POWER AUTHORITY OF THE STATE OF NEW YORK 10 CoLUMeus CIRCLE NEW YORK. N. Y. loo 19 2ia i as7.szoo o r oac,c,v,m a,a a r inverare e,n. wi e.. onic a

' "" *ic"U U.."c Pat t e D$ NT-PROCE Du m E S a onor c.iucaLL.

VIC E C Ma lm es A N JOSEPH R C IEDER

  • ago,i,=,,acin, alcuano u r ev u ~

most RT t. MILLONZ8 LEROY W. SINCL AIR March 5, 1982

', ;,a, ;,'",,* "> o = ~ '

rnicanicx a cuana JPN-82-26

  • "'c"

'" ",^'."./.""........,

Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. Domenic Vassallo, Chief Operating Reactors Branch No. 2

\\ 9 Division of Operating Reactors g

Subject:

James A. FitzPatrick Nuclear Power Plant O

U "i"i-Ij Docket No.

50-333 2

d Implementation of General Electric Service {j hy IO32 Information Letter (SIL) No. 299, Including tE7-

.v Supplement 1

\\a Rv NN

References:

1.

GE SIL 299, "High Drywell Temperature Effection:'

Reactor Vessel Water Level Instrumentation," A ?

July 26, 1979.

2.

GE SIL 299, Supplement 1, "High Drywell Tempera-ture Effect on Reactor Vessel Water Level Instru-mentation," September 1980.

3.

Lei.ter dated February 1, 1982 from T.J. Dente (Chairman, BWROG) to BWROG Primary Representa-tives regarding January 27, 1982 meeting between BWROG and NRC.

Dear Sir:

The Power Authority has recently become aware of a ueeting held January 27, 1982 between the BWR Owners Group (BWROG) and the NRC where the question was raised whether all operating BWRs had implemented the recommendations of GE's SIL 299 and Supplement 1 to SIL 299, (References 1 and 2, respectively).

Reference 3 notified us of the NRC's concerns expressed in this meeting and suggested that licensees of operating BWRs commit to comply with the recommendations of SIL 299 including Supplement 1.

According-ly, the Authority submits the following information.

/

00 SIL 299 made three recommendations:

f 1.

Review reactor water level instrumentation and the

/g of fects of high drywell temperature; 8203090264 820305 PDR ADOCK 05000333 p

PDR

1

-2' e

2.

Provide guidance to operators on the use of level instrumentation during conditions of high drywell ambient temperatures and rapid depressurization; and 3.

Modify level instrumentation scale readings to make control room operators aware of the effects of drywell temperature on level instrumentation.

The Authority completed the recommendations of SIL 299 in December 1979, including:

1.

A revised, more conservative, triple-low water limit switch setpoint (which initiates core spray, LPCI, I

emergency diesel generators and ADS logic) was estab-lished; 2.

Operators received supplemental training as part of the Requalification Program including required reading, classroom instruction, control-room walk-through of emergency procedures; and 3.

In lieu of modifying level instrument scales, a graph relating correct indicated level to drywell ambient temperature was prepared and is readily accessible to operators.

Supplement 1 to SIL 299 did not provide further recommenda-tions but emphasized the importance of implementing the recom-mendations of the original SIL while supplying additional infor-mation on the behavior of cold-leg level instrumentation under high drywell temperature conditions.

No further action was re-quired as a result of Supplement 1.

If you have any questions, do not hesitate to contact us.

Very truly y*ours',

C\\_J. [.Bayne

\\

Senio Vice President Nuclear Generation JPB/JE:mp cc:

Mr. J.

Linville Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Ron Barton United Engineers & Constructors, Inc.

30 S.

17th Street Philadelphia, PA 19101

.