Responds to NRC Re Violations Noted in IE Insp Repts 50-508/81-17 & 50-509/81-17.Corrective Actions: Nonconformance Rept Redispositioned to Provide Directions for Resetting Containment Penetration Bellows Assemblies
ML20040E754
Person / Time
Site: Satsop
Issue date: 01/20/1982
From: Leddick R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Faulkenberry B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20040E749 List:
References
GO3-82-055, GO3-82-55, NUDOCS 8202050315
Download: ML20040E754 (3)


Text

,

o Washington Public Power Supply System Box 1223 Elma, Washington 98541 (206)482-4428 Docket Numbers 50-508 and 50-509 January 20, 1982 G03-82-055 U. S. Nuclear Regulatory Commission, Region V Office of Inspection and Enforcement 1450 Maria Lane, Suite 260 Walnut Creek, California 94596-5368 Attention: Mr. B. H. Faulkenberry Chief, Reactor Construction Projects Branch

Subject:

NRC INSPECTION AT WNP-3/5 ITEM 0F NONCOMPLIANCE IE REPORT NO. 50-508/509/81-17/05

Reference:

NRC Letter, dated December 17,1981, Mr. B. H.

Faulkenberry to Mr. R. S. Leddick, NRC Inspection at Washington Nuclear Project Nos. 3 and 5, (WNP-3/5).

The referenced letter reported the results of the NRC inspections conducted by Mr. D. P. Haist on October 5-9 and 26-30,1981, of acti-vities authorized by NRC Construction Permit Nos. CPPR-154 and 155.

One Item of Noncompliance (81-17/05) concerning Ebasco's failure to follow conditional release procedures was identified.

Attached is a report detailing corrective / preventive actions taken for the subject noncompliance. As a result of achieving full compli-ance on January 15, 1982, the Supply System considers the violation to be satisfactorily resolved.

Sho ' d you have any questions or desire further information, please c tk me directly.

. S. Leddick (1000)

Program Director, WNP-3/5 DRC/tt j]

Attachment g

h

.=

cc:

J. Adams - NESCO 6,~

M m

D. Smithpeter - BPA y

m

' # ;-5 Ebasco - New York O

o WNP-3/5 Files - Richland 8202050315 820129 PDR ADOCK 05000500 G

PDR 3

Page 1 ATTACHMENT I Nuclear Regulatory Commission - Noncompliance (50-508/81-17/05) 10CFR50, Appendix B, Criterion V, states:

" Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

Instructions, procedures, or drawings shall include appropriate quantitative or qualita-tive acceptance criteria for determining that important activities have been satisfactorily accomplished."

WPPSS Quality Assurance Requirement No. QAR 2.1, Rev.1, Paragraph 3.5.4 states:

" Representatives of the CM at the Project Site shall be in com-pliance with the Supply System-approved CM Quality Assurance Program and the applicable Project interface requirements."

Ebasco Project Site Procedure No. MM-ll-10, Rev. O, " Conditional Release of Material, Equipment for Construction," Paragraph 3.2.3 states "If con-ditional release of the item modifies the disposition or evaluation of the NCR, (originator) initiates change to correct NCR in accordance with PSP-QA-7-3 (Reference 4.1)."

Contrary to the above, Conditional Release Request No. 54-06 was issued on June 4,1981 to release fourteen (14) nonconforming containment pene-tration assemblies for partial installation prior to completion of dis-position of nonconformance report no.12966 in accordance with vendor procedure no. 3240-36529, Rev. 1.

Vendor procedure no. 3240-36529 spe-cifies methods for resetting containment penetration bellows assemblies prior to any installation activities.

Nonconformance report no.12966 was not revised to provide engineering direction to the installing con-tractor to enable resetting of the containment penetration bellows assem-blies after partial installation.

This is a Severity Level V Violation (Supplement VI) applicable to Unit No. 3.

Corrective Actions Taken The following corrective actions have been taken to assure compliance with 10CFR50, Appendix B, Criterion V:

1.

Engineering has redispositioned the NCR to provide explicit direction to the installing Contractor for resetting of the containment pene-tration bellows assemblies after partial installation.

2.

Engineering has rewritten the vendor's procedure to describe the meth-od of checking bellows assembly alignment after partial installation and the method for resetting as necessary.

This procedure has been made a part of the installing contractor's installation procedure.

Action Taken To Prevent Recurrence 1.

The Condition Release Originator has been re-instructed to follow Pro-cedure No. MM-ll-10, Paragraph 3.2.3-NOTE and to initiate revision to

Page 2

_,, ~ >

Action Taken To Prevent Recurrence (Continued) the NCR whenever any change to the disposition occurs from the writing

~~

of a Conditional Release.

2.

Engineering has been instructed to promptly revise any NCR issued to the installing Contractor whenever there is a change to the disposi-tion.

Date of Full Compliance 1.

The NCR was redispositioned on December 2,1981.

2.

The Engineer's approved procedure for resetting of bellows on par-tially installed mechanical penetrations was incorporated into the installing contractor's installation procedure on December 11, 1981.

3.

Actions taken to prevent recurrence were completed and documented on January 15, 1982.