Interim Deficiency Rept Re Undocumented Section of Pipe & Welds in Gas Stripper in Violation of ASME Code.No New Info to Be Reported at This Time.Next Rept by 820407
ML20040F379
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 01/28/1982
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Faulkenberry B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, ANP-20011, NUDOCS 8202090136
Download: ML20040F379 (2)


Text

--

1 Docket Nos. 50-528/529/530 50 55(e) Report SLFMIM 1.MMMIla3:D SL'IllHWHUDIl (DDTif&"2fTf P. O. D O X 216 6 6 PHOENIX. ARIZON A 85036 January 28, 1982 I

ANPP-20011-CHD/ JAR f

e n

U. S. Nuclear Regulatory Commission p

co' Region V Creekside Oaks Office Park RECEplM p

1350 Maria Lane - Suite 210 FEB 8 1982 5 Z Walnut Creek, California 94596-5368 D

$$Qfp'" D Attention:

Mr. B. H. Faulkenberry, Chief Reactor Construction and Tc; Engineering Support Branch

//

Subject:

Time Extension for Report - DER 81-39 A 50.55(c) Potentially Reportable Deficiency Relating to Unit 1 Gas Stripper by CE Has Undocumented Section of Pipe and Welds in Violation of ASME Code File: 82-019-026 D.4.33.2

Reference:

(A) Telephone Conversation between J. Eckhardt and l

G. Duckworth on November 12, 1981 (B) ANPP-19646, dated December 9, 1981 (Interim Report)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A) and an Interim Report was transmitted by Reference (B). At that time, it was estimated that a Final Report would be available by Janu-ary 29,1982.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by April 7,1982, when a complete report will be submitted.

There is no new information or change to the Interim Report-at this time.

Very truly y urs.

i dP^ist CLQ ALd i

E. E. Van Brunt, Jr.

APS Vice President u J :l dj l - p g *; q Nuclear Projects ANPP Project Director f

EEVBJr/GHD:skc u.

l

'SeeAttachedPag[ENO3d cc:

l bM2090136 820128 I' l F.5. ADOCK 05000528 S

PDR Q.)...

U. S. Nuclear Rigulatory Commission Attention:

Mr. B. H. Faulkenberry, Chief ANPP-20011-GHD/BSK January 28, 1982 Page 2 cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 J. A. Roedel D. B. Fasnacht G. C. Andognini F. W. Hartley J. M. Allen A. C. Rogers B. S. Kaplan W. E. Ide J. Vorces J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen R. L. Greenfield Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 Ms. Patricia Lee Hourihan 6413 South 26th Street Phoenix, Arizona 85040

.-