ML20042A484
| ML20042A484 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 03/12/1982 |
| From: | Davidson D CLEVELAND ELECTRIC ILLUMINATING CO. |
| To: | Tedesco R Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 8203230481 | |
| Download: ML20042A484 (8) | |
Text
.
T il E C L E V E l A N D E L E C T !!! C I L L U M ! N Ai! N G C O M P A N
P o DOX 5000 e CLEVEL AND. OHIO 44101 e TELEPHONE (216) 622-9fl00 m ILLUMINATING BLOG e
55 PUBLICSOUARE
'N I ' C"I# " '"
Dalwyn R. Davidson V4E PHf 5HJE NY 5 f S TE M [NGIN(IHING AND CONS THUCTiON tg \\
D 9
March 12, 1982 s
e } ?,)
av U i@, g jgg'd.r Q Mr. Robert L. Tedesco Assistant Director for Licensing
,Py gru ;
$ g\\. c y %" W*
mX0 Division of Licensing
//
U. S. Nuclear Regulatory Commission Washington, D. C.
20555
/;3
.Co Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Additional Inforn.ation -
Initial Test Program
Dear Mr. Tedesco:
In our response to question 640.41 regarding instrument air pre-operational test, which we submitted to you on October 30, 1981, we committed to inform you as to the extent to which Perry will comply with items c8, c9, and cl0 of Regulatory Guide 1.80 (June 1974) by March 15, 1982. This letter and its attachment is submitted to provide such a response.
It is our intention to incorporate this response in a subsequent amendment to our Final Safety Analysis Report.
Very Truly Yours,
$+7 #
Dalwyn R. Davidson Vice President System Engineering and Construction DRD: mlb cc:
Jay Silberg, Esq.
John Stefano Max Gildner 3 00/
s l
08R*DOhgof9y}jO 30 es A
A PDR
TABLE 1.8-1 (Continued)
Regulatory Guide (Rev. ;RRRC Category)
Degree of Conformance Reference 1.78 - (Revision 0 - 6/74;RRRC Cat. 1)
Assumptions for evaluating the PNPP design conforms to this guide.
2.2.3 habitability of a nuclear power plant control room during a postulated hazardous chemical release 1.79 - (Revision 1 - 9/75;RRRC Cat. 1) i Preoperational testing of emergency core Not applicable to the PNPP design.
cooling systems for pressurized water reactors
'o>
1.80 - (Revision 0 - 6/74;RRRC Cat. 4) e Preoperational testing of instrument PNPP conforms to this guide for the preoperational 14.0 air systems testing of the P57 safety related instrument air system with the following clarification:
Item C7 test and check requirements will be accomplished during the served equipment's system preoperational phase testing.
g PNPP conforms to this guide for the acceptance h
't'esting of,the PS2 non-safety related instrument air system with the following clarifications:
1)
Item C7 test and check requirement-will be accomplished during the served equ.pment's system preoperational phase testing.
TABLE 1.8-1 (Continued)
Regulatory Guide (Rev.;RRRC Category)
Degree of Conformance Reference 1.80 - (Revision 0) (Continued) 2)
Items C8, C9 and C10 will be accomplished by placing the valves to be tested in their normal operating position for simulation of the instrument air pipe break on selected system branches. Similarly, valves to be tested will be placed in their normal operating position g
for =imulation of instrument air pipe
-c freezing / plugging on the selected system g
branches. The response of valves to a loss of air pressure when placed in a position other than failed as described in Item C8a vill be verified, where required, on an individual component basis.
F 1.81 - (Revision 1 - 1/75;RRRC Cat. 1)
?g Shared emergency and shutdown electric PNPP design conforms to this guide for Class 1E 8.1.1 4
systems for multi-unit nuclear power power systems. Each unit has separate, plants independent electric systems capable of supplying ESF and safe shutdown loads, assuming a single failure and loss of offsite power.
1.82 - (Revision 0 - 6/74;RRRC Cat. 4)
Sumps for emergency core cooling and Not applicable to the PNPP design.
containment spray systems t
1.83 - (Revision 1 - 7/75;RRRC Cat. 4)
Inservice inspection of pressurized Not applicable to the PNPP design.
water reactor steam generator tubes 1.84 - (Revision 16 - 11/78;RRRC Cat. 1)
Design and fabrication code case PNPP conforms to this guide.
5.2.1 acceptability - ASME Section III Division 1
i 640.41 from our review of Sections 1.8 and 9.3.1.4 it is not clear to l
(14.2.12.1) us as to what extent you intend to comply with Regulatory Guide 1.80 for the instrument air preoperational test.
Provide a test description for the instrument air test.
Response
Clarification of the extent to which PNPP will comply with Regulatory Guide 1.80 is provided in revised Table 1.8-1.
The Safety Related Instrument Air System (P57) preoperational test description is provided in revised Section 14.2.12.1.48.
Testing of the Non-Safety Related Instrument Air System and the Non-Safety Related Instrument Air System Loss of Instrument Air Test will be accomplished according to the Acceptance Test Program discussed in Section 14.2.12.3.
A description of the Non-Safety Related Instrument Air System Acceptance Test and the Non-Safety Related Instrument Air System Loss of Instrument Air Acceptance Test are included.
NON-SAFETY RELATED INSTRUMEdT AIR ACCEPTANCE TEST a.
Test Objectives 1.
Verify the instrument air (IA) system is capable of supplying air at the required flow, pressure, temperature and dew point.
2.
Verify proper operation and control for the manual and automatic modes of operation of the IA compressor.
3.
Verify proper operation of redundant components.
Q&R 14.2-57
.=
I b.
Prerequisites 1.
Instrument calibration complete.
2.
Electric power available.
3.
Required support s'ystems are available.
4.
Individual initial checkout and run-in component tests are complete.
5.
Cleanliness requirements have been verified during initial checkout and run-in testing.
c.
Test Procedure 1.
Demonstrate that the IA co.npressor will supply instrument air at the required design flow, pressure and temperature.
2.
Demonstrate that the IA compressor functions properly in the manual and automatic modes of operation.
3.
Demonstrate that the failure or loss of function of redundant components will not prevent proper operation of the others.
4.
Demonstrate proper operation of the IA dryers to supply air at the required dew point.
d.
Acceptance Criteria 1.
IA compressor flow, pressure and temperature requirements are met.
2.
IA compressor requirements for manual and automatic operation are met.
I Q&R 14.2-58
3.
IA dryers air dew point requirements are met.
4.
Requirements for. failure or loss of furetion of redundant components so as to not jeopardize proper operation of the other components are met.
NON-SAFETY RELATED INSTRUMENT AIR SYSTFM LOSS OF INSTRUMENT AIR ACCEPTANCE TEST
- n. Test Objective 1.
Upon sudden depressurization (simulated pipe break) of the instrument air supply verify that the air operated components fail from their normal operating position in a man"cr maintaining continued capability to provide system safety functions.
2.
Upon slow depressurization (simulated pipe plugging by freezing) of the instrument air supply verify that the air operated components fail frot their normal operating position in a manner maintaining continued capability to provide system safety functions.
- b. Prerequisites 1.
Instrument calibration and initial checkout and run-in testing is complete on pneumatic operated components to be tested.
l r
2.
The Instrument Air System and required support systems are available to I
supply instrument air to the components being tested.
I
- c. Test Procedure l
1.
Pressurize the instrument air header.
2.
Position the components being tested in the test branch to their normal operating position and record position on data sheet.
Q&R 14.2-59
3.
Isolate the instrument air branch to be tested.
4.
a.
Rapidly depressurize the test branch and record the failed position of the components being tested.
b.
Monitor system responses and interaction and record any unexpected characteristics.
5.
After all the component's failed positions have been recorded, open the isolation valve to the test branch to re pressurize.
6.
If the components do not return to their normal operating position, re position them (in the test branch) the same as in step 2 and record position.
7.
Isolate t;ie test branch.
8.
a.
Slowing depressurize the test branch and record the failed position of the components being tested.
b.
Monitor system responses and interaction and record any unexpected characteristics.
9.
Proceed to the next branch to be tested and perform steps 1 through 8.
10.
After all branches have been tested, return system to the required
- status,
- d. Acceptance Criteria 1.
Upon rapid depressurization of the instrument air supply, the requirements for the air operated components to fail in the designed position are met and no unexpected system interactions are observed.
Q&R 14.2-59a
2.
Upon slow depressurization of the instrument air supply, the requirements for the air operated components to fail in the designed position are met and no unexpected system interactions are observed.
l l
1
\\
i l
(
l Q&R 14.2-59b l
i