications. There were no questions

regarding this item,

www

r

--

s-

4m.

'

.

..

.

5

8.

IE Bulletin 81-03

The inspector reviewed the licensee's response to IE Bulletin 81-03 (Flow

Blockage of Cooling Water to Safety System Components by Corbicula Sp.

(Asiatic Clam) and Mytilus Sp. (Mussel)). Although no fouling has occurred

as a consequence of clam infestation, the licensee discovered Corbicula Sp.

(Clams) during preoperational testing of the Fire Protection Sy sten' in

August of 1978.

The licensee has implemented periodic monitoring of the

Nuclear Service Water System and performance tests are conducted monthly to

insure adequate flow to the Nuclear Service Water Pumps.

In view of the

absence of clans in the subiect system, no control measures have been

implemented to date. In the case of the Fire Protection System, chlorine is

periodically added to the system to maintain a chlorine residual lethal to

young (non shelled) clams. There were no questions regarding this item.