ML20039G940

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-267/81-26 on 811101-30.Noncompliance Noted: Emergency Diesel Generator Sets 1A & 1B Removed from Svc W/O Prior Demonstration of Operability of Alternate Set & Technician Failed to Wear Pocket Dosimeter
ML20039G940
Person / Time
Site: Fort Saint Vrain 
Issue date: 12/18/1981
From: Dickerson M, Plumlee K, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20039G932 List:
References
50-267-81-26, NUDOCS 8201190324
Download: ML20039G940 (8)


See also: IR 05000267/1981026

Text

.

.

APPENDIX B

,

U. S. NUCLEAR REGULATORY C0fSIISSION

REGION IV

NRC Inspection Report: 50-267/81-26

License DPR-34

Docket: 50-267

Licensee: Public Service Company of Colorado

P. O. Box 840

Denver, Colorado

80201

Facility Name: Fort St. Vrain Nuclear Generation Station

Inspection at: Fort St. Vrain Site, Platteville, Colorado

Inspection Conducted: November 1-30, 1981

'

Inspectors:

3 [/A/

M

/2 -/F -3/

M. W. Dickerson, Senior Resident Reactor Inspector

Date

ff

N&

/2 -/1- W

G. L. Plumlee III, Resident Reactor Inspector

Date

Approved By:

N

/2-/F4/

T. F. Westerman, Chief, Reactor Project Section No. 1

Date

Inspection Summary

Inspection conducted November 1-30,1981 (Recort: 50-267/81-26)

Areas Inspected: Routine, announced inspection of Surveillance; Maintenance;

Operational Safety Verification; and Review of Periodic and Special Reports.

The inspection involved 115 insoection-hours on site by two NRC inspectors.

Results: Within the four areas inspected, three violations were identified

(Failure to adhere to Technical Specifications, Paragraph 2.A, failure to

follow procedures, Paragraphs 2.B. and 4. A. )

8201190324 811222

PDR ADOCK 05000267

G

PDR

_

_

.

.

2

?

1.

Persons contacted

T. Borst, Radiatica Protection Manager

M. Block, Superintendent of Operations

R. Craun, Site Enaineering Supervisor

M. Deniston, Shift Supsrvisor

D. Evans, Shift Suoervisor

M. Ferris, QA Technical Support Supervisor

W. Franek, Nuclear Site Engineering Manaaer

W. Franklin, Shift Supervisor

C. Fuller, Technical Services Engineering Supervisor

J. Gahm, QA Manager

E. Hill, Operations Manager

D. Hood, Shift Supervisor

J. Jackson, OA/QC Supervisor

J. Liebelt, Senior Maintenance Supervisor

,

M. McBride, Technical Services Manager

F. Novachek, Technical Advisor

T. Orlin, Superintendent 0A Services

T. Schleiger, Health Physics Supervisor

L. Singleton, Superintendent Operations QA

r

D. Warembourg, Manager Nuclear Production

R. Webb, Maintenance Supervisor

The NRCinspectors also coittacted other plant personnel including

reactor operators, maintenance men, electricians, technicians and

'

administrative personnel.

2.

Operational Safety Verification _

The NRC inspector reviewed licensee activities to ascertain that

the facility is being operated safely and in conformance with

regulatory requirements, and the licensee's manangement control

system is effectively discharging its responsibilities for continued

safe operation. The review was conducted by direct observation

of activities, tours of the facility, interviews and discussion

with licensee personnel, independent verification of safety system

status and limiting condition for operations, and review of facility

records.

Included in the inspection were observation of control room

activities, review of operational logs, records, and tours of

accessible areas. Logs and records reviewed included:

Shift Supervisor Logs

.

Peactor Operator Logs

.

. - .

.

. . - .. .

-,

,

.

..

. . . .

1

3

Equipment Operator Logs

.

Auxiliary Operator Logs

.

Technical Specification Compliance Logs

.

Operations Order Book

.

Operations Deviations Reports

.

Clearance Log

.

Temporcry Configuration Reports

.

Plant Trouble Reports

.

During tours of accessible areas, particular attention was directed

to the following:

Monitoring Instrumentation

.

Radiation Controls

.

Housekeeping

.

i

Fluid Leaks

.

.

Piping Vibrations

.

Hanger / Seismic Restraints

.

Clearance Tags

.

Fire Hazards

.

Control Room Manning

.

Annunciators

.

The operability of selected systems or portions of systems were

verified by walkdown of the accessible portions. The NRC inspector

verified the operability of the Turbine Generator and Auxiliaries System.

,

No problems were identified during the system walkdown.

,

l

,

t

-

,_ ._.

m

,

-, , - - , -

. . , _

-

._ ___

- __

.

-_ _

4

A.

Removal of Diesel-Generators From Service

<

On October 20, 1981, at 9:50 a.m. MST, the licensee removed

i

the 1A Emergency Diesel-Generator set from service to change

the coolant on the diesel engines. lA was returned to service

,

that same day at 3:45 a.m. MST. Also, on October 21, 1981,

at 7:40 a.m. MST, the licensee removed the 1B Emeraency Diesel-

Generator set from service for the same reason. 1B was returned

to service that same day at 10:30 a.m. MST. However, neither

Emergency Diesel-Generator set was started immediately prior

,

to removal from service of tue alternate diesel-generator set

as required by Technical Specifications LC0 4.6.1.d).

Technical Specification LC0 4.6.1.d) requires that the reactor

not be operated at power unless both diesel-generator sets are

operable. However, they can be removed from service one at

.

a time providing the alternate set is verified operable immedi-

'

ately prior to the removal. Since the reactor was at power

this constituted a violation of the Technica? Specification.

(8126-01)

The violation was found by the licensee and reported in Report-

able Occurrence 81-066, dated November 6,1981. This violation

is similar to that reported in IE Report 81-24 and in Reportable

Occurrcr.ce 81-058, dated October 9,1931.

The NRC inspector's concern over the fact that the corrective

action addressed in Reportable Occurrence 81-066 was essentially

the same as that addressed in Reportable Occurrence 81-058, and

the licensee's management controls that permitted a reoccurrence

of this type of violation was brought to the licensee's attention.

The licensee's evaluation of this problem resulted in the commit-

ment to change all the licensee's Standard Clearance Points forms

related to the equipment addressed in LCO 4.6.i to reflect the

requirements o' LC0 4.6.1 prior to taking the equipment out-o#-

service and prior to placing it back in service.

On November 30,1981, at 10:45 a.m. MST, the NRC inspector

verified that the standard clearences for the 1 A and 1B Emergency

Diesel Generator sets had been changed to incorporate operability

verifications as required by LCD 4.6.1.

The NRC inspector also

identified two other System 92 Standard Clearance Points forms

which would yield a diesel generator set inoperable that did not

contain this new change. This was discussed with the licensee

who concurred that the change was necessary and would be made.

The NRC inspector has no further questions in this area.

,

1

~

l

.

.

i

5

.

B.

Radiation Work Permit Requirements

!

On November 16,1981, at 8:45 a.m. MST, during a tour of the

reactor building, the NRC inspector reviewed Radiation Work

Pe'rmit (RWP) 02861, issued to control work currently in progress

'

inside the Hat Service Facility (HSF) and dctermined that a

1

Health Physics (HP) technician performing surveys inside the

s

HSF had failed to log in and was not wearing a pocket dosimeter

or film badge on the outside of his Anti-C's as were the other

personnel inside the HSF. Discussions with HP supervision

verified that the technician did have his film. badge underneath

his Anti-C's but no pocket dosimeter was worn as required by

the RWP. Administrative Procedure P-1 requires that each

,

assigned employee log in and cut of the RWP and comply with the

'

RWP requirements.

The NRC inspector discussed the above with the licensee and

informed the licensee that failure to follow procedures which

are Technical Specification requiremer.ts is considered a

'

violation. (8125-02)

"

The NRC inspector had no additional c,uestions in thi

'rea.

.

l

3.

Surveillance (Monthly)

I

The NRC inspector reviewed all aspects of surveillance testing involving

l

safety-related systems. The review included observation and review

relative to Technical Specification requirements. The surveillance

j

tests reviewed and observed were:

SR 5.8.1d-W

Radioactive Gaseous Effluent Vent Monitor System

Functional Test

SR 5.2.6-X

Plateout Probe Evaluation

i

SR 5.2.la-A

PCRV Rupture Disk and Safety Valve Test

SR 5.4.5-A2

PCRV Cooling Water Flow Scan Calibration

SR 5.4.1.1.6.c-R

Primary Coolant Moisture Scram Calibration

!

No violations or deviations were identified.

4

Maintenance (Monthly)

The NRC insoector reviewed records and observed work in progress to

ascertain that the following maintenance activities were being con-

ducted in accordance with approved procedures Technical Specifica-

tions, and appropriate Codes and Standards. The following maintenance

i

activities were reviewed and observed:

I

,

..

.

.

,

i

I

6

,

!

Steam Generator Module B-2-3 Penetration Modifications

CWP 81-250/CN1427

Isolation of Penetration B-2-3

CWP 81-251

Remove V-ll39 and Associated Piping and

Valves from Eystem

CWP 81-252/CN 1427A Steam Generator B-2-3 Interspace Discharge

Piping Nodification

<

CWP 81-253/CN 1427B Steam Cenerator B-2-3 Interspace Discharge

Piping Modification Add Tailpiece to V-1139

r

Loop Split Modification

CN 1314

Buffer Helium Piping

CN 1315

System 23/24 Valve Station

CN 1313

Radiation Monitors

CN 1321

North Stairs Modification

CN 1323

Main Control Board Modifications

CN 1322

Electrical Cable Routing

CN 1324

Process Control Equipment

Shutdown Maintenance

i

PTR 11-130 Repair Control Rod Drive (CRD 17) in accordance

with MP 12-6, " Maintenance and Repair of CRD

Orificing Assemblies," and RP 5, " Control Rod Drive

Checkout"

,

PTR 11-145 Remove Containment Tank Cover T-1101

PTR 11-202 Repair Hot Reheat Steam Line (B-2-1) in accordance

,

with MP-lCO, " General Welding Procedures"

PTR 12-257 HV-2246 Repair in accordance with MP-4, " Maintenance

and Repair of Velan Valves," MP-5, " Valve Packing

7

Procedure," and MP-39, " Installation and Maintenance

'

of Limitorque Valve Operators and Retork Valve Operators"

PTR 5-9

Remove P-3105 for Repair in accordance with MP-105,

" General Pump Removal and Installation," and MP-103,

" Electric Motor Removal, Repair, and Replacement

Procedure"

i

!

t

,

i

i

'

.

.

_

_

-7-

CWP 81-ll3/CN 1355A Installation of Isolation Valves on Stem

Generator Modules

A.

Steam Generator B-2-3 Modification

On Ncvember 3, 1981, at 6:30 a.m. MST, with the plant at approximately

8% reactor power,'the NRC ir,spector performed a walkdown of the work

previcusly rompleted on the steam gentrator (5/G) penetration modifi-

cation.

The i4RC inspector determined that one hydraulic support

(snubber CRS-951) required to be installed on the relief valve

tailpiece per CWP 81-253, and one pipe *,upport (hanger) required to

be installed on the helium penetration interspace ring header per

CWP 81-252, were not installed.

The question as to the system's

operability was immediately brought to the licensee's attention.

The licensee initiated an engineering safety evaluation and made

no further power increases until both the snubber and hanger had

been installec!.

The results of the engineering evaluation indicated that the hydraulic

snubber was not required to meet the system's seismic qualification,

but that the mechanical hanger was required.

From this evaluation

the licensee determined that the S/G penetration interspace pressuri-

zation portion of the PCRV Auxiliary Piping System, Loop II penetration

ring header, was not normal in that the system was not operational at

the time the equipment clearance was returned and the system returned

to operation. Administrative Procedure P-2, " Equipment Clearances

and Operation Deviations," requires the return of the equipment

clearance only when the equipment has been restored to normal

conditions.

l

A review by the NRC inspector of the Change Notices and the Control

Work Permits (CVP) that authorized and documented the modification

indicated that in CWP 81-252, the QA/QC inspection verification

step for the installation of the pipe hanger on the Loop II helium

penetration interspace ring header had been signed off. This step

had been classified by QA/QC as a Witness Point (WP) and was required

l

to be signed after verification by the Quality Control Technician

that the work was performed correctly. However, at the time this

verification was made, the pipe hanger had not been installed.

The NRC inspector discussed the above with the licensee and inform-

ed the licensee that failure to follow procedures, which are Technical

Specification requirements, is considered a violation (8126-03).

During this discussion, the licensee informed the NRC inspector

that communication errors within the licensee's management involved

in the performance of this modification was the underlying cause,

and that changes to the licensee's plant modification program would

be necessary to mitigate a possible reoccurrence.

The inspector had no additional questions in this area.

-

-

-

4

....

. . .

.

.

.g.

B.

Loop Split

During an inspection of replacement parts and materials being used

in the loop split modification, the NRC inspector performed

traceability verifications on electrical cables used on safety

related equipment. The following cable reals located inside the

reactor building were traced to a specific Purchase Order (PO)

number and Direct Change Requisition (DC) assigned to a specific

change notice for the loop split modification.

~

Reel No.

Item No.

DC No.

P0 No.

'

042065

1733177

85949

N1702A

8CJ045

1733175

73961

N2262A

86J068

1733656

73963

N2262C

No violatio a or deviations were identified.

5.

Report Reviews

,

The NRC inspector reviewed the following reports for content, reporting

requirements and adequacy:

Monthly Operating Information Report, October 1981

Monthly Operations Reports, October 1981

i

Twentieth Startup Repart, May 23, 1981, through August 22, 1981

i

No violations or deviations were identified.

6.

Exit Interview

!

Exit interviews were conducted at the end of various segments of this

!

inspection with Mr. D. W Warembourg, Manager, Nuclear Production, and/or

other members of the Public Service Company staff. At the interviews, the

inspector discussed the findings indicated in the previous paragraphs.

f

The licensee acknowledged these findings.

1

l

l

'

i

.

.