Interim Deficiency Rept Re Defect in Starting Air Sys Check Valve.Final Rept Date Changed to 820528.Delay Due to Investigation Not Being Completed Until 820430
ML20041D418
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 02/25/1982
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8203050312
Download: ML20041D418 (1)


Text

THE CLEVELAND ELECTRIC ILLUMIN ATING COMPANY P O BOX 5000 m CLEVELAND. OHIO 44101 e TELEPHONE (216) 622-9800 m ILLUMINATING BLOG e 55 PUBLIC SOUARE Sewing The Best Location in the Nation D1!wyn R. Davidson v,ce PResioENT February 25, 1982 4 to SYSTE M ENGINEERING AND CONSTRUCTION g 2

Mr. James G. Keppler Director, Region III g.

NEC$1VED 1L "g 4 0 5 tgg b S -

Office of Inspection and Enforcement ~

U.S. Nuclear Regulatory Commission 799 Roosevelt Road V #

Glen Ellyn, Illinois 60137 g RE: Perry Nuclear Power t:: D Docket Nos. 50-440; 50-4 Standby Diesel Generators l Model DSRV16: Potential '

Defect in Starting Air System Check Valve [RDC 43(82)]

Dear Mr. Keppler:

The interim report concerning subject deficiency states that our Final Report is scheduled to be submitted to ycur office by March 1, 1982.

As discussed with Mr. J. H. Neisler of your office on February 23, 1982, our Final Report is now scheduled to be submitted by May 28, 1982.

We were not if ted by Transamerica Delaval, the supplier of the diesel generators, that they are still working with Wm. Powell Company, supplier of the questionable starting air : heck valve, on the investigation of the depth of the problem.

Delaval now e3timates that the report for their investigation, including recommended corrective action, will be completed, by April 30, 1982.

If there are any questions, please do not hesitate to call.

Sincerely, kpf Dalwy R. Davidson Vice President System Engineering and Construction DRD:pab cc: M. L. Gildner - NRC Resident Inspector Perry Nuclear Power Plant Director Office of Inspection and Eaforcement U.S. Nuclear Regulatory Coumission Washington, D.C. 20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch ]E f } kl $

Washington, D.C. 20555 8203050312 820225 PDR ADOCK 05000440